Saturday, November 28, 2015

Winston Plywood Weekly Update 11-27-2015

Setting forms, embeds, and rebar for Log Pro equipment foundations

Buildings:
  • Installed south wall sheets on Building 3
  •  Installed east wall sheets on south end section of Building 3 (adjacent to Building 6)
  •  Installed east side wall sheets on Building 4
  •  Installed south end wall sheets on Building 6
  • Continued punchlists on Building 1, 2, & 3
  •  Completed trim-out and louver installation on Buildings 3 (North End), 6, 6A, 7, 8, and 11

Fire Protection:
  • Continued installing hose station piping
  •  Continued installing drum-drips and drains for sprinkler    systems
  •  Continued installing sprinkler systems in Buildings 6, 6A, 7, 8, and 11
Hog Room, Glue Room, and Lathe & Chipper Deck:
  •  Placed charger pedestal concrete foundations at Lathes 1 & 2
Electrical:
  • Continued electrical rough-in for lighting and miscellaneous  electrical services
  •  Continued installing cable tray throughout the plant
  •  Continued hanging lighting fixtures in Building 2
  •  Continued setting electrical switchgear in north electrical room
  •  Continued pulling primary electrical feeders to north and south  electrical rooms
  •  Continued running conduit for process equipment at green-  end, dryers, presses, and dry-end
  •  Continued installing primary underground service to  transformers 9-13 on north end and 1-4 on south end of plant
Racetrack Piping:
  •  Continued installing flexible connections between sections of  racetrack piping
  • Continued installing support hangers for branch lines from  racetrack piping
  •  Continued installation and insulation of branch lines for water  and air piping from racetrack
Boiler and Steam:
  • Continued installing valving and instrumentation on boilers and water softener units
Log Conditioning Vaults
  • Continued curing bottom slab in vault water holding tank
  •  Began excavation and placing No. 57 stone for vault foundations
  •  Began demo of forms and installed drainage piping around base of vault water holding tank
Log Pro Merchandiser:
  • Began setting forms and embedded steel for foundations (adjacent to and east of Building 10)
Winston Plywood:
  • Continued refurbishing and installing green-end equipment for  both east and west lathe lines
  •  Continued painting green-end equipment at lathes
  •  Continued to receive both new and used process equipment
  •  Continued construction of No. 3 Veneer Dryer
  •  Began setting electrical gear in south electrical room
Miscellaneous:
  • City of Louisville (MDR) installed power from corner of parking lot to final pole at southwest corner of site
  •  No rain recorded at the site this week
Excavation and placement of #57 stone for vault foundations


Exterior wall on Buildings 1, 6, and 6A

Power supply from Louisville Utilities to feeder poles at southwest corner of plywood plant

Monday, November 23, 2015

Winston Plywood Weekly Update 11-20-2015

Setting final section of Racetrack truss and piping

Foundations:
  • Placed Lathe Charger pedestals at Lathes 1 and 2

Buildings:
  • Completed installing upper wall sheets on west side of Building 1 and installed ground-level wall sheets on east side of Building 1
  • Started punchlists on Building 1
  • Completed valley metals on Building 3 (North and south sides at Buildings 7 & 8)

  •  Completed installing wall sheets and translucent panels on Building 4 (south end of plant)

  • Completed installing wall sheets on north end of Building 5 and began installing louver trim-out (north end of plant)
  • Completed installing insulation and roof sheets on Building 7
  • Continued installing mezzanine decking for elevated slab in Building 8
  • Completed installing standing-seam roof on Building 11

Fire Protection:
  • Continued installing hose station piping
  • Continued installing drum-drips and drains for sprinkler systems
  • Completed installing underground fire loop, specifically along the north side of the existing main parking lot
  • Continued erecting fire water storage tank (two remaining nozzles to install)
  • Received two prefabricated fire system houses
  • Pneumatically tested building sprinkler systems and repaired leaks
  • Began installing sprinkler systems in Buildings 6, 6A, 7, 8, and 11

Hog Room, Glue Room, and Lathe & Chipper Deck:
  • Continued erecting structural steel on Glue Room
  • Continued finishing concrete walls around Glue Room

Electrical:
  • Continued electrical rough-in for lighting and miscellaneous electrical services
  • Continued installing cable tray throughout the plant
  • Continued setting electrical switchgear in north electrical room
  • Continued pulling primary electrical feeders to north and center electrical rooms
  • Continued running conduit for process equipment at green-end, dryers, presses, and dry-end
  • Continued installing primary underground service to transformers 9-13

Racetrack Piping:
  • Completed installation of Racetrack trusses and piping
  • Continued installing flexible connections between sections of racetrack piping
  • Continued installing support hangers for branch lines from racetrack piping
  • Continued installation and insulation of branch lines for water and air piping from racetrack

Boiler and Steam:
  • Began installing valving and instrumentation on boilers

Log Conditioning Vaults
  • Completed forms and rebar, and placed bottom slab in vault water holding tank

Log Pro Merchandiser:
  • Drained and removed rain water from foundation area

Winston Plywood:

  • Continued refurbishing and installing green-end equipment for both east and west lathe lines
  • Began painting green-end equipment downstream from lathes

  • Continued to receive both new and used process equipment
  • Continued construction of No. 3 Veneer Dryer (Dryer main framework, heating coils, side plating, and fan drive motors)
  • Continued concrete base and wall modifications in Press Pit No. 3
Miscellaneous:
  • City of Louisville (MDR) installed power line across rail track to corner of WPV parking lot

  • Received 4.8” of rain on Tuesday night and Wednesday of this week








Monday, November 16, 2015

Meeting Agenda-Nov 17

CITY OF LOUISVILLE

TUESDAY, NOVEMBER 17, 2015 


REGULAR MEETING AGENDA  5:30 P.M.

I.             CALL TO ORDER
II.            INVOCATION
III.          PLEDGE OF ALLEGIANCE TO FLAG
IV.          APPROVAL OF MINUTES
V.            NEW BUSINESS

A.    Zoning Petition from Winston Medical Foundation, recommendation from the Zoning Board, to rezone property on East Main from R-1 to B-1
B.    Unclean property:  Hearing for three properties
1.    Sara Walker, 206 Thompson, parcel 80-151282802 0401500
2.    Sara Wragg, 109 Warner Avenue, parcel 80-151283301 0500900
3.    Shelia Beasley, at 208 East Jefferson, parcel 80-151283301 0700700

C.    Adopt a resolution adjudicating $450.48, the cost of cleaning property at 201 West Poplar Drive, owned by Paula Mass, and enrolling the lien against the property
D.    Authorize payment to Clearwater Consultants for $18,880.00 for engineering on Airport 2015 Hangar project funded by MDOT MultiModal Grant which is a 50% match
E.    Authorize payment to MS Municipal Service Company for $48,096.00 (with discounts) for annual liability premium
F.    Request for Andy Taylor to attend the MS Chiefs’ of Police Winter Conference in Oxford on December 8-11, registration, meals and mileage
G.    Request for Johnnie Roy Haynes to attend the MS Fire Chiefs’ Conference in Ridgeland on January 19-21, registration, meals and mileage
H.    Hire Police Officers - enclosed
I.     Discuss Comprehensive Plan
J.    Discuss Landfill Consultants Agreement
K.    Christmas Party to be held Tuesday, December 15 at 6:00 for City employees and families
L.    Holiday Schedule for Office: closed November 26-27, December 24-25, and January 1
M.   Holiday schedule for Landfill: closed November 26 for Thanksgiving and December 25 for Christmas;  Garbage pickup for those days will be changed to the Wednesday prior to the holiday
N.    Notice of Appointment to Housing Authority Board: Pauline Nicholson’s 5-year term ends January 1, 2016


VI.          OTHER BUSINESS
VII.         ADJOURN



CITY OF LOUISVILLE GARBAGE PICKUP FOR THANKSGIVING HOLIDAY


The Louisville Solid Waste Garbage Pickup schedule has only been changed so that the Thursday, November 26 garbage pickup will be made on Wednesday, November 25, the day before Thanksgiving.  The Friday route is not changed. 

Happy Thanksgiving to all!

Winston Plywood Weekly Update 11-13-15





Foundations:

· Continued to set forms and install rebar on pedestals for lathe chargers

Buildings:

· Completed seaming roof panels on Buildings 3 and 4

· Continued installing wall sheets and translucent panels on Building 4

· Continued installing wall sheets on north end of Building 5

· Completed framing and began installing decking on mezzanine in Building 7

· Completed installing standing-seam roofing on Building 8

· Began installing standing-seam roof on Building 11

Fire Protection:

· Continued installing hose station piping

· Continued installing drum-drips and drains for sprinkler systems

· Continued installing underground fire loop, specifically along the north side of the existing main parking lot

· Installed two hydrants in parking lot area

· Continued installing underground sectional valve boxes

· Continued erecting fire water storage tank

Hog Room, Glue Room, and Lathe & Chipper Deck:
· Continued erecting structural steel on Glue Room

· Installed roof decking on glue rooms and hog room

· Demo’d forms on glue room containment wall and finished walls


Electrical:

· Continued electrical rough-in for lighting and miscellaneous electrical

· Completed lighting mock-up installation on building lighting; Mock-up was approved

· Continued installing cable tray throughout the plant

· Completed installing electrical switchgear in center electrical room and continued pulling primary feeders

· Began installing electrical switchgear in north electrical room

· Continued running conduit for process equipment at green-end, dryers, presses, and dry-end

· Continued installing primary underground service to transformers 9-13

Site Utilities:

· Completed installing water line from connection at City of Louisville main water line

Racetrack Piping:

· Received and installed additional sections of racetrack trusses and piping; two sections remain to be installed on east side of racetrack, as well as north and south sections of track

· Continued installing flexible connections between sections of racetrack piping

· Continued installing support hangers for branch lines from the racetrack piping

· Continued installation of branch lines for process water and air piping from racetrack

Boiler and Steam:

· Installed support structure and DA tank for boilers


Log Conditioning Vaults

· Placed stone, set forms, and began installing rebar for floor slab in holding tank for vaults


Log Pro Merchandiser:

· Received remaining embed plates and rebar for foundations

· Began grading foundation site to finish grade

Winston Plywood:

· Continued refurbishing and installing green-end equipment for both east and west lathe lines

· Continued to receive both new and used process equipment

· Continued construction of No. 3 Veneer Dryer (Dryer main framework and heating coils)

· Continued concrete base and wall modifications in Press Pit No. 3

· Continued to set layup line and finishing line equipment

Miscellaneous:

· Made tie-in at main substation for new primary electrical line to plywood plant

· Received 2.6” of rain through noon Friday of this week







Thursday, November 12, 2015

Welcome to our Updated Website

The City of Louisville's website is in the process of updating. There should be no interruption of service but we ask for your patience. In the meantime, browse our pages for information.

Monday, November 9, 2015

Winston Plywood Weekly Update 11-06-15


Buildings:

· Continued installing wall sheets and translucent wall panels on Building 2

· Began installing wall sheets on Building 4

· Installed roof decking on Buildings 6, 6A, and 11

· Began installing standing-seam roofing on Building 8

· Completed installing wall purling on Buildings 6, 6A, 7, 8, and 11

· Continued seaming roof panels on Buildings 3 and 4



Fire Protection:

· Continued installing pipe bracings and supports throughout buildings in preparation for system testing

· Continued installing hose station piping

· Continued installing underground fire loop, specifically along the north side of the existing main parking lot

· Tied in main loop to previously installed section of piping at northwest corner of plywood plant building

· Began erecting fire water storage tank



Hog Room, Glue Room, and Lathe & Chipper Deck:

· Continued erecting structural steel on Glue Room

· Finished installing glue tanks in glue room

· Placed concrete containment wall at west section of glue room



Electrical:

· Continued electrical rough-in for lighting and miscellaneous electrical

· Began lighting mock-up installation for review and acceptance for building lighting system

· Continued installing cable tray throughout the plant

· Installed electrical switchgear in center electrical room and began pulling primary feeders

· Continued running conduit for process equipment at green-end, dryers, presses, and dry-end

· Continued installing primary underground service to transformers 9-13



Site Utilities:

· Continued installing water line from connection at City of Louisville main water line; Made hot-tap connection onto existing city water line to connect plywood plant water systems

· Installed precast meter vault, meter base, and back-flow prevention system just west of fire water storage tank

· Installed final section of storm drain piping and tied into trench drain

Racetrack Piping:

· Received and installed six additional sections of racetrack trusses and piping

· Continued installing flexible connections between sections of racetrack piping

· Continued installing support hangers for branch lines from the racetrack piping

· Began installation of branch lines for process water and air piping from racetrack



Boiler and Steam:

· Installed exhaust stacks on three boilers

· Received and staged boiler DA tank



Log Conditioning Vaults

· Continued excavation for 16’ deep concrete holding tank and reached final grade

· Continued to pump accumulated water from rains throughout the week



Log Pro Merchandiser:

· Laid out boundaries of Log Pro equipment foundations



Winston Plywood:

· Continued refurbishing and installing green-end equipment for both east and west lathe lines

· Disassembled east lathe and painted main frames

· Continued to receive both new and used process equipment

· Continued construction of No. 3 Veneer Dryer (Dryer main framework and heating system)

· Continued concrete base and wall modifications in Press Pit No. 3

· Installed press platens in Press No. 4

· Continued to set layup line and finishing line equipment in place



Miscellaneous:

· Continued construction for primary power line to WP&V site – pulled overhead transmission wiring into place along power line

· Received 2.5” of rain through noon Friday of this week








Monday, November 2, 2015

Winston Plywood Weekly Update 10-30-15



Foundations:
·         Removed forms for sander foundation
·         Connected sanitary sewer to west restrooms
·         Installed grating in boiler room drains trenches

Building:
·         Installed decking on Building 8
·         Started installing decking on Building
·         Continued installing standing seam roofing on Building 2 & 3, and started installing on Building 4
·         Continued installing louvers on west wall of Building 2 and started installing on Building 4
·         Started installing louvers on east wall of Building 3
·         Installed framed opening for 16’ door on Building 8
·         Continued installing personnel doors on Buildings 8 and 11
·         Completed installing edge angles for decking on Building 8
·         Continued installing wall sheets on west side of Building 1 (upper wall section)
·         Continued installing wall sheets on west side of Building 2
·         Started pressure washing structural steel framing
·         Began installing decking on Building 6A

Fire Protection:
·         Continued installing pipe bracings and supports throughout buildings
·         Received partial shipment of piping for Buildings 8 & 11

Hog Room, Glue Room, and Lathe & Chipper Deck:
·         Began erecting structural steel on Glue Room
·         Began installing glue tanks in glue room

Electrical:
·         Continued electrical rough-in for lighting and miscellaneous electrical in Buildings 1, 2, 3, 5 and 9, and continued rough-in for lighting in building 4 (Conduit and junction boxes)
·         Received shipment of cable tray for electrical installations
·         Started installing cable tray throughout the plant
·         Completed coring for electrical in both north electrical rooms and began coring on south electrical room
·         Began  moving switchgear to the north electrical rooms to begin installation
·         Continued running conduit for process equipment at Dryers 1 & 2
·         Continued installing primary underground service to transformers (grounding only) on transformers 5-13 and started installation on transformers 1-4

Site Utilities:
·         Continued installing water line from connection at City of Louisville main water line
·         Continued saw-cutting paving in parking lot and installed city water approximately 95% of way across lot

Racetrack Piping:
·         Received and installed four additional sections of racetrack trusses and piping
·         Began installing flexible connections between sections of racetrack piping
·         Started installing support hangers for branch lines from the racetrack piping

Log Conditioning Vaults
·         Continued excavation for 16’ deep concrete holding tank for vault water and pumped rainwater that accumulated in excavation

Winston Plywood:
·         Continued refurbishing and installing green-end equipment for both east and west lathe lines
·         Continued to receive used process equipment
·         Continued construction of No. 3 Veneer Dryer (Dryer main framework)
·         Completed press pit foundation modifications on Presses No. 1 and 3
·         Continued press pit foundation modifications on Press No. 2
·         Installed press columns, base, frame and platens on Press No. 1;  Installed press columns, base, and top frame on Press No. 4
·         Continued modifications to veneer lathes

Miscellaneous:
·         Continued construction for primary power line to WP&V site
·         Received a total of 3.6” of rain during the week