Winston Plywood Progress-6-26-14

This is a weekly update on construction progress at the Winston Plywood and Veneer Facility in Louisvile:

Foundations:
· Placed slab for Building 3 from Column Rows 3-21 (East side of

· Formed and place rebar on Columns A-1, A-3, A-5, and A-9.

· Prepared Old No. 1 dryer demolition area for concrete. Removed soil and filled with crushed concrete. Drilled existing slab for dowels into existing slabs.

· Backfilled and performed grading for grade beam on Building
Building)

Plumbing:

· Installed floor drains and cleanouts for restrooms on east side of

Building:

· Performed detailing on Building 1 at Column Rows 1-5
· Completed detailing and trim-out from Column Rows 6 – 31 on Building No. 1

· Installed framing detailing on north end of Building 1 and Building 5

· Insulation and roofing placed from Column Rows 1-8 on east side

· Install wall girts and trim-out on Building 9 & 10

· Bar-joists complete on Building 5, working on trim-out components

· Began erecting structural steel on Building 3 (East side of plant)


Fire Protection:

· Completed final installation of underground fire line from main fire loop to riser building

· Continued installation of underground service and hydrants on west side of building

· Installed thrust blocks for underground fittings on underground service on west side of building


Electrical:

· Contractor for 13 KV primary power supply continued underground duct banks to transformers and switchboards on south east side of building


https://ssl.gstatic.com/ui/v1/icons/mail/images/cleardot.gif
Building 3 prior to placement of concrete slab