Monday, June 20, 2016

Winston Plywood Weekly Update- 6-17-16

Finished concrete paving between plyblock kickout pockets and vaults

Northeast Corner – Log Ramp Construction
  • Performed layout, sawcutting, and demo of existing concrete for installation of wall footings
  • Installed rebar and placed both east and west wall footings
  • Installed rebar and set forms for placement of west concrete wall
Hog, Glue Room, and Chipper Pad
  • Continued installing air conditioning units in glue make-up area
  • Continued installing piping at glue makeup and storage area
  • Continued installing piping from glue room to lay-up line equipment
Low Voltage Electrical:
  • Continued installing conduit and wiring to breakroom / restrooms / offices at mezzanine area
  • Continued checkout on Fire Alarm System controls
Plant Build-Out:
  • Continued painting building door frames on exterior of main building
  • Continued installing stud wall framing on boiler room
  • Completed laying blocks on breakroom at west side of plant
  • Completed laying blocks at shipping office inside access door to plant
  • Continued installing rails for overhead crane system at lathe deck
  • Began placing wall tile in restrooms at mezzanine area
  • Grid system for ceiling panels was installed in rooms at mezzanine area
Plant Piping:
  • Continued installing steam and condensate piping to Dryers No. 1, 2, and 3
  • Continued steam and condensate piping in boiler room
  • Continued piping for High Pressure Receiver and pump system
  • Continued checkout and commissioning on air compressors and air dryers
Plant Ducting
  • Continued installing ducting inside plant (ran line from dry hog building, across the main drive through plant site)
  • Continued installing exterior ducting along the west wall of plant
Site Paving:
  • Placed section of concrete in roadway between vaults and plyblock kickout pockets
  • Began work on paving at access to main door to plant (northwest corner of building)
Fire Protection System:
  • Continued installing hose reels at building columns
  • Continued installing overhead feeder lines to Dryers 1 & 2
  • Performed tests on fire pumps (both jockey pump and main diesel-driven pump)
Log Conditioning Vaults:
  • Completed placing roof system over vault water holding pit
  • Placed roofing material on stoop over water return trench on north side of vaults
  • Began installing doors on log conditioning vaults
RTO Rebuild
  • Continued installing insulation on ductwork over south roadway (ductwork from building to RTO)
  • Continued installing new gas train and piping for RTO
  • Continued refurbishing RTO equipment
East and West Side Residuals
  • Continued installing roofing on electrical building for West Side Residuals
  • Installed ceiling in west side residual electrical room
  • Painted west side residuals electrical building
  • Set MCC units in west side residuals electrical building
  • Placed concrete around perimeter of bark hog tower
  • Received and began erecting west-side truck bins
Winston Plywood & Veneer
  • Continued refurbishing and installing Lathes No. 1 & 2 and related equipment (continued focus on east lathe line)
  • Continued installing equipment at both clippers, green stackers, and pull chains (continued focus on east lathe line)
  • Continued refurbishing chippers and conveyors for green-end by products (on chipper deck)
  • Continued cleaning and painting green-end and dry end equipment and support steel
  • Continued electrical installation at Green-End equipment (conduit and power wiring)
  • Continued installing electrical service from electrical room to Log Pro equipment
  • Continued assembly and installation of Dryer No. 1, 2, & 3 infeed and outfeed sections
  • Continued making modifications to Stackers for Dryers No. 2 & 3
  • Continued installing electrical power to Dryers 1, 2, & 3
  • Continued installing air piping to veneer dryers and other mill equipment
  • Continued installing glue lay-up line equipment and access stairs / platforms
  • Continued installing trim-saw equipment and plywood stacker platforms and stairs
  • Continued installing two trusses and conveyors from bark hog tower to top of east side residuals truck bins (over truck bins)
  • Continued installing chutework from bark and block conveyors to bark hog
  • Continued installing chutework at transitions from tree-length infeed deck and debarker conveyor, and from block saw equipment block conveyor to hog I/F system
  • Continued performing preliminary test runs on No. 1 Lathe line motors and equipment
  • Continued installing piping on roof of vaults
  • Began installing doors on log pre-conditioning vaults
  • Set RTO ID fan on new foundations
  • Continued installing chutework at bark hog and at conveyor transition points from debark and Log Pro cut up system
  • Installed belting on material handling conveyors
  • Installed saw blades on cutup system
  • Began erection of building over cutup system
  • Continued construction of decks to core kickout pockets
  • Continued refurbishing and installing core chippers on chipper deck
  • Began installing insulation on economizers and boilers in boiler room
Installing doors on plyblock preconditioning vaults

Installing saw blades on cutup system


Installation of ductwork over main drive inside plant (from dry hogs)