Monday, August 8, 2016

Winston Plywood Update 8-5-16


Hog, Glue Room, and Chipper Deck:
·         Continued installing piping and valves at glue make-up and storage area
·         Completed installation of emergency eye wash station at glue room and caustic unloading area
·         Began  insulating water piping to eye-wash stations

Low Voltage Electrical:
·         Continued installing conduit and wiring to breakroom / restrooms / offices at mezzanine area, west side break & restroom area, and in shipping office
·         Continued installing fire alarm system on metal wall at mezzanine and maintenance shop area
·         Completed installation of power wiring from primary feeder line to WSR transformer, and from transformer to MCC unit inside West-Side Residuals electrical building

Log Pre-Conditioning Vaults:
·         Removed temporary safety fence and installed permanent safety fencing around perimeter of vault water storage pit & vault water return trench to storage pit
·         Installed safety fencing around perimeter of top of vault concrete structure

Plant Build-Out:
·         Began installing toilet accessories in east-side restrooms
·         Continued installing door hardware throughout east and west side restroom and break areas
·         Continued installation of HVAC unit at shipping office, MCC rooms and glue loft area
·         Began installing ceiling grid in upstairs offices at mezzanine area
·         Installed ceiling grid in west-side lunch room
·         Installed sink in QC room (TECO Lab)

Site Paving:
·         Continued excavation and placement of stone for paving between vaults and log infeed deck
·         Finished layout and preparation for placement of reinforcing steel between vaults and log infeed deck for paving
·         Placed concrete paving and performed sawcutting in area between vaults and log infeed deck

East Side & West Side Residuals:
·         Continued installing ductwork to equipment inside building (dry hogs, trim-saws, sander)
·         Continued installing ductwork to truck bins on west-side residual