Foundations:
· Formed,
placed, and finished glue line foundation with sumps
· Installed
rebar and set forms for sawline foundations
· Drilled
& doweled rebar into existing floor slab; began installing rebar and forms
for spec saw foundation
Buildings:
· Additional
louvers received; installation pending receipt of additional gutters and down
spouts
Racetrack
Piping:
·Continued
installing trim-out piping and valves to plant equipment
High
Voltage Electrical:
·Engineer,
contractor, and city representatives performed commissioning on remaining transformers
and gear
Low
Voltage Electrical:
· Continued
installing electrical conduits and cables to chipper deck electrical room
· Continued
installing fire alarm piping, boxes, and wiring
· Continued
testing fire alarm system
·Continued
commissioning electrical gear and MCC’s
·Continued
running electrical service to plant equipment
·Installed
electrical duct bank from RTO transformer to RTO Control Room
·Continued
installing conduit and wiring to breakroom / restrooms / offices at mezzanine
area
Continued
running conduit and wiring to green-end and out to north wall on building 9
Hog
Room, Glue Room, Chipper Deck:
· Placed
and finished upper floor concrete slab at glue room
Plant
Build-Out:
· Laid
blocks in interior offices below mezzanine area (east side of plant)
· Laid
blocks at west side break room and rest rooms
Plant
Piping:
· Continued
installing steam and condensate piping to Dryers No. 1, 2, and 3
· Continued
installing trim-out and insulation on steam & condensate piping to dryers
and presses
· Received
condensate return system equipment for hot presses (3 systems)
· Continued
steam and condensate piping in boiler room
· Main
relief valve from steam header installed and vented through the roof of boiler
room
· Began
final alignment of air compressors to exhaust fans in air compressor room
Site
Paving:
· Continued
installing rebar in unused block-outs on east side of plant
Fire
Protection System:
· Continued
installing new deluge system in dryer #3
· Continued
installing sprinkler piping at lathes
· Began
filling sprinkler systems and testing for leaks
Log
Conditioning Vaults:
· Placed
vault wall “T”
· Continued
pre-tying rebar mats for final vault wall
· Installed
Tee-Wall at vault wall “Q”
· Continued
installing galvanized, angled, deflector plates in vaults at base of vaults
· Continued
installation of support system for vault roof concrete slab; placed concrete
mats on support structure (Vaults 1-8)
Equipment
Foundations (East and West Residuals):
· Removed
forms from Hog Tower walls
· Placed
rebar in two unused block-outs on east side of plant
RTO
Rebuild
· Contractor
mobilized to site; began installing ductwork
Winston
Plywood & Veneer
· Continued
refurbishing and installing Lathes No. 1 & 2 and related equipment
· Continued
installing equipment at both clippers, green stackers, and pull chains
· Continued
cleaning and painting green-end equipment
· Continued
electrical installation at Green-End equipment (conduit and power wiring)
· Continued
installing electrical service from electrical room to Log Pro equipment
(unistrut, cable tray, and conduit)
· Continued
refurbishing Dryers No. 1 & 2
· Continued
assembly and installation of Dryer No. 1, 2, & 3 infeed and outfeed
sections
· Continued
making modifications to Stackers for Dryers No. 2 & 3
· Continued
installing diverter and circle conveyor to transfer veneer to round-table
· Continued
refurbishing and painting dry-end equipment
· Continued
installing electrical power to Dryers 1, 2, & 3
· Continued
installing insulation on RTO Ducting (From dryers 1, 2, & 3)
· Continued
installing steam piping from boilers to main steam header
· Completed
installing air line along Log Pro equipment line to debarker, ready for
pressure testing
· Began
setting east side residual equipment (conveyors to screening platform)
· Continued
fabrication of lathe infeed decks and platform for screen tower