Foundations:
· Completed block work on Hog Room
· Continued work on Green-end Electrical Rooms
· Continued form work on Sander Foundation in finishing area
· Placed and finished foundation walls for Green Chipper
· Completed base slab for glue room and began installing rebar and forming for 24” slab at Glue Room
Building:· Continued installing standing-seam roof on Buildings 3
· Continued installing insulation and water seal on Buildings 3
· Completed installing beams and joists on Building 2 (West side of overall building)
· Continued trim-out and finishing on structural steel framing on Building 2
· Continued erecting structural steel framing for Lathe & Chipper Deck
· Continued installing wall girts on Building 3
· Installed structural framing and bar joists on Building 4
Fire Protection:· Continued installing sprinkler system in Building 3 and began installing system in Building 2
· Continued installing risers and system control valves in Building 2
Electrical:· Continued installing primary power duct bank at transformers 1-4 (at south end of Building No. 3)
· Continued finish grading and placement of stone around transformers 5-13
· Completed block work on electrical room (southeast corner of Building 3)
· Continued block work on green-end electrical rooms
· Continued underground primary power supply duct banks (moving west through previous RTO site)
Sitework and Paving:· Began finish grading and forming for paving in area between Buildings 8 and 10
Winston Plywood:· Continued refurbishing existing veneer dryers
· Continued refurbishing and installing green-end equipment for west lathe line
· Received and off-loaded additional loads of green-end equipment
· Received and off-loaded additional Log-Pro equipment for log processing
· Began installing boiler base plates