Winston Plywood Weekly Update 12-11-15
Site Utilities:
· Installed electrical duct bank from main feeder to RTO
Buildings:
· Continued installing wall sheets and trim-out on Building 1
· Continued installing wall sheets on east side of Building 3
· Continued installing trim material around louvers on Building 3
· Completed trim-out on roof framing for wall sheets on Building 6
· Installed upper wall sheets and translucent panels on Buildings 7, 8, & 11
· Continued work on mezzanine deck (installed concrete anchors) in Building 8
· Continued punchlists on Buildings 4, 6, 6A, 7, 8, & 11
· Installed interior wall sheets between Buildings 9 & 10
Fire Protection:
· Continued installing hose station piping
· Continued installing drum-drips and drains for sprinkler systems
· Continued installing sprinkler systems in Buildings 7, 8, and 11
· Placed concrete foundation for fire pump building
Electrical:
· Continued electrical rough-in for lighting and miscellaneous electrical services
· Continued installing lighting fixtures in Buildings 2, 4, 5, 9, & 10
· Continued installing cable tray throughout the plant
· Continued pulling primary electrical feeders to south electrical rooms
· Continued running conduit for process equipment at green-end, dryers, presses, and dry-end
· Completed installing primary underground service to transformers 1-4 on south end of building
· Continued installing underground service to RTO transformer pad; Placed concrete on electrical duct bank to RTO
· Began testing on underground service to transformers and began connections at switchgear and transformers
Racetrack Piping:
· Completed installing flexible connections between sections of racetrack piping
· Continued installing support hangers for branch lines from racetrack piping
· Completed installation of branch lines for water and air piping from racetrack, and continued insulation on piping
Log Conditioning Vaults
· Continued excavation and placing No. 57 stone for vault foundation
· Continued work on forms for slab on Vaults No. 7-14
· Set forms, installed reinforcing, and placed Section 1 on Vault Holding Tank walls (North wall, approximately 2/3 of east wall – up to 8’-0”)
· Set forms and installed rebar on west wall & both south walls on Vault Holding Tank
Log Pro Merchandiser:
· Continued setting forms, reinforcing, and embedded steel for foundations
· Placed concrete in Section 1 foundation
· Contractor began setting and welding structural bents on Section 1 foundation
Plant Build-out:
· Performed layout for office area, lunchroom area, and mezzanine area to begin block work
· Masonry contractor mobilized to the site
Winston Plywood:
· Continued refurbishing and installing green-end equipment for both east and west lathe lines
· Continued refurbishing Dryer No. 2
· Continued to receive both new and used process equipment
· Continued construction of No. 3 Veneer Dryer
· Continued installing MCC units throughout plant
· Began installing equipment in Hog Room
Miscellaneous:
· City of Louisville (MDR) completed installing primary power from railroad crossing to corner of parking lot
· Recorded no rain at the site this week
· Contractor continued installing natural gas line to metering station from rail spur
· Continued installing metering station for natural gas piping