Site Utilities
· Continued installing drain system north of Building 5 (Installing inverts and 15” drain pipe)
Northeast Corner – Log Ramp Construction
· Placed east-side and west-side concrete walls.
· Removed forms and began placing fill material
Hog, Glue Room, and Chipper Deck
· Continued installing piping and valves at glue makeup and storage area
· Continued installing piping from glue room to lay-up line equipment
Low Voltage Electrical:
· Continued installing conduit and wiring to breakroom / restrooms / offices at mezzanine area
· Installed lighting in TECO Lab building
Plant Build-Out:
· Continued painting building door frames on exterior of main building
· Completed installing stud wall framing on boiler room and air compressor room
· Continued placing wall tile in restrooms at mezzanine area
· Began placing floor tile in restrooms at mezzanine area
· Began installing sheeting on stud walls at mezzanine area
Plant Piping:
· Continued steam and condensate piping in boiler room
· Continued installing pumps and piping for High Pressure Receiver
· Began installing insulation on High Pressure Receiver piping
· Continued checkout and commissioning on air compressors and air dryers
· Began fabrication of piping to cross truss across north roadway (piping to vaults)
Plant Ducting
· Continued installing ducting inside plant (to trim-saw line and dry hog building)
· Continued installing exterior ducting along the west wall of plant
Site Paving:
· Continued demo work and paving at access to main door to plant (front door at northwest corner of building)
· Continued excavation, backfill, and compaction on roadway north of Building 5
Log Conditioning Vaults:
· Completed installing doors on log conditioning vaults
· Began installing counterweights and hydraulic cylinders on vault doors
· Continued weld-out on piping on vault heating system
· Continued electrical service to components at vaults
· Installed four concrete pads in bottom of vault water holding tank (for pump mounting)
RTO Rebuild
· Completed installing insulation on ductwork over south roadway (ductwork from building to RTO)
· Completed installing new gas train and piping for RTO
· Continued refurbishing RTO duct and equipment
· Finished setting RTO ID fan and motor
· Connected electrical power to RTO ID fan motor
· Continued installing conduit and power to RTO duct controls and devices
East and West Side Residuals
· Continued erecting west-side truck bins
· Continued installing ducting from building to west-side residuals cyclones
· Began fabricating and installing chutework from belt conveyor frames into east-side residuals truck bins
· Continued weld-out on structures and framework for belt conveyors to truck bins on east side
Winston Plywood & Veneer
· Continued refurbishing and installing Lathes No. 1 & 2 and related equipment (continued focus on east lathe line)
· Continued installing equipment at both clippers, green stackers, and pull chains (continued focus on east lathe line)
· Continued checkout on No. 2 lathe line equipment (clipper & stackers)
· Continued refurbishing chippers and conveyors for green-end by products (on chipper deck)
· Continued cleaning and painting green-end and dry end equipment and support steel
· Continued electrical installation at Green-End equipment (conduit and power wiring)
· Continued electrical checkout on Log Pro equipment
· Completed installing framework for building over cut-up saws and installed roof decking
· Completed installing framework for building over debarker (no roof decking installed)
· Continued assembly and installation of Dryer No. 1, 2, & 3 infeed and outfeed sections
· Continued making modifications to Stackers for Dryers No. 2 & 3
· Continued installing electrical power to No. 1, 2, & 3 dryer components
· Continued installing glue lay-up line mechanical and electrical equipment
· Continued installing trim-saw equipment and stacker platforms and stairs
· Continued installing two trusses and conveyors from bark hog tower to top of east side residuals truck bins (over truck bins)
· Continued installing chutework from bark and block conveyors to bark hog
· Continued installing chutework at transitions from tree-length infeed deck and debarker conveyor, and from block saw equipment block conveyor to hog I/F system
· Continued performing preliminary test runs on No. 1 Lathe line motors and equipment
· Continued installing chutework at bark hog and at conveyor transition points from debark and Log Pro cut up system
· Installed belting on material handling conveyors
· Installed saw blades on cutup system
· Continued construction of decks to core kickout pockets
· Continued refurbishing and installing core chippers on chipper deck
· Continued installing insulation on economizers and boilers in boiler room
· Continued fabrication of infeed deck to No. 2 lathe step-feeder
· Continued fabrication and installation of support steel for No. 1 lathe step feeder
· Continued fabrication and installation of fines & overs conveyors at east-side residuals shaker screens
· Began fabrication and installation of chute work from conveyors to shaker screen infeed pans