· Performed grading and backfill on east side of log ramp and log deck
· Installed wall in drain pipe from drain ditch east side of ramp
· Installed wall in drain pipe from drain ditch east side of ramp
Hog,
Glue Room, and Chipper Deck:
· Continued installing piping and valves at glue makeup and storage area· Continued installing piping from glue room to lay-up line equipment
· Set hog in place and positioned trash conveyor from lay-up line
Low
Voltage Electrical:
· Continued installing conduit and wiring to breakroom / restrooms / offices at mezzanine area· Continued installing fire alarm system on metal wall at maintenance shop area
· Finished installing conductor bar for lathe gantry crane
Plant
Build-Out:
· Continued painting doors in mezzanine area and on shipping office· Continued installing bathroom fixtures in east-side restrooms
· Continued running ductwork and installed grills in mezzanine area
· Continued installing sheeting on stud walls at mezzanine area
· Installed ceiling grid in restrooms on west side of plant
· Installed structural support beam in west side lunch room
· Installed glass in shipping office and east side office doors and windows
· Completed installing handrails around stair opening to upper floor at mezzanine area
Plant
Piping:
·Completed installing insulation on High Pressure Receiver piping
· Continued installing insulation on steam piping and ductwork in boiler room
· Continued checkout and commissioning on air compressors and air dryers
· Continued fabrication of piping to cross truss across north roadway (piping to vaults)
· Continued installing insulation on steam piping and ductwork in boiler room
· Continued checkout and commissioning on air compressors and air dryers
· Continued fabrication of piping to cross truss across north roadway (piping to vaults)
Fire
Suppression:
·Continued
installing hose reels at building columns
Site
Paving:
· Placed section of roadway paving between RTO and main building at south end of plant· Began grading area north of Building 5 and west of Log Conditioning Vaults for paving
· Began grading for paving around east side of log infeed deck to debarker
RTO
Rebuild:
· Continued refurbishing RTO duct and equipment· Continued installing conduit and power to RTO duct controls and devices
East
Side & West Side Residuals:
·Continued fabricating and installing by –products handling conveyors and equipment (East Side)
· Continued pulling wiring to by-products conveyors and equipment (East Side)
· Continued installing plating and chutework at transitions between conveyors
· Began fabricating and guards for conveyor drive units
· Continued pulling wiring to by-products conveyors and equipment (East Side)
· Continued installing plating and chutework at transitions between conveyors
· Began fabricating and guards for conveyor drive units
Winston
Plywood & Veneer:
· Continued refurbishing and installing Lathes No. 1 & 2 and related equipment (continued focus on east lathe line)
· Continued installing equipment at both clippers, green stackers, and pull chains (continued focus on east lathe line)
· Continued checkout on No. 2 lathe line equipment (clipper & stackers)
· Continued refurbishing chippers and conveyors for green-end by products (on chipper deck)
· Continued cleaning and painting green-end and dry end equipment and support steel
· Continued electrical installation at Green-End equipment (conduit and power wiring)
· Continued electrical checkout on Log Pro equipment
· Began relocating 3 cut-up saw frames
· Continued details on installation of Dryer No. 1, 2, & 3 infeed and outfeed sections
· Continued installing electrical power to No. 1, 2, & 3 dryer components
· Continued installing glue lay-up line mechanical and electrical equipment
· Continued details on installing trim-saw equipment and stacker platforms and stairs
· Continued installing chutework at transitions from tree-length infeed deck and debarker conveyor, and from block saw equipment block conveyor to hog I/F system
· Continued installing chute work at transitions on by-products handling conveyors at ESR
· Continued installing drive components on miscellaneous ESR conveyors
· Continued performing preliminary test runs on No. 1 Lathe line motors and equipment
· Continued installing chutework at bark hog and at conveyor transition points from debark and Log Pro cut up system
· Continued construction of decks to core kickout pockets
· Began refurbishing core kickout pockets
· Completed installing insulation on economizers and boilers in boiler room
· Continued fabrication of infeed deck to No. 2 Lathe step-feeder and began installing infeed system to No. 1 Lathe step-feeder
· Continued fabrication and installation of support steel for No. 1 lathe step feeder
· Continued fabrication and installation of fines & overs conveyors at east-side residuals shaker screens; began installing drive components
· Continued fabrication and installation plating and chutework at conveyor transition points