Monday, August 15, 2016

Winston Plywood Weekly Update 8-12-16


Hog, Glue Room, and Chipper Deck:
·         Continued insulating water piping to eye-wash stations

Low Voltage Electrical:
·         Continued installing conduit and wiring to breakroom / restrooms / offices at mezzanine area, west side break & restroom area, and in shipping office
·         Continued installing fire alarm system on metal wall at mezzanine and maintenance shop area
·         Continued electrical installation at fire pump buildings

Plant Build-Out:
·         Continued installation of HVAC unit at shipping office, MCC rooms and glue loft area
·         Began installing ceiling grid in upstairs offices at mezzanine area
·         Continued installing ceiling grid in west-side lunch room
·         Installed metal roof decking over west side lunch room
·         Installed ceiling tile in west side lunchroom
·         Received and began installing millwork in east side offices and lunch room
·         Continued finish painting in east side offices and lunch room

Site Paving:
·         Continued draining water from west side light duty paving

East Side & West Side Residuals:
·         Continued installing ductwork to equipment inside building (dry hogs, trim-saws, sander)
·         Continued installing support steel and equipment for west side residuals (fans and blowers)