Masonry work at Electrical Room |
Foundations:
· Continued work on Green-end Electrical Room
· Completed 24” slab at Glue Room
Building:
· Continued installing standing-seam roof on Buildings 3
· Continued trim-out and structural detailing on structural steel framing on Building 2
· Installed insulation and water-shield on Building 2 from Columns 3-27
· Completed structural framing for Lathe Deck, placed and finished Lathe Deck concrete
· Continued installing wall girts on Building 3
· Continued bracing and trim-out on Building 4
· Erected structural steel framing for Building 11
Fire Protection:
· Continued installing sprinkler systems in Building 2
Electrical:
· Continued block work on green-end electrical rooms
· Continued underground primary power supply duct banks – installed ducts across south end of plywood building and underneath rail spurs at southwest corner of building
· Began installing boxes in ceiling of Buildings 1, 3, and 5 for lighting grid
Sitework and Paving:
· Placed concrete paving between Buildings 8 & 10 (around transformers 5-13 and primary switches)
Winston Plywood:
· Continued refurbishing existing veneer dryers
· Continued refurbishing and installing green-end equipment for west lathe line
· Received and off-loaded additional Log-Pro equipment for log processor
· Received first two loads of No. 3 Dryer components
· Set base plates for steam boilers (not grouted)
· Continued press pit modifications
Setting Conex for east lathe control room |
Setting Boiler No. 1 |
Setting Boiler No. 1 |
Boilers No. 1 and 2 in place on foundations |