Monday, May 9, 2016

Winston Plywood Update 5-6-16



Buildings:

· Completed installing additional wall louvers in boiler room and air compressor rooms

· Continued work on building punchlist items

· Began installing additional gutters on Building No. 1 (Tallest section of plant building)

Foundations:

· Placed remaining conveyor foundations for East-Side Residuals

· Laid out and began installing foundation for Pipe Truss from plywood plant building, across north roadway to roof of vaults



Site Utilities

· Tap main fire water line for water storage tank heater circulating system

· Investigating alternate routing of sewer piping to avoid interference with other piping system and electrical duct bank


Racetrack Piping:

· Continued installing trim-out piping and valves to plant equipment


Low Voltage Electrical:

· Continued installing conduit and wiring to breakroom / restrooms / offices at mezzanine area

· Continued running conduit and wiring to green-end and out to north wall on Building 9

· Stood remaining poles for lighting in west-side main parking lot

· Continued installing underground conduits and power to light poles

Plant Build-Out:

· Continued installing HVAC system components in electrical and MCC rooms



Plant Piping:

· Continued installing steam and condensate piping to Dryers No. 1, 2, and 3

· Continued steam and condensate piping in boiler room

· Completed installing expansion loops in steam piping

· Fabricated piping for connecting air compressors and overhead line to connect to racetrack piping, shipped pipe to shop to be painted

Site Paving:

· Continued grading for paving and equipment foundations on east side of plant (in open strip between Log Pro foundation and Hog Tower

· Began installing rebar in paving strip at Log Pro / Bark Hog



Fire Protection System:
· Continued installing hose reels at building columns

· Continued installing deluge systems in dryers (For WPV)



Log Conditioning Vaults:

· Completed installing galvanized, angled, deflector plates in vaults at base of vaults

· Completed relocating support system for placement of east half of vault roof

· Began setting forms and placing rebar on east half of vault roof

Equipment Foundations (East and West Residuals):

· Placed concrete roof on hog tower

· Excavated, formed, and placed East-Side Residual conveyor foundations to truck bins

· Completed block work on west side residual control room



RTO Rebuild

· Continued to work on arrangement of ID fan and fan motor foundations

· Continued construction of RTO control room



Winston Plywood & Veneer

· Continued refurbishing and installing Lathes No. 1 & 2 and related equipment

· Continued installing equipment at both clippers, green stackers, and pull chains

· Continued cleaning and painting green-end equipment

· Continued electrical installation at Green-End equipment (conduit and power wiring)

· Continued installing electrical service from electrical room to Log Pro equipment (unistrut, cable tray, and conduit)

· Continued refurbishing Dryers No. 1 & 2

· Continued assembly and installation of Dryer No. 1, 2, & 3 infeed and outfeed sections

· Continued making modifications to Stackers for Dryers No. 2 & 3

· Continued refurbishing and painting dry-end equipment

· Continued installing electrical power to Dryers 1, 2, & 3

· Continued setting east side residual equipment (conveyors to screening platform)

· Continued installation of east side truck bins

· Continued installing air piping on dryers

· Continued refurbishing east side residual equipment (at Roseburg site)

· Continued installing glue lay-up line equipment

· Continued flushing and testing of boiler piping

· Continued installing trim-saw equipment and plywood stacker

· Began setting support steel on hog tower to support tower upper level

· Continued installing chutework at tree-length infeed bark conveyor and at cut-up saw trash conveyo