Monday, October 12, 2015

Winston Plywood Weekly Update-10-09-2015



Foundations:
·         Placed roofs on both electrical rooms at north end of building
·         Continued forming on finishing equipment and lathe charger pedestals
·         Completed boiler foundations

Building:
·         Installed decking on Building 4
·         Continued trim-out and detailing on Building 2
·         Continued installing standing seam roofing on Building 2
·         Continued installing wall girts on Buildings 2 and 4
·         Continued bracing and trim-out on Building 4 roof
·         Installed insulation on Building 4 roof
·         Installed ridge cap on Building 1

Fire Protection:
·         Continued installing sprinkler systems in Building 2 roof
·         Started and completed sprinkler piping for Building 4 roof
·         Began installing foundations for fire water tank

Hog Room, Glue Room, and Lathe & Chipper Deck:
·         Continued installing chipper deck support steel and installed 60-70% of decking

Electrical:
·         Completed block work on two north control rooms
·         Continued electrical rough-in for lighting in Buildings 1, 2, 3,  and 5 (Conduit and junction boxes)
·         Began running conduit for process equipment at Dryers 1 & 2
·         Completed underground primary duct bank to power pole east of plant

Site Utilities:
·         Completed main underground storm drain piping east of plant site
·         Set two inlet boxes on storm drains east of plant
·         Began installing trunk line and inlets for storm drain from building downspouts
·         Contractor completed installation of 12” fire-loop at south end of plywood building
·         Contractor sawcut paving in existing parking lot to complete 12” fire loop around plant site

Log Conditioning Vaults
·         Did grading and began excavation for tank at log conditioning vaults

Site Paving
·         Continued fine grading for paving in area east of Building 10 and north transformer bank

Winston Plywood:
·         Continued refurbishing and installing green-end equipment for both east and west lathe lines
·         Received and off-loaded additional Log-Pro equipment for log processor
·         Received additional six loads of No. 3 Dryer components
·         Received and set No. 3 Boiler and Economizers
·         Continued press pit modifications




Thursday, October 8, 2015

NOTICE OF APPLICATION FOR EMPLOYMENT FOR POLICE OFFICER

Notice is hereby given that the City of Louisville, MS, is now taking applications to fill the position of a full-time Police Officer. Job descriptions and requirements are available upon request at the City Hall, 662-773-9201 or 773-3511. Applications may be filed at the City Hall, 200 South Church Street, or P.O. Box 510, Louisville, MS 39339, no later than eleven o’clock (11:00) A.M. on Friday October 23, 2015.

NOTICE OF APPLICATIONS FOR EMPLOYMENT


Notice is hereby given that the City of Louisville, Mississippi is now taking applications for employment to fill the position of full-time E-911 Dispatcher with the Louisville/Winston County E-911 Service. Job description and requirements are available upon request at the City Clerk’s Office. Applications may be filed at City Hall, 200 South Church Avenue, no later than eleven o’clock (11:00) A. M. on Friday, October 23, 2015.

So ordered by the Mayor and Board of Aldermen, this the 6th day of October, 2015.

BABS W. FULTON
City Clerk

Tuesday, October 6, 2015

Meeting Agenda-Oct 6

CITY OF LOUISVILLE

TUESDAY, OCTOBER 6, 2015  


REGULAR MEETING AGENDA  5:30 P.M.

  1. CALL TO ORDER
  2. INVOCATION
  3. PLEDGE OF ALLEGIANCE TO FLAG
  4. APPROVAL OF MINUTES
  5. NEW BUSINESS

    1. Accept Zoning petition by Winston County for the Hospital
    2. Unclean property:  hearing for three properties
      1. Bullock Realty, LLC, at 317 Mills Street, parcel 80-151283402 0700400
      2. Jim Anderson, at 880 Brooksville Road, parcel 80-151262301 0400401
      3. Paula Mass, at 201 West Poplar Drive, parcel 80-151242001 0600500

    1. Justin McDonald:  Winston Plywood and Veneer payments
    2. Justin McDonald:  Winston Plywood and Veneer recommendations
    3. Winston Plywood Electrical #3-  Authorize the Mayor to sign the pay request for CDBG Funds and upon same order authorize the payment (when the money is received) to Irby Electrical for $430,393.00 for low voltage switchboards
    4. HMGP SAFE ROOM- authorize notice for project manager
    5. Accept low quote of $7.00 epr cubic yard from McDevitt Enterprise, LLC for furnishing, hauling and spreading approximately 100 trailer loads of select fill dirt to Transload site, and upon the same order, authorize payment upon completion of the project
    6. Payment for Docket of Claims # 15705-15900 for $145,284.89 for September invoices
    7. Declare an Erroneous Tax Sale on parcel 80-151283301 0600100, owned by Willie L. Loving Etux Dorothea, property was tax exempt  
    8. Change regular meeting time from December 1 meeting to December 8
    9. Request for Mayor to attend Washington, D.C. economic development trip, October 21-23
    10. Acknowledge training requests:
      1. Request for Felisha Mays to attend the MS 911 Fall Training in Tunica on October 19-21
      2. Request for Quanda Davenport to attend NAED Basic Telecommunicator training in Philadelphia on Nov 9-13
    11. Executive Session for Personnel Matters

  1. OTHER BUSINESS
  2. ADJOURN

Monday, October 5, 2015

Winston Plywood Weekly Update-9-29-15

Masonry work at Electrical Room

Foundations:

· Continued work on Green-end Electrical Room

· Completed 24” slab at Glue Room

Building:

· Continued installing standing-seam roof on Buildings 3

· Continued trim-out and structural detailing on structural steel framing on Building 2

· Installed insulation and water-shield on Building 2 from Columns 3-27

· Completed structural framing for Lathe Deck, placed and finished Lathe Deck concrete

· Continued installing wall girts on Building 3

· Continued bracing and trim-out on Building 4

· Erected structural steel framing for Building 11

Fire Protection:

· Continued installing sprinkler systems in Building 2

Electrical:

· Continued block work on green-end electrical rooms

· Continued underground primary power supply duct banks – installed ducts across south end of plywood building and underneath rail spurs at southwest corner of building

· Began installing boxes in ceiling of Buildings 1, 3, and 5 for lighting grid

Sitework and Paving:

· Placed concrete paving between Buildings 8 & 10 (around transformers 5-13 and primary switches)

Winston Plywood:

· Continued refurbishing existing veneer dryers

· Continued refurbishing and installing green-end equipment for west lathe line

· Received and off-loaded additional Log-Pro equipment for log processor

· Received first two loads of No. 3 Dryer components

· Set base plates for steam boilers (not grouted)

· Continued press pit modifications

 Setting Conex for east lathe control room


Setting Boiler No. 1

Setting Boiler No. 1

Boilers No. 1 and 2 in place on foundations

Monday, September 28, 2015

Winston Plywood Weekly Update-9-25-15


Foundations:
· Continued work on Green-end Electrical Room
· Completed 24” slab at Glue Room

Building:
· Continued installing standing-seam roof on Buildings 3
· Continued trim-out and structural detailing on structural steel framing on Building 2
· Installed insulation and water-shield on Building 2 from Columns 3-27
· Completed structural framing for Lathe Deck, placed and finished Lathe Deck concrete
· Continued installing wall girts on Building 3
· Continued bracing and trim-out on Building 4
· Erected structural steel framing for Building 11

Fire Protection:
· Continued installing sprinkler systems in Building 2

Electrical:
· Continued block work on green-end electrical rooms
· Continued underground primary power supply duct banks – installed ducts across south end of plywood building and underneath rail spurs at southwest corner of building
· Began installing boxes in ceiling of Buildings 1, 3, and 5 for lighting grid

Sitework and Paving:
· Placed concrete paving between Buildings 8 & 10 (around transformers 5-13 and primary switches)


Winston Plywood:
· Continued refurbishing existing veneer dryers
· Continued refurbishing and installing green-end equipment for west lathe line
· Received and off-loaded additional Log-Pro equipment for log processor
· Received first two loads of No. 3 Dryer components
· Set base plates for steam boilers (not grouted)
· Continued press pit modifications






Monday, September 21, 2015

Winston Plywood Weekly Update-9-18-15



 Foundations:
·         Completed block work on Hog Room
·         Continued work on Green-end Electrical Rooms
·         Continued form work on Sander Foundation in finishing area
·         Placed and finished foundation walls for Green Chipper
·         Completed base slab for glue room and began installing rebar and forming for 24” slab at Glue Room

Building:
·         Continued installing standing-seam roof on Buildings 3
·         Continued installing insulation and water seal on Buildings 3
·         Completed installing beams and joists on Building 2 (West side of overall building)
·         Continued trim-out and finishing on structural steel framing on Building 2
·         Continued erecting structural steel framing for Lathe & Chipper Deck
·         Continued installing wall girts on Building 3
·         Installed structural framing and bar joists on Building 4

Fire Protection:
·         Continued installing sprinkler system in Building 3 and began installing system in Building 2
·         Continued installing risers and system control valves in Building 2

Electrical:
·         Continued installing primary power duct bank at transformers 1-4  (at south end of Building No. 3)
·         Continued finish grading and placement of stone around transformers 5-13
·         Completed block work on electrical room (southeast corner of Building 3)
·         Continued block work on green-end electrical rooms
·         Continued underground primary power supply duct banks (moving west through previous RTO site)

Sitework and Paving:
·         Began finish grading and forming for paving in area between Buildings 8 and 10

Winston Plywood:
·         Continued refurbishing existing veneer dryers
·         Continued refurbishing and installing green-end equipment for west lathe line
·         Received and off-loaded additional loads of green-end equipment
·         Received and off-loaded additional Log-Pro equipment for log processing
·         Began installing boiler base plates