Foundations:
· Continued
making repairs to old floor slab (North side of No. 1 dryer and along building
column line E)
Site
Utilities:
· Completed
placing concrete in treads on stairs at lathe access areas
Northeast
Corner – Log Ramp Construction Area:
· Removed
material, graded area, and set forms between vaults and tree-length deck for
paving
Hog,
Glue Room, and Chipper Deck:
· Continued
installing piping and valves at glue makeup and storage area
· Completed
installation of emergency eye wash station at glue room and caustic unloading
area
· Installed
roll-up door at south end of second floor elevation in glue room
Low
Voltage Electrical:
· Continued
installing conduit and wiring to breakroom / restrooms / offices at mezzanine
area, west side break & restroom area, and in shipping office
· Continued
installing fire alarm system on metal wall at mezzanine and maintenance shop
area
Log
Pre-Conditioning Vaults:
· Continued
placing plywood blocks inside vaults for heating and peeling
· Heated
water in vault water holding tank by circulating through heat exchangers
· Pumped
water onto logs in vaults and heated logs
· Installed
temporary fencing around perimeter of vault water holding pit and along north
side of vault water drainage trench
Plant
Build-Out:
· Continued
installing bathroom fixtures in west-side restrooms
· Placed
concrete in stair treads and lands on stairs at west side of mezzanine area
· Continued
installing door hardware throughout east and west side restroom and break areas
· Continued
installation of HVAC unit at shipping offices
Site
Paving:
· Continued
excavation and placement of stone for paving between vaults and log infeed deck
· Began
layout and preparation for placement of reinforcing steel between vaults and
log infeed deck for paving
RTO
Rebuild:
· Continued
installing insulation on RTO duct (completed south side and continued on ID fan
and stack)
· Began
insulating ID fan and RTO stack
· Continued
installing conduit and power to RTO duct controls and devices
East
Side & West Side Residuals:
· Continued
fabricating and installing guards for conveyor drive units
· Continued
installing ductwork to truck bins on west-side residuals
· Set
cyclone down-comer piping on both cyclones
· Set
rotary feeders for high pressure blowers
Winston
Plywood & Veneer:
· Continued
running logs through debarker and cut-up system, and kicked blocks out into log
pockets
· Continued
placing logs in vaults and heating logs for peeling at Lathe No. 2
· Continued
checkout and peeling hot blocks on Lathe No. 2
· Continued
checkout on No. 2 lathe line equipment (lathe, clipper, & stacker)
· Continued
checkout and tuning on Log Pro equipment
· Continued
installing piping from glue room to lay-up line equipment
· Continued
installing trash conveyor for lay-up line to hog room
· Continued
details on installation of Dryer No. 1 & 2 infeed and outfeed sections
· Continued
testing dryer infeed systems and main dryer chains and rolls in No. 1 & 2
dryers
· Continued
installing glue lay-up line mechanical and electrical equipment
· Continued
details on installing trim-saw equipment