Monday, September 21, 2015

Winston Plywood Weekly Update-9-18-15



 Foundations:
·         Completed block work on Hog Room
·         Continued work on Green-end Electrical Rooms
·         Continued form work on Sander Foundation in finishing area
·         Placed and finished foundation walls for Green Chipper
·         Completed base slab for glue room and began installing rebar and forming for 24” slab at Glue Room

Building:
·         Continued installing standing-seam roof on Buildings 3
·         Continued installing insulation and water seal on Buildings 3
·         Completed installing beams and joists on Building 2 (West side of overall building)
·         Continued trim-out and finishing on structural steel framing on Building 2
·         Continued erecting structural steel framing for Lathe & Chipper Deck
·         Continued installing wall girts on Building 3
·         Installed structural framing and bar joists on Building 4

Fire Protection:
·         Continued installing sprinkler system in Building 3 and began installing system in Building 2
·         Continued installing risers and system control valves in Building 2

Electrical:
·         Continued installing primary power duct bank at transformers 1-4  (at south end of Building No. 3)
·         Continued finish grading and placement of stone around transformers 5-13
·         Completed block work on electrical room (southeast corner of Building 3)
·         Continued block work on green-end electrical rooms
·         Continued underground primary power supply duct banks (moving west through previous RTO site)

Sitework and Paving:
·         Began finish grading and forming for paving in area between Buildings 8 and 10

Winston Plywood:
·         Continued refurbishing existing veneer dryers
·         Continued refurbishing and installing green-end equipment for west lathe line
·         Received and off-loaded additional loads of green-end equipment
·         Received and off-loaded additional Log-Pro equipment for log processing
·         Began installing boiler base plates