Monday, October 5, 2015

Winston Plywood Weekly Update-9-29-15

Masonry work at Electrical Room

Foundations:

· Continued work on Green-end Electrical Room

· Completed 24” slab at Glue Room

Building:

· Continued installing standing-seam roof on Buildings 3

· Continued trim-out and structural detailing on structural steel framing on Building 2

· Installed insulation and water-shield on Building 2 from Columns 3-27

· Completed structural framing for Lathe Deck, placed and finished Lathe Deck concrete

· Continued installing wall girts on Building 3

· Continued bracing and trim-out on Building 4

· Erected structural steel framing for Building 11

Fire Protection:

· Continued installing sprinkler systems in Building 2

Electrical:

· Continued block work on green-end electrical rooms

· Continued underground primary power supply duct banks – installed ducts across south end of plywood building and underneath rail spurs at southwest corner of building

· Began installing boxes in ceiling of Buildings 1, 3, and 5 for lighting grid

Sitework and Paving:

· Placed concrete paving between Buildings 8 & 10 (around transformers 5-13 and primary switches)

Winston Plywood:

· Continued refurbishing existing veneer dryers

· Continued refurbishing and installing green-end equipment for west lathe line

· Received and off-loaded additional Log-Pro equipment for log processor

· Received first two loads of No. 3 Dryer components

· Set base plates for steam boilers (not grouted)

· Continued press pit modifications

 Setting Conex for east lathe control room


Setting Boiler No. 1

Setting Boiler No. 1

Boilers No. 1 and 2 in place on foundations