Site
Utilities:
· Continued
installing pipe bollards at corners of building
· Placed
concrete in treads on stairs at lathe access areas
Northeast
Corner – Log Ramp Construction Area:
· Finished
grading and cleanup in northeast corner for log handling equipment to deliver
logs to tree-length ramp
· Installed
guard rails on infeed ramp to tree-length log deck
Hog,
Glue Room, and Chipper Deck:
· Continued
installing piping and valves at glue makeup and storage area
· Continued
installing and refurbishing equipment on chipper deck
Low
Voltage Electrical:
· Continued
installing conduit and wiring to breakroom / restrooms / offices at mezzanine
area and shipping office
· Continued
installing fire alarm system on metal wall at mezzanine and maintenance shop
area
Log Pre-Conditioning
Vaults:
· Began
cleaning holding pit for vault water
· Continued
final cleaning inside vaults
Plant
Build-Out:
· Continued
installing bathroom fixtures in east-side restrooms
· Continued
running ductwork and installed grills in mezzanine area
· Completed
installing sheeting on stud walls at mezzanine area and continued installing
sheeting in maintenance shop, boiler room, and air compressor room
· Continued
installing ceiling grid in west-side restrooms
· Installed
partial roof joists in west-side lunch room
· Installed
access stairs to mezzanine area (handrails remain to be installed)
· Installed
sheetrock in offices on upper floor at mezzanine and began tape & float
· Installed
fence around storage area on upper floor at mezzanine
· Began
installing toilet fixtures on west-side restrooms
· Began
installing wall tile in west-side restrooms
Plant
Piping:
· Completed
installing insulation on piping in boiler room at HPR and DA tank
· Continued
checkout and commissioning on air compressors and air dryers
· Continued
fabrication of piping to cross the truss across north roadway (piping to
vaults)
· Continued
installing piping from dryer wash-water pit to vaults
Fire
Suppression:
· Continued
installing hose reels at building columns
· Continued
installing sprinkler heads in automatic systems throughout the plant
· Installed
sprinkler piping around step feeder structure at No. 1 Lathe
Site
Paving:
· Continued
excavation, backfill, and compaction of material in area north of Building 5
and west of Log Conditioning Vaults for paving
· Continued
grading for paving around east side of log infeed deck to debarker
RTO
Rebuild:
· Continued
refurbishing RTO duct and equipment
· Continued
installing insulation on RTO duct
· Installed
access stairs to RTO duct platform
· Completed
fabrication and weld-out on transition duct from RTO ID fan to RTO stack
· Continued
installing conduit and power to RTO duct controls and devices
East
Side & West Side Residuals:
· Continued
fabricating and installing by –products handling conveyors and equipment (East
Side)
· Continued
pulling wiring to by-products conveyors and equipment (East Side)
· Continued
installing plating and chutework at transitions between conveyors (East Side)
· Continued
fabricating and installing guards for conveyor drive units
· Continued
installing foundations on West-Side Residuals
Winston
Plywood & Veneer:
· Continued
installing hydraulic components for cylinders on vault doors
· Modified
foundations for vault water circulation pumps
· Received
two vault water circulation pumps
· Ran
additional logs through debarker and cut-up system, and kicked blocks out into
log pocket
· Continued
refurbishing and installing Lathes No. 1 & 2 and related equipment
(continued focus on east lathe line)
· Continued
installing equipment at both clippers, green stackers, and pull chains
(continued focus on east lathe line)
· Continued
checkout on No. 2 lathe line equipment (clipper & stackers)
· Ran
first blocks through Lathe No. 2
· Continued
refurbishing chippers and conveyors for green-end by products (on chipper deck)
· Continued
electrical installation at Green-End equipment (conduit and power wiring)
· Continued
electrical checkout on Log Pro equipment
· Relocated
2 cut-up saw frames
· Continued
installing piping from glue room to lay-up line equipment
· Continued
installing trash conveyor for lay-up line to hog room
· Continued
details on installation of Dryer No. 1, 2, & 3 infeed and outfeed sections
· Continued
installing electrical power to No. 1, 2, & 3 dryer components
· Began
testing dryer infeed systems and main dryer chains and rolls in No. 1 & 2
dryers
· Continued
installing glue lay-up line mechanical and electrical equipment
· Continued
details on installing trim-saw equipment
· Continued
installing chute work at transitions on by-products handling conveyors at ESR
· Continued
installing drive components on miscellaneous ESR conveyors
· Continued
performing preliminary test runs and program changes on No. 1 Lathe line motors
and equipment
· Continued
construction of decks to core kickout pockets
· Continued
refurbishing core kickout pockets
· Continued
fabrication of infeed deck to No. 2 Lathe step-feeder and began installing
infeed system to No. 1 Lathe step-feeder
· Continued
fabrication and installation of support steel for No. 1 lathe step feeder
· Continued
fabrication and installation of fines & overs conveyors at east-side
residuals shaker screens; continued installing drive components and safety
guarding
· Continued
installing components on east side truck bins and infeed conveyors