· Completed installing additional wall louvers in boiler room and air compressor rooms
· Continued work on building punchlist items
· Began installing additional gutters on Building No. 1 (Tallest section of plant building)
Foundations:
· Placed remaining conveyor foundations for East-Side Residuals
· Laid out and began installing foundation for Pipe Truss from plywood plant building, across north roadway to roof of vaults
Site Utilities
· Tap main fire water line for water storage tank heater circulating system
· Investigating alternate routing of sewer piping to avoid interference with other piping system and electrical duct bank
Racetrack Piping:
· Continued installing trim-out piping and valves to plant equipment
Low Voltage Electrical:
· Continued installing conduit and wiring to breakroom / restrooms / offices at mezzanine area
· Continued running conduit and wiring to green-end and out to north wall on Building 9
· Stood remaining poles for lighting in west-side main parking lot
· Continued installing underground conduits and power to light poles
Plant Build-Out:
· Continued installing HVAC system components in electrical and MCC rooms
Plant Piping:
· Continued installing steam and condensate piping to Dryers No. 1, 2, and 3
· Continued steam and condensate piping in boiler room
· Completed installing expansion loops in steam piping
· Fabricated piping for connecting air compressors and overhead line to connect to racetrack piping, shipped pipe to shop to be painted
Site Paving:
· Continued grading for paving and equipment foundations on east side of plant (in open strip between Log Pro foundation and Hog Tower
· Began installing rebar in paving strip at Log Pro / Bark Hog
Fire Protection System:
· Continued installing hose reels at building columns
· Continued installing deluge systems in dryers (For WPV)
Log Conditioning Vaults:
· Completed installing galvanized, angled, deflector plates in vaults at base of vaults
· Completed relocating support system for placement of east half of vault roof
· Began setting forms and placing rebar on east half of vault roof
Equipment Foundations (East and West Residuals):
· Placed concrete roof on hog tower
· Excavated, formed, and placed East-Side Residual conveyor foundations to truck bins
· Completed block work on west side residual control room
RTO Rebuild
· Continued to work on arrangement of ID fan and fan motor foundations
· Continued construction of RTO control room
Winston Plywood & Veneer
· Continued refurbishing and installing Lathes No. 1 & 2 and related equipment
· Continued installing equipment at both clippers, green stackers, and pull chains
· Continued cleaning and painting green-end equipment
· Continued electrical installation at Green-End equipment (conduit and power wiring)
· Continued installing electrical service from electrical room to Log Pro equipment (unistrut, cable tray, and conduit)
· Continued refurbishing Dryers No. 1 & 2
· Continued assembly and installation of Dryer No. 1, 2, & 3 infeed and outfeed sections
· Continued making modifications to Stackers for Dryers No. 2 & 3
· Continued refurbishing and painting dry-end equipment
· Continued installing electrical power to Dryers 1, 2, & 3
· Continued setting east side residual equipment (conveyors to screening platform)
· Continued installation of east side truck bins
· Continued installing air piping on dryers
· Continued refurbishing east side residual equipment (at Roseburg site)
· Continued installing glue lay-up line equipment
· Continued flushing and testing of boiler piping
· Continued installing trim-saw equipment and plywood stacker
· Began setting support steel on hog tower to support tower upper level
· Continued installing chutework at tree-length infeed bark conveyor and at cut-up saw trash conveyo