Foundations:
· Continued repairs to floor concrete voids and trenches; placed concrete in both trenches to restrooms
Site Utilities:
· Contractor installed final three fire hydrants at north end of building (on both sides of vaults and holding tank)
Buildings:
· Building installation contractor onsite addressing warranty issues
Racetrack Piping:
· Pressure testing on lines remains to be performed
High Voltage Electrical:
· Pending Change Order installation of additional louvers remains to be performed. Louvers have arrived and are onsite.
· Pending Change Order for additional gutters and downspouts is forthcoming.
Low Voltage Electrical:
· Continued terminations in center and north electrical room
· Continued installing electrical conduits and cables to chipper deck electrical room
· Continued installing fire alarm piping, boxes, and wiring
Hog Room, Glue Room, Chipper Deck:
· Installed EPDM electrical room roofing
· Installed handrails around chipper deck
· Installed cross-over deck above No. 1 Lathe infeed deck
· Installed access stairs to west end of lathe deck (beside No. 1 lathe)
Plant Build-Out:
· Continued laying block walls and setting door frames in east mezzanine area (Restrooms, breakroom, offices, boiler room, air compressor room, and maintenance shop)
Plant Piping:
· Continued installing steam and condensate piping to Dryers No. 1, 2, and 3
· Continued installing steam and condensate pipe hangers and piping along east building wall to green-end
· Installed steam and condensate piping across green-end (Building No. 9) and out north wall of building
· Continued installing insulation on steam and condensate piping
Site Paving:
· No work this week
· In process of resolving contractor coordination issues with access to paving site
Fire Protection System:
· Continued installing sprinkler system at mezzanine office area (ground floor level)
· Continued installing sprinklers in ceiling at Building 11
· Began installing piping for rework of deluge systems in dryers #1 & 2 and installation of new deluge system in dryer #3
· Began installing hose reels on columns in Buildings 1, 3, & 5
Log Conditioning Vaults:
· Placed vault wall “N” and tee section at north end of Vault “K”
· Continued pre-tying rebar mats for additional vault walls
· Began forming vault wall “O”
Log Pro Equipment Foundations:
· Placed concrete retaining wall at north end of tree-length log deck to debarker
Equipment Foundations (East and West Residuals):
· Continued saw-cutting new openings for east-side residual foundations
· Began breaking and removing concrete for east-side residuals
· Began pre-tying foundation steel for east-side residuals
· Began layout and forming for truck bin foundation on east-side residuals
Winston Plywood & Veneer
· Continued refurbishing and installing Lathes No. 1 & 2
· Continued installing equipment at both clippers, stackers, and pull chains
· Painted green-end equipment on lathe lines (decline belts, clippers, stackers, and pull chains)
· Continued electrical installation at Green-End equipment (conduit and power wiring)
· Continued installing electrical service from electrical room to Log Pro equipment (unistrut, cable tray, and conduit)
· Continued refurbishing Dryers No. 1 & 2
· Continued assembly and installation of Dryer No. 1, 2, & 3 infeed and outfeed sections
· Continued making modifications to Stacker for Dryer No. 2 (reverse hand)
· Continued installing dry stacker out-feed roll cases and discharge equipment
· Continued refurbishing and painting dry-end equipment
· Continued installing electrical power to Dryers 2 & 3
· Building installation contractor onsite addressing warranty issues
Racetrack Piping:
· Pressure testing on lines remains to be performed
High Voltage Electrical:
· Pending Change Order installation of additional louvers remains to be performed. Louvers have arrived and are onsite.
· Pending Change Order for additional gutters and downspouts is forthcoming.
Low Voltage Electrical:
· Continued terminations in center and north electrical room
· Continued installing electrical conduits and cables to chipper deck electrical room
· Continued installing fire alarm piping, boxes, and wiring
Hog Room, Glue Room, Chipper Deck:
· Installed EPDM electrical room roofing
· Installed handrails around chipper deck
· Installed cross-over deck above No. 1 Lathe infeed deck
· Installed access stairs to west end of lathe deck (beside No. 1 lathe)
Plant Build-Out:
· Continued laying block walls and setting door frames in east mezzanine area (Restrooms, breakroom, offices, boiler room, air compressor room, and maintenance shop)
Plant Piping:
· Continued installing steam and condensate piping to Dryers No. 1, 2, and 3
· Continued installing steam and condensate pipe hangers and piping along east building wall to green-end
· Installed steam and condensate piping across green-end (Building No. 9) and out north wall of building
· Continued installing insulation on steam and condensate piping
Site Paving:
· No work this week
· In process of resolving contractor coordination issues with access to paving site
Fire Protection System:
· Continued installing sprinkler system at mezzanine office area (ground floor level)
· Continued installing sprinklers in ceiling at Building 11
· Began installing piping for rework of deluge systems in dryers #1 & 2 and installation of new deluge system in dryer #3
· Began installing hose reels on columns in Buildings 1, 3, & 5
Log Conditioning Vaults:
· Placed vault wall “N” and tee section at north end of Vault “K”
· Continued pre-tying rebar mats for additional vault walls
· Began forming vault wall “O”
Log Pro Equipment Foundations:
· Placed concrete retaining wall at north end of tree-length log deck to debarker
Equipment Foundations (East and West Residuals):
· Continued saw-cutting new openings for east-side residual foundations
· Began breaking and removing concrete for east-side residuals
· Began pre-tying foundation steel for east-side residuals
· Began layout and forming for truck bin foundation on east-side residuals
Winston Plywood & Veneer
· Continued refurbishing and installing Lathes No. 1 & 2
· Continued installing equipment at both clippers, stackers, and pull chains
· Painted green-end equipment on lathe lines (decline belts, clippers, stackers, and pull chains)
· Continued electrical installation at Green-End equipment (conduit and power wiring)
· Continued installing electrical service from electrical room to Log Pro equipment (unistrut, cable tray, and conduit)
· Continued refurbishing Dryers No. 1 & 2
· Continued assembly and installation of Dryer No. 1, 2, & 3 infeed and outfeed sections
· Continued making modifications to Stacker for Dryer No. 2 (reverse hand)
· Continued installing dry stacker out-feed roll cases and discharge equipment
· Continued refurbishing and painting dry-end equipment
· Continued installing electrical power to Dryers 2 & 3