Foundations:
· Began repairs to floor concrete voids and trenches
Site Utilities:
· No work this week
Buildings:
· No work this week
Racetrack Piping:
· No work this week
High Voltage Electrical:
· No work this week
Low Voltage Electrical:
· Completed installing lighting fixtures in Buildings 6, 6A, & 7
· Pulled electrical tray cable to boiler room and glue room
· Continued terminations in center and north electrical room
· Continued installing electrical conduits to chipper deck electrical room
· Completed installing lights in glue room and hog room
· Continued installing fire alarm piping, boxes, and wiring
· Performed 4 underground borings from main plant to fire pump house for fire alarm system
· Performed two additional underground borings: one to existing guard house and one to corner at main entrance/parking lot
Hog Room, Glue Room, Chipper Deck:
· Completed installing support framing for Chipper Deck Electrical Room roofing system; awaiting delivery of EPDM roofing material for installation the week of March 7-11
Plant Build-Out:
· Continued installing HVAC units in both lathe control rooms (Conex boxes)
· Continued laying block walls and set door frames in east mezzanine area (Restrooms, breakroom, offices, boiler room, air compressor room, and maintenance shop)
· Removed block wall at west-side break room; wall is to be relocated 7’-4” to the east or original location
Plant Piping:
· Continued installing steam and condensate piping to Dryers No. 1, 2, and 3
· Continued installing steam and condensate piping along east building wall to green-end and vaults
· Continued installing insulation on steam and condensate piping
· Continued running steam and condensate piping along west side of presses
· Installed steam trap systems at infeed to Dryers No. 1 & 2
· Began changing steam and condensate piping on presses (moving steam piping tree to north side and condensate to south side)
Site Paving:
· No work this week
Fire Protection System:
· Installed sprinkler system at mezzanine office area
· Built sprinkler riser at building 11
· Continued installing sprinklers in ceiling at building 11
· Received piping for rework of deluge systems in dryers #1 & 2 and installation of new deluge system in dryer #3
Log Conditioning Vaults:
· Placed vault walls “L” and “M”, and tee sections at vault walls “I” and “J”
· Completed forming & installation of rebar, and placed concrete floor slab for Vaults No. 17, 18, 19, & 20
· Continued pre-tying rebar mats for additional vault walls
· Continued wet curing of floor slab for Vaults No. 17, 18, 19, & 20 with burlap blankets
Log Pro Equipment Foundations:
· Continued work on concrete wall at tree-length log deck
Equipment Foundations (East and West Residuals):
· Performed layout and began saw-cutting new openings in paving for east-side residual foundations
Winston Plywood & Veneer
· Continued refurbishing and installing Lathes No. 1 & 2
· Continued installing equipment at both clippers, stackers, and pull chains
· Continued refurbishing Dryers No. 1 & 2
· Continued electrical installation at Green-End equipment (conduit and power wiring)
· Continued assembly and installation of Dryer No. 1, 2, & 3 I/F and O/F Sections
· Continued installing electrical service from electrical room to Log Pro equipment (unistrut, cable tray, and conduit)
· Continued installing electrical conduit from electrical room to Green-End equipment
· Continued installing electrical power to Dryers 2 & 3
· Continued making modifications to Stacker for Dryer No. 2 (reverse hand)
· Continued refurbishing and painting dry-end equipment