Winston Plywood Weekly Update- 3-11-16



Foundations:

· No work performed last week (plans are to perform this work when unable to place concrete outside of building due to rain)



Site Utilities:

· No work performed last week,

· Plan to set bollards at corners of building and fire hydrants for concrete paving this week



Buildings:

· Additional louvers have been delivered to side. Additional gutters and downspouts are on order. Contractor will mobilize to site to install louvers, gutters, and downspouts when gutters and downspouts arrive onsite.



Racetrack Piping:

· Pressure testing on lines remains to be performed when water piping is completed

· Trim-out piping and valves to plant equipment



High Voltage Electrical:

· No work performed this week

· Contractor will begin commissioning on balance of electrical gear on 03-28-2016



Low Voltage Electrical:

· Continued terminations in center and north electrical rooms

· Continued installing electrical conduits and cables to chipper deck electrical room

· Continued installing fire alarm piping, boxes, and wiring

· Continued installing cables to MCC’s



Hog Room, Glue Room, Chipper Deck:

· Continued installing handrails around lathe and chipper deck

· Finished installing cross-over deck above No. 2 Lathe infeed



Plant Build-Out:

· Continued laying block walls and setting door frames in east mezzanine area (Restrooms, breakroom, offices, boiler room, air compressor room, and maintenance shop)

· Laid out and delivered materials for modifications to west restroom and breakroom area

· Continued installing roll-up doors (On P-Line at air compressor room, boiler room, and maintenance shop



Plant Piping:

· Continued installing steam and condensate piping to Dryers No. 1, 2, and 3

· Continued installing steam and condensate pipe hangers and piping along east building wall

· Continued installing trim-out and insulation on steam & condensate piping to dryers and presses



Site Paving:

· No work this week

· Contractor on site this week to install paving on east and south sides of plant



Fire Protection System:

· Continued installing sprinkler system at mezzanine office area (ground floor level)

· Continued installing piping for rework of deluge systems in dryers #1 & 2 and installation of new deluge system in dryer #3

· Continued installing hose reels on building columns



Log Conditioning Vaults:

· Placed vault wall “O” and Vault wall “P”

· Continued pre-tying rebar mats for additional vault walls

· Began forming vault wall “Q”

· Installed Tee-Wall at vault wall “L”

· Began forming four thickened floor slabs at vault north ends (vaults 7, 8, 9 & 10)

· Received steel for wall at east side of vault 20

· Received steel for cover over vault water holding tank



Log Pro Equipment Foundations:


· Stripped wall forms and finished tree-length log deck retaining wall



Equipment Foundations (East and West Residuals):

· Continued saw-cutting new openings for east-side residual foundations

· Formed and placed grade beams for east-side truck bin

· Continued pre-tying foundation steel for east-side residuals

· Set forms and placed rebar for truck bin slab and elevated concrete



Winston Plywood & Veneer

· Continued refurbishing and installing Lathes No. 1 & 2

· Continued installing equipment at both clippers, stackers, and pull chains

· Continued painting green-end equipment on lathe lines (decline belts, clippers, stackers, and pull chains)

· Continued electrical installation at Green-End equipment (conduit and power wiring)

· Continued installing electrical service from electrical room to Log Pro equipment (unistrut, cable tray, and conduit)

· Continued refurbishing Dryers No. 1 & 2

· Continued assembly and installation of Dryer No. 1, 2, & 3 infeed and outfeed sections

· Continued making modifications to Stacker for Dryer No. 2 (reverse hand)

· Continued installing dry stacker out-feed roll cases and discharge equipment (transfer equipment to dry stackers

· Continued refurbishing and painting dry-end equipment

· Continued installing electrical power to Dryers 1, 2, & 3

· Continued installing RTO Ducting (From dryers 1 & 2)

· Installed Debarker Rotor assembly and finished debarker

· Boiler contractor began piping from boilers to main, steam header

· Contractor began layout and preparations to rotate RTO Stack to new position