Foundations:
· Placed and finished sander foundations
· Installed new foundation for Dryer No. 3 drive take-up assembly
· Placed roof on southeast electrical room
Building:
· Placed concrete around interior building columns
· Completed trim-out and bracing on Building 1
· Continued installing standing seam roofing on Building 2 & 3, and started installing on Building 4
· Completed trim-out and bracing on Buildings 2 & 4
· Completed installing louvers on west wall of Building 2 and started installing on Building 4
· Continued trim-out and bracing on Buildings 6, 6A, 7, 8, and 11
· Installed framed opening for 16’ door on Building 11
· Started installing edge angles for decking on Building 8
· Started installing wall sheets on Building 5
· Installed wall sheets on west side of Building 1
· Started installing wall sheets on west side of Building 2
Fire Protection:
· Completed installing foundations for fire water tank, including installing and compacting fill material in center of foundation
· Continued installing pipe bracings and supports throughout buildings
· Installed underground fire main across drainage ditch (from main parking lot to over-flow parking)
· Continued installation of trim-out and detailing on systems (drip-drains, riser trim, etc)
· Changed out incorrect temperature heads to higher temp heads
· Fire water storage tank delivered to site
Hog Room, Glue Room, and Lathe & Chipper Deck:
· Received one load of structural support steel for glue room
· Temporary handrails completed around lathe and chipper deck
Electrical:
· Continued electrical rough-in for lighting in Buildings 1, 2, 3, & 5, and continued rough-in for lighting in building 4 (Conduit and junction boxes)
· Located MCC units on floor throughout the plant
· Continued running conduit for process equipment at Dryers 1 & 2
· Began installing primary underground service to transformers (grounding only) on transformers 5-13
· Openings were cored on both north electrical room concrete roofs and performed layout on south electrical room roof
Site Utilities:
· Contractor began testing of underground fire protection lines
· Sawcut paving in parking lot and installed city water approximately 75% of way across lot
· Installed concrete thrust blocks on elbows for underground water main
· Installed trench drain at northwest entrance to plant site (behind guard house)
Racetrack Piping:
· Received and installed six sections of racetrack trusses and piping (south three sections on east and west column rows for Building 1)
Log Conditioning Vaults
· Continued excavation for 16’ deep concrete holding tank for vault water
· Removed old foundations from previous retaining wall
Site Paving
· Installed fill material and stone from southwest corner of plywood building, around south end of Building 4 and northward to Building 11
Winston Plywood:
· Continued refurbishing and installing green-end equipment for both east and west lathe lines
· Continued to receive used process equipment
· Continued construction of No. 3 Veneer Dryer (Dryer main framework)
· Completed press pit foundation modifications on Presses No. 1 and 3
· Continued press pit foundation modifications on Press No. 2
· Installed press columns and base & top frames; began placing press plates
· Continued modifications to veneer lathes
Miscellaneous:
· MDR Electrical erected power poles for primary power service to plant site
· Construction ongoing for primary power line to WP&V site