Hog,
Glue Room, and Chipper Deck:
· Continued
installing piping and valves at glue make-up and storage area
· Completed
installation of emergency eye wash station at glue room and caustic unloading
area
· Began
insulating water piping to eye-wash stations
Low
Voltage Electrical:
· Continued
installing conduit and wiring to breakroom / restrooms / offices at mezzanine
area, west side break & restroom area, and in shipping office
· Continued
installing fire alarm system on metal wall at mezzanine and maintenance shop
area
· Completed
installation of power wiring from primary feeder line to WSR transformer, and
from transformer to MCC unit inside West-Side Residuals electrical building
Log
Pre-Conditioning Vaults:
· Removed
temporary safety fence and installed permanent safety fencing around perimeter
of vault water storage pit & vault water return trench to storage pit
· Installed
safety fencing around perimeter of top of vault concrete structure
Plant
Build-Out:
· Began
installing toilet accessories in east-side restrooms
· Continued
installing door hardware throughout east and west side restroom and break areas
· Continued
installation of HVAC unit at shipping office, MCC rooms and glue loft area
· Began
installing ceiling grid in upstairs offices at mezzanine area
· Installed
ceiling grid in west-side lunch room
· Installed
sink in QC room (TECO Lab)
Site
Paving:
· Continued
excavation and placement of stone for paving between vaults and log infeed deck
· Finished
layout and preparation for placement of reinforcing steel between vaults and
log infeed deck for paving
· Placed
concrete paving and performed sawcutting in area between vaults and log infeed
deck
East
Side & West Side Residuals:
· Continued
installing ductwork to equipment inside building (dry hogs, trim-saws, sander)
· Continued
installing ductwork to truck bins on west-side residual