Winston Plywood Update 5-27-16
Site Utilities
· Continued investigating alternate routing of sewer piping to avoid interference with other piping system and electrical duct bank
· Continued installing pipe bollards around fire hydrants on south and west sides of plywood building and filled with concrete
· Flushed underground piping and valves for fire system
Hog, Glue Room, and Chipper Pad
· Continued cleanup on blocks and area around glue make-up and storage rooms
Low Voltage Electrical:
· Continued installing conduit and wiring to breakroom / restrooms / offices at mezzanine area
· Pulled power cable from switchgear to Vault MCC unit
Plant Build-Out:
· Installed rails and 5-ton overhead crane in maintenance shop
Plant Piping:
· Continued installing steam and condensate piping to Dryers No. 1, 2, and 3
· Continued steam and condensate piping in boiler room
· Continued installing air piping in compressor room
· Began connecting air compressors to oil coolers in compressor room
Site Paving:
· Performed excavation and grading on strip of remaining paving between vault infeed aprons and paving strip north of building 10
· Began placing reinforcing in area listed above
Fire Protection System:
· Continued installing hose reels at building columns
Log Conditioning Vaults:
· Continued construction of 5’ concrete knee wall along north side of vault drain ditch to holding pit
· Continued installation of steel framework for stoop over ditch along north wall on vaults
· Continued installation of steel structure and roof system over vault water holding tank (east of vaults)
· Completed installation of posts and rails for safety fence around top of vaults
· Installed west-end access stairs to top of vaults
· Began pulling power cables to vault MCC unit
· Began backfill and compaction of material along west and north walls at vaults
· Removed some of debris from vault water holding tank and pumped water from tank
·
Equipment Foundations (East and West Residuals):
· Continued installing handrails around hog tower at mid-level concrete floor
· Continued installing access stairs to hog tower concrete floor (second elevation)
· Continued installing access stairs to hog tower (third elevation)
· Continued installing support frame for conveyor feeding East-Side Residual truck bins
· Placed additional concrete pedestals for additional column foundations on West-Side residuals (for blowpipe supports)
RTO Rebuild
· Continued pulling power cables to MCC unit and turned on lights in Control Room
· Install duct supports for RTO duct from building to RTO
· Began installing ductwork from dryers to RTO
Winston Plywood & Veneer
· Continued refurbishing and installing Lathes No. 1 & 2 and related equipment (focus on east lathe line)
· Continued installing equipment at both clippers, green stackers, and pull chains (focus on east lathe line)
· Continued refurbishing chippers for green-end by products
· Continued cleaning and painting green-end and dry end equipment and support steel
· Continued electrical installation at Green-End equipment (conduit and power wiring)
· Continued installing electrical service from electrical room to Log Pro equipment
· Continued refurbishing Dryers No. 1 & 2
· Continued assembly and installation of Dryer No. 1, 2, & 3 infeed and outfeed sections
· Continued making modifications to Stackers for Dryers No. 2 & 3
· Continued installing electrical power to Dryers 1, 2, & 3
· Continued installation of east side residuals truck bins
· Continued installing air piping to veneer dryers
· Continued refurbishing east side residual equipment (at Roseburg site)
· Continued installing glue lay-up line equipment (Broke out old slab and installed new foundations in four places)
· Continued flushing and testing of boiler piping
· Continued installing trim-saw equipment and plywood stacker
· Continued installing chutework at tree-length infeed bark conveyor and at cut-up saw trash conveyor
· Installed two trusses and conveyors from bark hog tower to top of east side residuals truck bins
· Began saw-cutting and breaking paving concrete for lathe infeed deck foundations
· Performed preliminary test run on No. 1 Lathe line motors and equipment
· Set lathe knife grinder and began construction of knife grinding room