· Rain stopped work in this area
Buildings:
· Continued installing gutter system on West side Building 2.
· Continued forming column wraps in building 5
· Placed slab for Mezzanine
Electrical:
· Continued making terminations for primary power.
· Continued installing lighting throughout the plant.
· Continued electrical distribution throughout the plant
Racetrack Piping:
· Began hydro testing plant piping (Air and Water).
· Began making adjustments to pipe drops at exterior columns
Log Conditioning Vaults
· Began backfill of the 1st 8 foot of the recovery tank
· Began placing forms for the top portion of the walls for the water recovery tank
· Continued placing rebar for the Vault bottoms 7 thru 14.
· Began backfill of the 1st 8 foot of the recovery tank
· Began placing forms for the top portion of the walls for the water recovery tank
· Continued placing rebar for the Vault bottoms 7 thru 14.
Site Paving
· Rain stopped work in this area
Log Pro Merchandiser:
· Rain stopped work in this area
Plant Build-out:
· Began block work for Office area.
· Began block work for Lunch room area.
· Began block work for Mezzanine Area
Hog Glue Lathe Chipper:
· Placed roof for Hog room
· Modifications to Chipper deck elevations on going (WP&V Crews) Paving
· Rain stopped work in this area
Plant Build-out:
· Began block work for Office area.
· Began block work for Lunch room area.
· Began block work for Mezzanine Area
Hog Glue Lathe Chipper:
· Placed roof for Hog room
· Modifications to Chipper deck elevations on going (WP&V Crews) Paving
Miscellaneous:
· Gas line installation complete.
· Significant rain recorded