The purpose of this meeting is to help build a better relationship between Citizens and Law Enforcement Agencies. Louisville Police Chief L.M. Claiborne will be present to help informs us om ways to help better these relationships. He will be giving us important tips and demonstrating proper procedure for both Citizens and Law Enforcement Agencies. The public is welcome to attend.
Contact Robert Finch at 662-803-1901 or L.C. Hines at 662-392-7430 for more information.
Tuesday, August 30, 2016
Monday, August 15, 2016
Winston Plywood Weekly Update 8-12-16
Hog,
Glue Room, and Chipper Deck:
· Continued
insulating water piping to eye-wash stations
Low
Voltage Electrical:
· Continued
installing conduit and wiring to breakroom / restrooms / offices at mezzanine
area, west side break & restroom area, and in shipping office
· Continued
installing fire alarm system on metal wall at mezzanine and maintenance shop area
· Continued
electrical installation at fire pump buildings
Plant
Build-Out:
· Continued
installation of HVAC unit at shipping office, MCC rooms and glue loft area
· Began
installing ceiling grid in upstairs offices at mezzanine area
· Continued
installing ceiling grid in west-side lunch room
· Installed
metal roof decking over west side lunch room
· Installed
ceiling tile in west side lunchroom
· Received
and began installing millwork in east side offices and lunch room
· Continued
finish painting in east side offices and lunch room
Site
Paving:
· Continued
draining water from west side light duty paving
East
Side & West Side Residuals:
· Continued
installing ductwork to equipment inside building (dry hogs, trim-saws, sander)
· Continued
installing support steel and equipment for west side residuals (fans and
blowers)
Monday, August 8, 2016
Winston Plywood Update 8-5-16
Hog,
Glue Room, and Chipper Deck:
· Continued
installing piping and valves at glue make-up and storage area
· Completed
installation of emergency eye wash station at glue room and caustic unloading
area
· Began
insulating water piping to eye-wash stations
Low
Voltage Electrical:
· Continued
installing conduit and wiring to breakroom / restrooms / offices at mezzanine
area, west side break & restroom area, and in shipping office
· Continued
installing fire alarm system on metal wall at mezzanine and maintenance shop
area
· Completed
installation of power wiring from primary feeder line to WSR transformer, and
from transformer to MCC unit inside West-Side Residuals electrical building
Log
Pre-Conditioning Vaults:
· Removed
temporary safety fence and installed permanent safety fencing around perimeter
of vault water storage pit & vault water return trench to storage pit
· Installed
safety fencing around perimeter of top of vault concrete structure
Plant
Build-Out:
· Began
installing toilet accessories in east-side restrooms
· Continued
installing door hardware throughout east and west side restroom and break areas
· Continued
installation of HVAC unit at shipping office, MCC rooms and glue loft area
· Began
installing ceiling grid in upstairs offices at mezzanine area
· Installed
ceiling grid in west-side lunch room
· Installed
sink in QC room (TECO Lab)
Site
Paving:
· Continued
excavation and placement of stone for paving between vaults and log infeed deck
· Finished
layout and preparation for placement of reinforcing steel between vaults and
log infeed deck for paving
· Placed
concrete paving and performed sawcutting in area between vaults and log infeed
deck
East
Side & West Side Residuals:
· Continued
installing ductwork to equipment inside building (dry hogs, trim-saws, sander)
· Continued
installing ductwork to truck bins on west-side residual
Monday, August 1, 2016
Winston Plywood Weekly Update 7-29-16
Foundations:
· Continued
making repairs to old floor slab (North side of No. 1 dryer and along building
column line E)
Site
Utilities:
· Completed
placing concrete in treads on stairs at lathe access areas
Northeast
Corner – Log Ramp Construction Area:
· Removed
material, graded area, and set forms between vaults and tree-length deck for
paving
Hog,
Glue Room, and Chipper Deck:
· Continued
installing piping and valves at glue makeup and storage area
· Completed
installation of emergency eye wash station at glue room and caustic unloading
area
· Installed
roll-up door at south end of second floor elevation in glue room
Low
Voltage Electrical:
· Continued
installing conduit and wiring to breakroom / restrooms / offices at mezzanine
area, west side break & restroom area, and in shipping office
· Continued
installing fire alarm system on metal wall at mezzanine and maintenance shop
area
Log
Pre-Conditioning Vaults:
· Continued
placing plywood blocks inside vaults for heating and peeling
· Heated
water in vault water holding tank by circulating through heat exchangers
· Pumped
water onto logs in vaults and heated logs
· Installed
temporary fencing around perimeter of vault water holding pit and along north
side of vault water drainage trench
Plant
Build-Out:
· Continued
installing bathroom fixtures in west-side restrooms
· Placed
concrete in stair treads and lands on stairs at west side of mezzanine area
· Continued
installing door hardware throughout east and west side restroom and break areas
· Continued
installation of HVAC unit at shipping offices
Site
Paving:
· Continued
excavation and placement of stone for paving between vaults and log infeed deck
· Began
layout and preparation for placement of reinforcing steel between vaults and
log infeed deck for paving
RTO
Rebuild:
· Continued
installing insulation on RTO duct (completed south side and continued on ID fan
and stack)
· Began
insulating ID fan and RTO stack
· Continued
installing conduit and power to RTO duct controls and devices
East
Side & West Side Residuals:
· Continued
fabricating and installing guards for conveyor drive units
· Continued
installing ductwork to truck bins on west-side residuals
· Set
cyclone down-comer piping on both cyclones
· Set
rotary feeders for high pressure blowers
Winston
Plywood & Veneer:
· Continued
running logs through debarker and cut-up system, and kicked blocks out into log
pockets
· Continued
placing logs in vaults and heating logs for peeling at Lathe No. 2
· Continued
checkout and peeling hot blocks on Lathe No. 2
· Continued
checkout on No. 2 lathe line equipment (lathe, clipper, & stacker)
· Continued
checkout and tuning on Log Pro equipment
· Continued
installing piping from glue room to lay-up line equipment
· Continued
installing trash conveyor for lay-up line to hog room
· Continued
details on installation of Dryer No. 1 & 2 infeed and outfeed sections
· Continued
testing dryer infeed systems and main dryer chains and rolls in No. 1 & 2
dryers
· Continued
installing glue lay-up line mechanical and electrical equipment
· Continued
details on installing trim-saw equipment