Weekly Progress Update - Winston Plywood and Veneer- May 15

This is a weekly update on construction progress at the Winston Plywood and Veneer Facility in LouisvileDemolition:

·         Existing dryer wash-down water pit removed

Foundations:
·         Building grade wall placed and finished across west end of Building 5
·         Grade beams and floor slab placed and finished on west ½ of Building 5 (building 5 foundations and slab complete)
·         Grade beams excavated and rebar in place along building line north of existing lathes.

Building Structural Steel:
·         Structural columns on Building 1 in place at E-9, E-11, E-13, E-15, I-9, I-11, I-13, and I-15
·         Bar joists in place on Building 1 between Column Rows 19-21, 21-23 and 23-25.  Trim-out ongoing between Column Rows 19-25

Fire Protection:
·         Approximately 1,400 feet of 12” underground fire protection piping in place (underground main loop is in place across north end of site and approximately half way down east side property line)

Miscellaneous:
·         Subgrade excavation and backfill complete in area north of Building 5, north of lathes, northeast of plywood building, and along east side of plywood building
·         Crushed stone in place in areas listed above
·         Electrical duct-bank stub-outs in place from switchboards MSB1, MSB2, and MSB3