·Placed
backfill material on each side of infeed ramp to tree-length deck
· Placed
concrete slab on log ramp to tree-length deck
Hog,
Glue Room, and Chipper Deck
· Continued
installing piping and valves at glue makeup and storage area
·Continued
installing piping from glue room to lay-up line equipment
Low
Voltage Electrical:
· Continued
installing conduit and wiring to breakroom / restrooms / offices at mezzanine
area
Plant
Build-Out:
· Continued
painting building door frames on exterior of main building
· Began
installing bathroom fixtures in east-side restrooms
· Completed
placing wall tile in restrooms at mezzanine area
· Completed
placing floor tile and grout in restrooms at mezzanine area
·Continued
installing sheeting on stud walls at mezzanine area
Plant
Piping:
·Continued
installing insulation on High Pressure Receiver piping
·Continued
installing insulation on steam piping and ductwork in boiler room
·Continued
checkout and commissioning on air compressors and air dryers
·Continued
fabrication of piping to cross truss across north roadway (piping to vaults)
Plant
Ducting
·Continued
installing ducting inside plant (to trim-saw line and dry hog building)
·Continued
installing exterior ducting along the west wall of plant
Site
Paving:
·Continued
demo work and paving at access to main door to plant (front door at northwest
corner of building)
· Completed
excavation, backfill, and compaction on roadway north of Building 5
·Set
forms, tied rebar, and placed/finished 30’ wide roadway along north side of
Building 5
·Set
forms, tied rebar, and placed concrete slab at front door to plant (Northwest
corner)
Log
Conditioning Vaults:
·Completed
installing counterweights and hydraulic cylinders on vault doors
·Continued
weld-out on piping on vault heating system
·Continued
electrical service to components at vaults
·Installed
two additional concrete pads in bottom of vault water holding tank (for pump
mounting)
· Set
heat exchangers on roof of vaults and piped into heating distribution system
RTO
Rebuild
·Continued
refurbishing RTO duct and equipment
·Connected
electrical power to RTO ID fan motor
·Continued
installing conduit and power to RTO duct controls and devices
East
and West Side Residuals
· Continued
erecting west-side truck bins
·Continued
installing ducting from building to west-side residuals cyclones
· Began
fabricating and installing chutework from belt conveyor frames into east-side
residuals truck bins
·Continued
weld-out on structures and framework for belt conveyors to truck bins on east
side
Winston
Plywood & Veneer
·Continued
refurbishing and installing Lathes No. 1 & 2 and related equipment
(continued focus on east lathe line)
·Continued
installing equipment at both clippers, green stackers, and pull chains
(continued focus on east lathe line)
·Continued
checkout on No. 2 lathe line equipment (clipper & stackers)
·Continued
refurbishing chippers and conveyors for green-end by products (on chipper deck)
·Continued
cleaning and painting green-end and dry end equipment and support steel
·Continued
electrical installation at Green-End equipment (conduit and power wiring)
·Continued
electrical checkout on Log Pro equipment
·Installed
roof over debarker
· Continued
details on installation of Dryer No. 1, 2, & 3 infeed and outfeed sections
·Continued
installing electrical power to No. 1, 2, & 3 dryer components
·Continued
installing glue lay-up line mechanical and electrical equipment
·Continued
details on installing trim-saw equipment and stacker platforms and stairs
· Installed
belting on two conveyors to truck bins on East Side Residuals (ESR)
·Continued
installing chutework from bark and block conveyors to bark hog
·Continued
installing chutework at transitions from tree-length infeed deck and debarker
conveyor, and from block saw equipment block conveyor to hog I/F system
·Continued
installing chute work at transitions on by-products handling conveyors at ESR
·Continued
installing drive components on miscellaneous ESR conveyors
·Continued
performing preliminary test runs on No. 1 Lathe line motors and equipment
·Continued
installing chutework at bark hog and at conveyor transition points from debark
and Log Pro cut up system
·Continued
construction of decks to core kickout pockets
·Continued
installing insulation on economizers and boilers in boiler room
· Continued
fabrication of infeed deck to No. 2 Lathe step-feeder and began installing
infeed system to No. 1 Lathe step-feeder
·Continued
fabrication and installation of support steel for No. 1 lathe step feeder
·Continued
fabrication and installation of fines & overs conveyors at east-side
residuals shaker screens; began installing drive components
·Began
fabrication and installation of chute work from conveyors to shaker screen
infeed pans
·Fabricated
and installed infeed pan on south shaker screen
·Ran
first log through debarker and cut-up saws