Foundations:
· Completed demo of existing building slab for installation of new layup line foundations
· Excavated materials for placement of new glue line foundations
· Placed footing for Sawline (Trimsaws)
Site Utilities:
· Made tie-in’s for downspouts from building roof to underground drain piping
Buildings:
· Additional louvers delivered to site. Additional gutters and downspouts are on order. Contractor will mobilize to site to install louvers, gutters, and downspouts when gutters and downspouts arrive onsite.
· Building representative on site to review plans to make penetrations through roofing system at boiler room
Racetrack Piping:
· Pressure testing on lines remains to be performed when water piping is completed
· Continued installing trim-out piping and valves to plant equipment
High Voltage Electrical:
· Contractor performed commissioning on balance of electrical gear
Low Voltage Electrical:
· Continued installing electrical conduits and cables to chipper deck electrical room
· Continued installing fire alarm piping, boxes, and wiring
· Continued testing fire alarm system
· Commissioning electrical power equipment
Hog Room, Glue Room, Chipper Deck:
· Modifications made to roof of lower floor glue room and tanks & mixer set in place
Plant Build-Out:
· Set door frames in west lunch room area (Restrooms, breakroom, and offices
· Laid out and delivered materials for modifications to west restroom and breakroom area
· Installed grout block walls in east side mezzanine area
Plant Piping:
· Continued installing steam and condensate piping to Dryers No. 1, 2, and 3
· Continued installing trim-out and insulation on steam & condensate piping to dryers and presses
Site Paving:
· Demo’d forms from last week’s paving and cleaned paving site
Fire Protection System:
· Continued installing new deluge system in dryer #3
· Continued installing sprinkler piping at lathes
Log Conditioning Vaults:
· Placed vault wall “S”
· Continued pre-tying rebar mats for additional vault walls
· Installed Tee-Wall at vault wall “O” and “P”
· Continued installing galvanized, angled, deflector plates in vaults at base of vault walls
· Continued installation of support system for vault roof (Vaults 1-8)
Log Pro Equipment Foundations:
· All foundation work complete in this area
Equipment Foundations (East and West Residuals):
· Formed and placed walls for hog tower
· Formed, set embeds & rebar, and placed two remaining truck bin pier walls on east side residuals
· Completed erecting structural support steel for ductwork along west wall of building (for west side residuals)
Winston Plywood & Veneer
· Continued refurbishing and installing Lathes No. 1 & 2 and related equipment
· Continued installing equipment at both clippers, green stackers, and pull chains
· Continued electrical installation at Green-End equipment (conduit and power wiring)
· Continued installing electrical service from electrical room to Log Pro equipment (unistrut, cable tray, and conduit)
· Continued refurbishing Dryers No. 1 & 2
· Continued assembly and installation of Dryer No. 1, 2, & 3 infeed and outfeed sections
· Continued making modifications to Stacker for Dryer No. 2 (reverse hand – Electrical control boxes)
· Continued installing dry stacker out-feed roll cases and discharge equipment (transfer equipment to dry stackers
· Installed diverter and circle conveyor to transfer veneer to round-table
· Continued refurbishing and painting dry-end equipment
· Continued installing electrical power to Dryers 1, 2, & 3
· Continued installing insulation on RTO Ducting (From dryers 1, 2, & 3)
· Continued installing steam piping from boilers to main steam header
· Continued installing air line along Log Pro equipment line to debarker