Tuesday, June 7, 2016

Winston Plywood Update 6-3-16


Site Utilities

· Continued installing pipe bollards around fire hydrants on south and west sides of plywood building and filled with concrete

· Fire water tank was filled from City of Louisville water line and hydro test was performed on tank

Hog, Glue Room, and Chipper Pad

· Continued cleanup on blocks and area around glue make-up and storage rooms

· Began installing air conditioning units in glue make-up area

Low Voltage Electrical:


· Continued installing conduit and wiring to breakroom / restrooms / offices at mezzanine area

· Completed pulling cable from switchgear to Vault MCC unit

· Began terminations for electrical service to Vault MCC unit

· Continued installation of Fire Alarm System controls



Plant Build-Out:


· Completed weld-out on overhead crane in maintenance shop

· Began painting of building door frames

· Began finish-coat painting in lower floor offices at mezzanine area





Plant Piping:

· Continued installing steam and condensate piping to Dryers No. 1, 2, and 3

· Continued steam and condensate piping in boiler room

· Received and set HPR unit in boiler room

· Completed installing air piping in compressor room

· Installed piping to connect oil coolers to air compressor in compressor room

· Connected piping to air dryers in compressor room



Site Paving:

· Performed excavation and grading on strip of remaining paving between vault infeed aprons and paving strip north of building 10

· Began placing rebar in area between vault apron and building 10



Fire Protection System:

· Continued installing hose reels at building columns

· Continued installing overhead feeder lines to Dryers 1 & 2



Log Conditioning Vaults:

· Continued construction of 5’ concrete knee wall along north side of vault drain ditch to holding pit

· Continued installation of steel framework for stoop over ditch along north wall on vaults

· Completed pulling power cables to vault MCC unit

· Continued backfill and compaction of material along west and north walls at vaults



Equipment Foundations (East and West Residuals):

· Completed installing handrails around hog tower at mid-level concrete floor

· Completed installing access stairs to hog tower concrete floor (second elevation)

· Completed installing access stairs to hog tower (third elevation)

· Completed installing support frame for conveyor feeding East-Side Residual truck bins

· Completed installing frames and conveyor structures for residuals from screens and hog to truck bin



RTO Rebuild

· Completed pulling power cables to MCC unit

· Completed installing duct supports for RTO duct from building to RTO

· Continued installing ductwork from dryers to RTO



Winston Plywood & Veneer

· Continued refurbishing and installing Lathes No. 1 & 2 and related equipment (continued focus on east lathe line)

· Continued installing equipment at both clippers, green stackers, and pull chains (continued focus on east lathe line)

· Continued refurbishing chippers and conveyors for green-end by products

· Continued cleaning and painting green-end and dry end equipment and support steel

· Continued electrical installation at Green-End equipment (conduit and power wiring)

· Continued installing electrical service from electrical room to Log Pro equipment

· Continued assembly and installation of Dryer No. 1, 2, & 3 infeed and outfeed sections

· Continued making modifications to Stackers for Dryers No. 2 & 3

· Continued installing electrical power to Dryers 1, 2, & 3

· Continued installing air piping to veneer dryers

· Continued installing glue lay-up line equipment

· Continued installing trim-saw equipment and plywood stacker platforms and stairs

· Continued installing two trusses and conveyors from bark hog tower to top of east side residuals truck bins

· Completed saw-cutting and breaking paving concrete for lathe infeed deck foundations; installed foundations & base plates

· Continued performing preliminary test runs on No. 1 Lathe line motors and equipment

· Continued construction of knife grinding room