Foundations:
· Continued
making repairs to old floor slab (at west side of No. 2 lathe line pull chain)
Site
Utilities:
· Completed
installing pipe bollards at corners of building
· Continued
placing concrete in treads on stairs at lathe access areas
Northeast
Corner – Log Ramp Construction Area:
· Completed
installing guard rails on infeed ramp to tree-length log deck
Hog,
Glue Room, and Chipper Deck:
· Continued
installing piping and valves at glue makeup and storage area
· Continued
installing and refurbishing equipment on chipper deck
· Installed
emergency eye wash station at glue room and caustic unloading area
Low
Voltage Electrical:
· Continued
installing conduit and wiring to breakroom / restrooms / offices at mezzanine
area and shipping office
· Continued
installing fire alarm system on metal wall at mezzanine and maintenance shop
area
· Completed
electrical connection to 5-ton overhead crane at lathe deck
Log
Pre-Conditioning Vaults:
· Completed
cleaning holding pit for vault water
· Completed
final cleaning inside vaults
· Began
placing plywood blocks inside vaults
· Continued
installing pumps and piping on vault hot-water system (WPV/BMI)
Plant
Build-Out:
· Completed
installing bathroom fixtures in east-side restrooms
· Continued
installing bathroom fixtures in west-side restrooms
· Continued
running ductwork and installed grills in mezzanine area
· Continued
installing sheeting in maintenance shop, boiler room, and air compressor room
· Completed
installing ceiling grid in west-side restrooms
· Continued
installing roof joists in west-side lunch room
· Completed
installing tile in west-side restrooms (walls and floor)
· Completed
installing stairs and handrails to upper floor access on west side of mezzanine
· Completed
installing fence around storage area on upper floor at mezzanine
Site
Paving:
· Continued
excavation, backfill, and compaction of material in area north of Building 5
and west of Log Conditioning Vaults for paving
· Completed
grading for paving around east side of log infeed deck to debarker
· Began
excavation and placement of stone for paving between vaults and log infeed deck
RTO
Rebuild:
· Continued
installing insulation on RTO duct (Completed north-side duct and began
installing on south-side duct)
· Continued
installing conduit and power to RTO duct controls and devices
East
Side & West Side Residuals:
· Continued
fabricating and installing guards for conveyor drive units
· Continued
installing ductwork and truck bins on west-side residuals
Winston
Plywood & Veneer:
· Continued
installing hydraulic components for cylinders on vault doors
· Installed
and piped in vault water circulation pumps
· Continued
running logs through debarker and cut-up system, and kicked blocks out into log
pockets
· Began
placing logs in vaults
· Continued
checkout and peeling cold logs on Lathe No. 2
· Continued
checkout on No. 2 lathe line equipment (clipper & stackers)
· Continued
refurbishing chippers and conveyors for green-end by products (on chipper deck)
· Continued
electrical installation at Green-End equipment (conduit and power wiring)
· Continued
electrical checkout on Log Pro equipment
· Continued
relocation of saw frames on cut-up system
· Continued
installing piping from glue room to lay-up line equipment
· Continued
installing trash conveyor for lay-up line to hog room
· Continued
details on installation of Dryer No. 1 & 2 infeed and outfeed sections
· Continued
testing dryer infeed systems and main dryer chains and rolls in No. 1 & 2
dryers
· Continued
installing glue lay-up line mechanical and electrical equipment
· Continued
details on installing trim-saw equipment
· Continued
construction of decks to core kickout pockets
· Continued
refurbishing core kickout pockets
· Continued
fabrication of infeed deck to No. 2 Lathe step-feeder and began installing
infeed system to No. 1 Lathe step-feeder
· Completed
fabrication and installation of support steel for No. 1 lathe step feeder
· Continued
installing components on east side truck bins and infeed conveyors
· Set
trailer under transfer conveyor for bark from debarking system