Winston Plywood Weekly Update-March 11



Foundations:

· Continued repairs to floor concrete voids and trenches; placed concrete in both trenches to restrooms

Site Utilities:

· Contractor installed final three fire hydrants at north end of building (on both sides of vaults and holding tank)

Buildings:

· Building installation contractor onsite addressing warranty issues

Racetrack Piping:

· Pressure testing on lines remains to be performed

High Voltage Electrical:

· Pending Change Order installation of additional louvers remains to be performed. Louvers have arrived and are onsite.

· Pending Change Order for additional gutters and downspouts is forthcoming.
Low Voltage Electrical:

· Continued terminations in center and north electrical room

· Continued installing electrical conduits and cables to chipper deck electrical room

· Continued installing fire alarm piping, boxes, and wiring

Hog Room, Glue Room, Chipper Deck:

· Installed EPDM electrical room roofing

· Installed handrails around chipper deck

· Installed cross-over deck above No. 1 Lathe infeed deck

· Installed access stairs to west end of lathe deck (beside No. 1 lathe)

Plant Build-Out:

· Continued laying block walls and setting door frames in east mezzanine area (Restrooms, breakroom, offices, boiler room, air compressor room, and maintenance shop)

Plant Piping:

· Continued installing steam and condensate piping to Dryers No. 1, 2, and 3

· Continued installing steam and condensate pipe hangers and piping along east building wall to green-end

· Installed steam and condensate piping across green-end (Building No. 9) and out north wall of building

· Continued installing insulation on steam and condensate piping

Site Paving:

· No work this week

· In process of resolving contractor coordination issues with access to paving site

Fire Protection System:

· Continued installing sprinkler system at mezzanine office area (ground floor level)

· Continued installing sprinklers in ceiling at Building 11

· Began installing piping for rework of deluge systems in dryers #1 & 2 and installation of new deluge system in dryer #3

· Began installing hose reels on columns in Buildings 1, 3, & 5

Log Conditioning Vaults:

· Placed vault wall “N” and tee section at north end of Vault “K”

· Continued pre-tying rebar mats for additional vault walls

· Began forming vault wall “O”

Log Pro Equipment Foundations:

· Placed concrete retaining wall at north end of tree-length log deck to debarker

Equipment Foundations (East and West Residuals):

· Continued saw-cutting new openings for east-side residual foundations

· Began breaking and removing concrete for east-side residuals

· Began pre-tying foundation steel for east-side residuals

· Began layout and forming for truck bin foundation on east-side residuals

Winston Plywood & Veneer

· Continued refurbishing and installing Lathes No. 1 & 2

· Continued installing equipment at both clippers, stackers, and pull chains

· Painted green-end equipment on lathe lines (decline belts, clippers, stackers, and pull chains)

· Continued electrical installation at Green-End equipment (conduit and power wiring)

· Continued installing electrical service from electrical room to Log Pro equipment (unistrut, cable tray, and conduit)

· Continued refurbishing Dryers No. 1 & 2

· Continued assembly and installation of Dryer No. 1, 2, & 3 infeed and outfeed sections

· Continued making modifications to Stacker for Dryer No. 2 (reverse hand)

· Continued installing dry stacker out-feed roll cases and discharge equipment

· Continued refurbishing and painting dry-end equipment

· Continued installing electrical power to Dryers 2 & 3