Northeast Corner – Log Ramp Construction
- Performed layout, sawcutting, and demo of existing concrete for installation of wall footings
- Installed rebar and placed both east and west wall footings
- Installed rebar and set forms for placement of west concrete wall
- Continued installing air conditioning units in glue make-up area
- Continued installing piping at glue makeup and storage area
- Continued installing piping from glue room to lay-up line equipment
- Continued installing conduit and wiring to breakroom / restrooms / offices at mezzanine area
- Continued checkout on Fire Alarm System controls
- Continued painting building door frames on exterior of main building
- Continued installing stud wall framing on boiler room
- Completed laying blocks on breakroom at west side of plant
- Completed laying blocks at shipping office inside access door to plant
- Continued installing rails for overhead crane system at lathe deck
- Began placing wall tile in restrooms at mezzanine area
- Grid system for ceiling panels was installed in rooms at mezzanine area
- Continued installing steam and condensate piping to Dryers No. 1, 2, and 3
- Continued steam and condensate piping in boiler room
- Continued piping for High Pressure Receiver and pump system
- Continued checkout and commissioning on air compressors and air dryers
- Continued installing ducting inside plant (ran line from dry hog building, across the main drive through plant site)
- Continued installing exterior ducting along the west wall of plant
- Placed section of concrete in roadway between vaults and plyblock kickout pockets
- Began work on paving at access to main door to plant (northwest corner of building)
- Continued installing hose reels at building columns
- Continued installing overhead feeder lines to Dryers 1 & 2
- Performed tests on fire pumps (both jockey pump and main diesel-driven pump)
- Completed placing roof system over vault water holding pit
- Placed roofing material on stoop over water return trench on north side of vaults
- Began installing doors on log conditioning vaults
- Continued installing insulation on ductwork over south roadway (ductwork from building to RTO)
- Continued installing new gas train and piping for RTO
- Continued refurbishing RTO equipment
- Continued installing roofing on electrical building for West Side Residuals
- Installed ceiling in west side residual electrical room
- Painted west side residuals electrical building
- Set MCC units in west side residuals electrical building
- Placed concrete around perimeter of bark hog tower
- Received and began erecting west-side truck bins
Winston Plywood & Veneer
- Continued refurbishing and installing Lathes No. 1 & 2 and related equipment (continued focus on east lathe line)
- Continued installing equipment at both clippers, green stackers, and pull chains (continued focus on east lathe line)
- Continued refurbishing chippers and conveyors for green-end by products (on chipper deck)
- Continued cleaning and painting green-end and dry end equipment and support steel
- Continued electrical installation at Green-End equipment (conduit and power wiring)
- Continued installing electrical service from electrical room to Log Pro equipment
- Continued assembly and installation of Dryer No. 1, 2, & 3 infeed and outfeed sections
- Continued making modifications to Stackers for Dryers No. 2 & 3
- Continued installing electrical power to Dryers 1, 2, & 3
- Continued installing air piping to veneer dryers and other mill equipment
- Continued installing glue lay-up line equipment and access stairs / platforms
- Continued installing trim-saw equipment and plywood stacker platforms and stairs
- Continued installing two trusses and conveyors from bark hog tower to top of east side residuals truck bins (over truck bins)
- Continued installing chutework from bark and block conveyors to bark hog
- Continued installing chutework at transitions from tree-length infeed deck and debarker conveyor, and from block saw equipment block conveyor to hog I/F system
- Continued performing preliminary test runs on No. 1 Lathe line motors and equipment
- Continued installing piping on roof of vaults
- Began installing doors on log pre-conditioning vaults
- Set RTO ID fan on new foundations
- Continued installing chutework at bark hog and at conveyor transition points from debark and Log Pro cut up system
- Installed belting on material handling conveyors
- Installed saw blades on cutup system
- Began erection of building over cutup system
- Continued construction of decks to core kickout pockets
- Continued refurbishing and installing core chippers on chipper deck
- Began installing insulation on economizers and boilers in boiler room
Installing doors on plyblock preconditioning vaults |
Installing saw blades on cutup system |
Installation of ductwork over main drive inside plant (from dry hogs) |