Tuesday, August 30, 2016

Building Community Relationship Meeting-Sept 10

There will be a Community Relationship Meeting held Saturday, September 10, 2016 at 9:00 a.m. from the Mt. Moriah M.B Church in Louisville, Mississippi.

The purpose of this meeting is to help build a better relationship between Citizens and Law Enforcement Agencies. Louisville Police Chief L.M. Claiborne will be present to help informs us om ways to help better these relationships. He will be giving us important tips and demonstrating proper procedure for both Citizens and Law Enforcement Agencies. The public is welcome to attend.

Contact Robert Finch at 662-803-1901 or L.C. Hines at 662-392-7430 for more information.

Monday, August 15, 2016

Winston Plywood Weekly Update 8-12-16


Hog, Glue Room, and Chipper Deck:
·         Continued insulating water piping to eye-wash stations

Low Voltage Electrical:
·         Continued installing conduit and wiring to breakroom / restrooms / offices at mezzanine area, west side break & restroom area, and in shipping office
·         Continued installing fire alarm system on metal wall at mezzanine and maintenance shop area
·         Continued electrical installation at fire pump buildings

Plant Build-Out:
·         Continued installation of HVAC unit at shipping office, MCC rooms and glue loft area
·         Began installing ceiling grid in upstairs offices at mezzanine area
·         Continued installing ceiling grid in west-side lunch room
·         Installed metal roof decking over west side lunch room
·         Installed ceiling tile in west side lunchroom
·         Received and began installing millwork in east side offices and lunch room
·         Continued finish painting in east side offices and lunch room

Site Paving:
·         Continued draining water from west side light duty paving

East Side & West Side Residuals:
·         Continued installing ductwork to equipment inside building (dry hogs, trim-saws, sander)
·         Continued installing support steel and equipment for west side residuals (fans and blowers)




Monday, August 8, 2016

Winston Plywood Update 8-5-16


Hog, Glue Room, and Chipper Deck:
·         Continued installing piping and valves at glue make-up and storage area
·         Completed installation of emergency eye wash station at glue room and caustic unloading area
·         Began  insulating water piping to eye-wash stations

Low Voltage Electrical:
·         Continued installing conduit and wiring to breakroom / restrooms / offices at mezzanine area, west side break & restroom area, and in shipping office
·         Continued installing fire alarm system on metal wall at mezzanine and maintenance shop area
·         Completed installation of power wiring from primary feeder line to WSR transformer, and from transformer to MCC unit inside West-Side Residuals electrical building

Log Pre-Conditioning Vaults:
·         Removed temporary safety fence and installed permanent safety fencing around perimeter of vault water storage pit & vault water return trench to storage pit
·         Installed safety fencing around perimeter of top of vault concrete structure

Plant Build-Out:
·         Began installing toilet accessories in east-side restrooms
·         Continued installing door hardware throughout east and west side restroom and break areas
·         Continued installation of HVAC unit at shipping office, MCC rooms and glue loft area
·         Began installing ceiling grid in upstairs offices at mezzanine area
·         Installed ceiling grid in west-side lunch room
·         Installed sink in QC room (TECO Lab)

Site Paving:
·         Continued excavation and placement of stone for paving between vaults and log infeed deck
·         Finished layout and preparation for placement of reinforcing steel between vaults and log infeed deck for paving
·         Placed concrete paving and performed sawcutting in area between vaults and log infeed deck

East Side & West Side Residuals:
·         Continued installing ductwork to equipment inside building (dry hogs, trim-saws, sander)
·         Continued installing ductwork to truck bins on west-side residual


 





Monday, August 1, 2016

Advertisement For Bids Louisville Landfill


Winston Plywood Weekly Update 7-29-16




Foundations:
·         Continued making repairs to old floor slab (North side of No. 1 dryer and along building column line E)

Site Utilities:
·         Completed placing concrete in treads on stairs at lathe access areas

Northeast Corner – Log Ramp Construction Area:
·         Removed material, graded area, and set forms between vaults and tree-length deck for paving

Hog, Glue Room, and Chipper Deck:
·         Continued installing piping and valves at glue makeup and storage area
·         Completed installation of emergency eye wash station at glue room and caustic unloading area
·         Installed roll-up door at south end of second floor elevation in glue room

Low Voltage Electrical:
·         Continued installing conduit and wiring to breakroom / restrooms / offices at mezzanine area, west side break & restroom area, and in shipping office
·         Continued installing fire alarm system on metal wall at mezzanine and maintenance shop area

Log Pre-Conditioning Vaults:
·         Continued placing plywood blocks inside vaults for heating and peeling
·         Heated water in vault water holding tank by circulating through heat exchangers
·         Pumped water onto logs in vaults and heated logs
·         Installed temporary fencing around perimeter of vault water holding pit and along north side of vault water drainage trench

Plant Build-Out:
·         Continued installing bathroom fixtures in west-side restrooms
·         Placed concrete in stair treads and lands on stairs at west side of mezzanine area
·         Continued installing door hardware throughout east and west side restroom and break areas
·         Continued installation of HVAC unit at shipping offices

Site Paving:
·         Continued excavation and placement of stone for paving between vaults and log infeed deck
·         Began layout and preparation for placement of reinforcing steel between vaults and log infeed deck for paving

RTO Rebuild:
·         Continued installing insulation on RTO duct (completed south side and continued on ID fan and stack)
·         Began insulating ID fan and RTO stack
·         Continued installing conduit and power to RTO duct controls and devices

East Side & West Side Residuals:
·         Continued fabricating and installing guards for conveyor drive units
·         Continued installing ductwork to truck bins on west-side residuals
·         Set cyclone down-comer piping on both cyclones
·         Set rotary feeders for high pressure blowers

Winston Plywood & Veneer:
·         Continued running logs through debarker and cut-up system, and kicked blocks out into log pockets
·         Continued placing logs in vaults and heating logs for peeling at Lathe No. 2
·         Continued checkout and peeling hot blocks on Lathe No. 2
·         Continued checkout on No. 2 lathe line equipment (lathe, clipper, & stacker)
·         Continued checkout and tuning on Log Pro equipment
·         Continued installing piping from glue room to lay-up line equipment
·         Continued installing trash conveyor for lay-up line to hog room
·         Continued details on installation of Dryer No. 1 & 2 infeed and outfeed sections
·         Continued testing dryer infeed systems and main dryer chains and rolls in No. 1 & 2 dryers
·         Continued installing glue lay-up line mechanical and electrical equipment
·         Continued details on installing trim-saw equipment





Monday, July 25, 2016

Winston Plywood Update 7-22-16


Foundations:
·         Continued making repairs to old floor slab (at west side of No. 2 lathe line pull chain)

Site Utilities:
·         Completed installing pipe bollards at corners of building
·         Continued placing concrete in treads on stairs at lathe access areas

Northeast Corner – Log Ramp Construction Area:
·         Completed installing guard rails on infeed ramp to tree-length log deck

Hog, Glue Room, and Chipper Deck:
·         Continued installing piping and valves at glue makeup and storage area
·         Continued installing and refurbishing equipment on chipper deck
·         Installed emergency eye wash station at glue room and caustic unloading area

Low Voltage Electrical:
·         Continued installing conduit and wiring to breakroom / restrooms / offices at mezzanine area and shipping office
·         Continued installing fire alarm system on metal wall at mezzanine and maintenance shop area
·         Completed electrical connection to 5-ton overhead crane at lathe deck

Log Pre-Conditioning Vaults:
·         Completed cleaning holding pit for vault water
·         Completed final cleaning inside vaults
·         Began placing plywood blocks inside vaults
·         Continued installing pumps and piping on vault hot-water system (WPV/BMI)

Plant Build-Out:
·         Completed installing bathroom fixtures in east-side restrooms
·         Continued installing bathroom fixtures in west-side restrooms
·         Continued running ductwork and installed grills in mezzanine area
·         Continued installing sheeting in maintenance shop, boiler room, and air compressor room
·         Completed installing ceiling grid in west-side restrooms
·         Continued installing roof joists in west-side lunch room
·         Completed installing tile in west-side restrooms (walls and floor)
·         Completed installing stairs and handrails to upper floor access on west side of mezzanine
·         Completed installing fence around storage area on upper floor at mezzanine

Site Paving:
·         Continued excavation, backfill, and compaction of material in area north of Building 5 and west of Log Conditioning Vaults for paving
·         Completed grading for paving around east side of log infeed deck to debarker
·         Began excavation and placement of stone for paving between vaults and log infeed deck

RTO Rebuild:
·         Continued installing insulation on RTO duct (Completed north-side duct and began installing on south-side duct)
·         Continued installing conduit and power to RTO duct controls and devices

East Side & West Side Residuals:
·         Continued fabricating and installing guards for conveyor drive units
·         Continued installing ductwork and truck bins on west-side residuals

Winston Plywood & Veneer:
·         Continued installing hydraulic components for cylinders on vault doors
·         Installed and piped in vault water circulation pumps
·         Continued running logs through debarker and cut-up system, and kicked blocks out into log pockets
·         Began placing logs in vaults
·         Continued checkout and peeling cold logs on Lathe No. 2
·         Continued checkout on No. 2 lathe line equipment (clipper & stackers)
·         Continued refurbishing chippers and conveyors for green-end by products (on chipper deck)
·         Continued electrical installation at Green-End equipment (conduit and power wiring)
·         Continued electrical checkout on Log Pro equipment
·         Continued relocation of saw frames on cut-up system
·         Continued installing piping from glue room to lay-up line equipment
·         Continued installing trash conveyor for lay-up line to hog room
·         Continued details on installation of Dryer No. 1 & 2 infeed and outfeed sections
·         Continued testing dryer infeed systems and main dryer chains and rolls in No. 1 & 2 dryers
·         Continued installing glue lay-up line mechanical and electrical equipment
·         Continued details on installing trim-saw equipment
·         Continued construction of decks to core kickout pockets
·         Continued refurbishing core kickout pockets
·         Continued fabrication of infeed deck to No. 2 Lathe step-feeder and began installing infeed system to No. 1 Lathe step-feeder
·         Completed fabrication and installation of support steel for No. 1 lathe step feeder
·         Continued installing components on east side truck bins and infeed conveyors
·         Set trailer under transfer conveyor for bark from debarking system







Thursday, July 21, 2016

Louisville PD Receives a ThankYou

Thanks Winston Plywood for your support of our local law enforcement.!