Monday, July 25, 2016

Winston Plywood Update 7-22-16


Foundations:
·         Continued making repairs to old floor slab (at west side of No. 2 lathe line pull chain)

Site Utilities:
·         Completed installing pipe bollards at corners of building
·         Continued placing concrete in treads on stairs at lathe access areas

Northeast Corner – Log Ramp Construction Area:
·         Completed installing guard rails on infeed ramp to tree-length log deck

Hog, Glue Room, and Chipper Deck:
·         Continued installing piping and valves at glue makeup and storage area
·         Continued installing and refurbishing equipment on chipper deck
·         Installed emergency eye wash station at glue room and caustic unloading area

Low Voltage Electrical:
·         Continued installing conduit and wiring to breakroom / restrooms / offices at mezzanine area and shipping office
·         Continued installing fire alarm system on metal wall at mezzanine and maintenance shop area
·         Completed electrical connection to 5-ton overhead crane at lathe deck

Log Pre-Conditioning Vaults:
·         Completed cleaning holding pit for vault water
·         Completed final cleaning inside vaults
·         Began placing plywood blocks inside vaults
·         Continued installing pumps and piping on vault hot-water system (WPV/BMI)

Plant Build-Out:
·         Completed installing bathroom fixtures in east-side restrooms
·         Continued installing bathroom fixtures in west-side restrooms
·         Continued running ductwork and installed grills in mezzanine area
·         Continued installing sheeting in maintenance shop, boiler room, and air compressor room
·         Completed installing ceiling grid in west-side restrooms
·         Continued installing roof joists in west-side lunch room
·         Completed installing tile in west-side restrooms (walls and floor)
·         Completed installing stairs and handrails to upper floor access on west side of mezzanine
·         Completed installing fence around storage area on upper floor at mezzanine

Site Paving:
·         Continued excavation, backfill, and compaction of material in area north of Building 5 and west of Log Conditioning Vaults for paving
·         Completed grading for paving around east side of log infeed deck to debarker
·         Began excavation and placement of stone for paving between vaults and log infeed deck

RTO Rebuild:
·         Continued installing insulation on RTO duct (Completed north-side duct and began installing on south-side duct)
·         Continued installing conduit and power to RTO duct controls and devices

East Side & West Side Residuals:
·         Continued fabricating and installing guards for conveyor drive units
·         Continued installing ductwork and truck bins on west-side residuals

Winston Plywood & Veneer:
·         Continued installing hydraulic components for cylinders on vault doors
·         Installed and piped in vault water circulation pumps
·         Continued running logs through debarker and cut-up system, and kicked blocks out into log pockets
·         Began placing logs in vaults
·         Continued checkout and peeling cold logs on Lathe No. 2
·         Continued checkout on No. 2 lathe line equipment (clipper & stackers)
·         Continued refurbishing chippers and conveyors for green-end by products (on chipper deck)
·         Continued electrical installation at Green-End equipment (conduit and power wiring)
·         Continued electrical checkout on Log Pro equipment
·         Continued relocation of saw frames on cut-up system
·         Continued installing piping from glue room to lay-up line equipment
·         Continued installing trash conveyor for lay-up line to hog room
·         Continued details on installation of Dryer No. 1 & 2 infeed and outfeed sections
·         Continued testing dryer infeed systems and main dryer chains and rolls in No. 1 & 2 dryers
·         Continued installing glue lay-up line mechanical and electrical equipment
·         Continued details on installing trim-saw equipment
·         Continued construction of decks to core kickout pockets
·         Continued refurbishing core kickout pockets
·         Continued fabrication of infeed deck to No. 2 Lathe step-feeder and began installing infeed system to No. 1 Lathe step-feeder
·         Completed fabrication and installation of support steel for No. 1 lathe step feeder
·         Continued installing components on east side truck bins and infeed conveyors
·         Set trailer under transfer conveyor for bark from debarking system







Thursday, July 21, 2016

Louisville PD Receives a ThankYou

Thanks Winston Plywood for your support of our local law enforcement.!


Tuesday, July 19, 2016

Winston Plywood Update 7-15-16


Site Utilities:
·         Continued installing pipe bollards at corners of building
·         Placed concrete in treads on stairs at lathe access areas

Northeast Corner – Log Ramp Construction Area:
·         Finished grading and cleanup in northeast corner for log handling equipment to deliver logs to tree-length ramp
·         Installed guard rails on infeed ramp to tree-length log deck

Hog, Glue Room, and Chipper Deck:
·         Continued installing piping and valves at glue makeup and storage area
·         Continued installing and refurbishing equipment on chipper deck

Low Voltage Electrical:
·         Continued installing conduit and wiring to breakroom / restrooms / offices at mezzanine area and shipping office
·         Continued installing fire alarm system on metal wall at mezzanine and maintenance shop area

Log Pre-Conditioning Vaults:
·         Began cleaning holding pit for vault water
·         Continued final cleaning inside vaults

Plant Build-Out:
·         Continued installing bathroom fixtures in east-side restrooms
·         Continued running ductwork and installed grills in mezzanine area
·         Completed installing sheeting on stud walls at mezzanine area and continued installing sheeting in maintenance shop, boiler room, and air compressor room
·         Continued installing ceiling grid in west-side restrooms
·         Installed partial roof joists in west-side lunch room
·         Installed access stairs to mezzanine area (handrails remain to be installed)
·         Installed sheetrock in offices on upper floor at mezzanine and began tape & float
·         Installed fence around storage area on upper floor at mezzanine
·         Began installing toilet fixtures on west-side restrooms
·         Began installing wall tile in west-side restrooms

Plant Piping:
·         Completed installing insulation on piping in boiler room at HPR and DA tank
·         Continued checkout and commissioning on air compressors and air dryers
·         Continued fabrication of piping to cross the truss across north roadway (piping to vaults)
·         Continued installing piping from dryer wash-water pit to vaults

Fire Suppression:
·         Continued installing hose reels at building columns
·         Continued installing sprinkler heads in automatic systems throughout the plant
·         Installed sprinkler piping around step feeder structure at No. 1 Lathe

Site Paving:
·         Continued excavation, backfill, and compaction of material in area north of Building 5 and west of Log Conditioning Vaults for paving
·         Continued grading for paving around east side of log infeed deck to debarker

RTO Rebuild:
·         Continued refurbishing RTO duct and equipment
·         Continued installing insulation on RTO duct
·         Installed access stairs to RTO duct platform
·         Completed fabrication and weld-out on transition duct from RTO ID fan to RTO stack
·         Continued installing conduit and power to RTO duct controls and devices

East Side & West Side Residuals:
·         Continued fabricating and installing by –products handling conveyors and equipment (East Side)
·         Continued pulling wiring to by-products conveyors and equipment (East Side)
·         Continued installing plating and chutework at transitions between conveyors (East Side)
·         Continued fabricating and installing guards for conveyor drive units
·         Continued installing foundations on West-Side Residuals

Winston Plywood & Veneer:
·         Continued installing hydraulic components for cylinders on vault doors
·         Modified foundations for vault water circulation pumps
·         Received two vault water circulation pumps
·         Ran additional logs through debarker and cut-up system, and kicked blocks out into log pocket
·         Continued refurbishing and installing Lathes No. 1 & 2 and related equipment (continued focus on east lathe line)
·         Continued installing equipment at both clippers, green stackers, and pull chains (continued focus on east lathe line)
·         Continued checkout on No. 2 lathe line equipment (clipper & stackers)
·         Ran first blocks through Lathe No. 2
·         Continued refurbishing chippers and conveyors for green-end by products (on chipper deck)
·         Continued electrical installation at Green-End equipment (conduit and power wiring)
·         Continued electrical checkout on Log Pro equipment
·         Relocated 2 cut-up saw frames
·         Continued installing piping from glue room to lay-up line equipment
·         Continued installing trash conveyor for lay-up line to hog room
·         Continued details on installation of Dryer No. 1, 2, & 3 infeed and outfeed sections
·         Continued installing electrical power to No. 1, 2, & 3 dryer components
·         Began testing dryer infeed systems and main dryer chains and rolls in No. 1 & 2 dryers
·         Continued installing glue lay-up line mechanical and electrical equipment
·         Continued details on installing trim-saw equipment
·         Continued installing chute work at transitions on by-products handling conveyors at ESR
·         Continued installing drive components on miscellaneous ESR conveyors
·         Continued performing preliminary test runs and program changes on No. 1 Lathe line motors and equipment
·         Continued construction of decks to core kickout pockets
·         Continued refurbishing core kickout pockets
·         Continued fabrication of infeed deck to No. 2 Lathe step-feeder and began installing infeed system to No. 1 Lathe step-feeder
·         Continued fabrication and installation of support steel for No. 1 lathe step feeder
·         Continued fabrication and installation of fines & overs conveyors at east-side residuals shaker screens; continued installing drive components and safety guarding
·         Continued installing components on east side truck bins and infeed conveyors




Saturday, July 16, 2016

Meeting Agenda July 19

CITY OF LOUISVILLE

TUESDAY, JULY 19, 2016  


REGULAR MEETING AGENDA  5:30 P.M.

  1. CALL TO ORDER
  2. INVOCATION
  3. PLEDGE OF ALLEGIANCE TO FLAG
  4. APPROVAL OF MINUTES

  1. NEW BUSINESS
    1. Library report:   Beth Edwards
    2. Update on Airport projects:  Mike Forster
      1. Authorize payment of invoice to Davidson Hauling for $86,212.85
      2. Additional Airport business
    3. Unclean Property
      1. Hearing on 312 Pond Street, owned by Linda Cooper Triplett,
      2. Hearing on 112 Kenndey, owned by SKL Investments
      3. 105 Terry Lane- Phyllis Peden
    4. Alternate projects- Street bids
    5. Zoning and Comprehensive Plan (Slaughter & Associates)- set public hearing date
    6. Appointments to Historic Preservation Commission for three year terms  ending 8-1-2019
      1. Edna Prisock
      2. Annette Crabtree
    7. Notice for bids for Landfill cell construction
    8. Police Department Policy
      1. Addition to “In Car Video Policy”-  see enclosed
      2. Addition to “Fire Arms Policy”- see enclosed
    9. Authorize the Mayor to sign Memorandum on Wireless Communication
    10. E911 training
      1. “Crisis Call and Stress Management”  on August 15-16, at Golden Moon Hotel Casino,  for Vera McCarty and one other dispatcher, $300 registration, reimbursable
      2. “NAED Emergency Telecommunicator Course”  on August 22-26, at Neshoba County Emergency Center, for Patricia Coleman, $395.00, reimbursable
    11. Parks and Recreation training, for Todd McCullough, “Urban Forestry & Green Infrastructure Conference”, July 28-29, in Gulfport, Registration $95.00 plus meals and mileage

  1. OTHER BUSINESS
  2. ADJOURN



 

Monday, July 11, 2016

Winston Plywood Update 7-8-16



Northeast Corner – Log Ramp Construction Area:
· Performed grading and backfill on east side of log ramp and log deck

· Installed wall in drain pipe from drain ditch east side of ramp

Hog, Glue Room, and Chipper Deck:
· Continued installing piping and valves at glue makeup and storage area

· Continued installing piping from glue room to lay-up line equipment

· Set hog in place and positioned trash conveyor from lay-up line

Low Voltage Electrical:
· Continued installing conduit and wiring to breakroom / restrooms / offices at mezzanine area

· Continued installing fire alarm system on metal wall at maintenance shop area

· Finished installing conductor bar for lathe gantry crane

Plant Build-Out:
· Continued painting doors in mezzanine area and on shipping office

· Continued installing bathroom fixtures in east-side restrooms

· Continued running ductwork and installed grills in mezzanine area

· Continued installing sheeting on stud walls at mezzanine area

· Installed ceiling grid in restrooms on west side of plant

· Installed structural support beam in west side lunch room

· Installed glass in shipping office and east side office doors and windows

· Completed installing handrails around stair opening to upper floor at mezzanine area

Plant Piping:
·Completed installing insulation on High Pressure Receiver piping

· Continued installing insulation on steam piping and ductwork in boiler room

· Continued checkout and commissioning on air compressors and air dryers

· Continued fabrication of piping to cross truss across north roadway (piping to vaults)

Fire Suppression:
·Continued installing hose reels at building columns

Site Paving:
· Placed section of roadway paving between RTO and main building at south end of plant

· Began grading area north of Building 5 and west of Log Conditioning Vaults for paving

· Began grading for paving around east side of log infeed deck to debarker

RTO Rebuild:
· Continued refurbishing RTO duct and equipment
· Continued installing conduit and power to RTO duct controls and devices

East Side & West Side Residuals:
·Continued fabricating and installing by –products handling conveyors and equipment (East Side)

· Continued pulling wiring to by-products conveyors and equipment (East Side)

· Continued installing plating and chutework at transitions between conveyors

· Began fabricating and guards for conveyor drive units

Winston Plywood & Veneer:


· Continued refurbishing and installing Lathes No. 1 & 2 and related equipment (continued focus on east lathe line)

· Continued installing equipment at both clippers, green stackers, and pull chains (continued focus on east lathe line)

· Continued checkout on No. 2 lathe line equipment (clipper & stackers)

· Continued refurbishing chippers and conveyors for green-end by products (on chipper deck)

· Continued cleaning and painting green-end and dry end equipment and support steel

· Continued electrical installation at Green-End equipment (conduit and power wiring)

· Continued electrical checkout on Log Pro equipment

· Began relocating 3 cut-up saw frames

· Continued details on installation of Dryer No. 1, 2, & 3 infeed and outfeed sections

· Continued installing electrical power to No. 1, 2, & 3 dryer components

· Continued installing glue lay-up line mechanical and electrical equipment

· Continued details on installing trim-saw equipment and stacker platforms and stairs

· Continued installing chutework at transitions from tree-length infeed deck and debarker conveyor, and from block saw equipment block conveyor to hog I/F system

· Continued installing chute work at transitions on by-products handling conveyors at ESR

· Continued installing drive components on miscellaneous ESR conveyors

· Continued performing preliminary test runs on No. 1 Lathe line motors and equipment

· Continued installing chutework at bark hog and at conveyor transition points from debark and Log Pro cut up system

· Continued construction of decks to core kickout pockets

· Began refurbishing core kickout pockets

· Completed installing insulation on economizers and boilers in boiler room

· Continued fabrication of infeed deck to No. 2 Lathe step-feeder and began installing infeed system to No. 1 Lathe step-feeder

· Continued fabrication and installation of support steel for No. 1 lathe step feeder

· Continued fabrication and installation of fines & overs conveyors at east-side residuals shaker screens; began installing drive components

· Continued fabrication and installation plating and chutework at conveyor transition points








Tuesday, July 5, 2016

Meeting Agenda July 5

CITY OF LOUISVILLE

TUESDAY, JULY 5, 2016  



REGULAR MEETING AGENDA  5:30 P.M.


  1. CALL TO ORDER
  2. INVOCATION
  3. PLEDGE OF ALLEGIANCE TO FLAG
  4. APPROVAL OF MINUTES
  5. NEW BUSINESS
    1. Acknowledge Tonya McWhirter as the Mississippi DARE Officer of the Year
    2. Toby Sanford of GTPDD on the E911 addressing process
    3. Docket of Claims #18288-18470 for $115,623.65  
    4. Winston Plywood & Veneer business
      1. Authorize payments
      2. Approve recommendations for changes
    5. HMGP Safe Room business
    6. Alternate projects- Street bids
    7. Discuss agreement with Louisville Municipal School District and Ivy Property
    8. Slaughter & Associates- Zoning and Comprehensive Plan
    9. Polo Custom Products- Rural Impact Grant for HVAC upgrades-authorize the Mayor to sign  application and Memorandum of Agreement and related documents
    10. Accept Bids for Supplies #2  -enclosed
    11. Set budget hearing for Tuesday, August 2 at 5:00
    12. Transfer $25,000 from Accounts Payable to E911 for quarterly contribution from city
    13. Authorize payment to the Policy Center for $40,059.00 in 4 quarterly installments for annual insurance coverage
    14. Authorize annual payment to the State Tax Commission for $29,198.23 for Non-hazardous Solid Waste Fee and pay from Landfill account
    15. Unclean Property
      1. 314 South Jones Avenue-Michelle Hines & Henry Hudson
      2. 709 South Columbus Avenue-Tommy J. Dooley
      3. 101 Dawkins Street- Willie L. Loving
      4. 105 Terry Lane- Phyllis Peden
    16. Notice of two appointments to Historic Preservation Commission—Edna Prisock and Annette Crabtree’s terms expires  8-1-16


  1. OTHER BUSINESS
  2. ADJOURN


 

Winston Plywood Update 7-1-16



Northeast Corner – Log Ramp Construction
·Placed backfill material on each side of infeed ramp to tree-length deck
· Placed concrete slab on log ramp to tree-length deck

Hog, Glue Room, and Chipper Deck
· Continued installing piping and valves at glue makeup and storage area
·Continued installing piping from glue room to lay-up line equipment

Low Voltage Electrical:
· Continued installing conduit and wiring to breakroom / restrooms / offices at mezzanine area

Plant Build-Out:
· Continued painting building door frames on exterior of main building
· Began installing bathroom fixtures in east-side restrooms
· Completed placing wall tile in restrooms at mezzanine area
· Completed placing floor tile and grout in restrooms at mezzanine area
·Continued installing sheeting on stud walls at mezzanine area

Plant Piping:
·Continued installing insulation on High Pressure Receiver piping
·Continued installing insulation on steam piping and ductwork in boiler room
·Continued checkout and commissioning on air compressors and air dryers
·Continued fabrication of piping to cross truss across north roadway (piping to vaults)

Plant Ducting
·Continued installing ducting inside plant (to trim-saw line and dry hog building)
·Continued installing exterior ducting along the west wall of plant

Site Paving:
·Continued demo work and paving at access to main door to plant (front door at northwest corner of building)
· Completed excavation, backfill, and compaction on roadway north of Building 5
·Set forms, tied rebar, and placed/finished 30’ wide roadway along north side of Building 5
·Set forms, tied rebar, and placed concrete slab at front door to plant (Northwest corner)

Log Conditioning Vaults:
·Completed installing counterweights and hydraulic cylinders on vault doors
·Continued weld-out on piping on vault heating system
·Continued electrical service to components at vaults
·Installed two additional concrete pads in bottom of vault water holding tank (for pump mounting)
· Set heat exchangers on roof of vaults and piped into heating distribution system

RTO Rebuild
·Continued refurbishing RTO duct and equipment
·Connected electrical power to RTO ID fan motor
·Continued installing conduit and power to RTO duct controls and devices

East and West Side Residuals
· Continued erecting west-side truck bins
·Continued installing ducting from building to west-side residuals cyclones
·  Began fabricating and installing chutework from belt conveyor frames into east-side residuals truck bins
·Continued weld-out on structures and framework for belt conveyors to truck bins on east side

Winston Plywood & Veneer
·Continued refurbishing and installing Lathes No. 1 & 2 and related equipment (continued focus on east lathe line)
·Continued installing equipment at both clippers, green stackers, and pull chains (continued focus on east lathe line)
·Continued checkout on No. 2 lathe line equipment (clipper & stackers)
·Continued refurbishing chippers and conveyors for green-end by products (on chipper deck)
·Continued cleaning and painting green-end and dry end equipment and support steel
·Continued electrical installation at Green-End equipment (conduit and power wiring)
·Continued electrical checkout on Log Pro equipment
·Installed roof over debarker
· Continued details on installation of Dryer No. 1, 2, & 3 infeed and outfeed sections
·Continued installing electrical power to No. 1, 2, & 3 dryer components
·Continued installing glue lay-up line mechanical and electrical equipment
·Continued details on installing trim-saw equipment and stacker platforms and stairs
· Installed belting on two conveyors to truck bins on East Side Residuals (ESR)
·Continued installing chutework from bark and block conveyors to bark hog
·Continued installing chutework at transitions from tree-length infeed deck and debarker conveyor, and from block saw equipment block conveyor to hog I/F system
·Continued installing chute work at transitions on by-products handling conveyors at ESR
·Continued installing drive components on miscellaneous ESR conveyors
·Continued performing preliminary test runs on No. 1 Lathe line motors and equipment
·Continued installing chutework at bark hog and at conveyor transition points from debark and Log Pro cut up system
·Continued construction of decks to core kickout pockets
·Continued installing insulation on economizers and boilers in boiler room
· Continued fabrication of infeed deck to No. 2 Lathe step-feeder and began installing infeed system to No. 1 Lathe step-feeder
·Continued fabrication and installation of support steel for No. 1 lathe step feeder
·Continued fabrication and installation of fines & overs conveyors at east-side residuals shaker screens; began installing drive components
·Began fabrication and installation of chute work from conveyors to shaker screen infeed pans
·Fabricated and installed infeed pan on south shaker screen
·Ran first log through debarker and cut-up saws




a


Friday, July 1, 2016

Congrats to our Own LPD's Tonya McWhirter - Ms DARE Officer of the Year!!

On Thursday June 30th at their annual conference in Biloxi ,MS Mississippi Dare Officers


Association recognized Louisville Police Department’s Sgt. Tonya McWhirter as  Dare Officer of the year for the state of Mississippi. Pictured is Sgt. McWhirter being presented the award by incoming state present Sgt. Jackie Rhodes of the Biloxi Police Department. Second photograph is left to right Chief L M Claiborne, Sgt Tonya McWhirter, LT. Barry McWhirter and Assistant Chief Andy Taylor at the conference.