Monday, January 18, 2016

Winston Plywood Update 1-17-16


Foundations:

· Set forms and placed rebar for new charger foundation at Lathe No. 2

Site Utilities:

· Continued installing fire suppression valve boxes on underground piping in area to allow additional paving on east and south sides of plywood building

Buildings:

· Completed gutters on Building 2

· Continued downspouts on Buildings 2, 3, 5, & 9

· Installed roof curbs for boiler stacks in Building 7

· Continued installing Personnel Doors and Rollup Doors on exterior of building

· Continued installing finish trim on buildings 5 and 10


Racetrack Piping:

· Began work on raising piping over circulating fan motors on Dryers No. 1 & 2


High Voltage Electrical:

· Began work on punch list items


Low Voltage Electrical:

· Continued installing lighting in Buildings 3, 8, & 11

· Continued pulling tray cable throughout buildings

· Continued conduit rough-in for block walls in breakrooms, restrooms, and maintenance shop areas

· Continued installing exterior building lighting

Hog Room, Glue Room, Chipper Deck:

· Placed block walls on chipper deck electrical room


Plant Build-Out:

· Filled block at office, restrooms, and breakroom areas with grout

· Began laying block on Column Line F between Buildings 3 and 6, 6A & 7

· Continued installing plumbing rough-in for breakroom and restroom areas; performed pressure test on copper lines on west break room area

Plant Piping:

· No work this week

Site Paving:

· No work this week


Fire Protection System:

· Installed valve boxes in roadway on east side of plywood building

· Installed piping from fire tank fill pump to fire water holding tank


Log Conditioning Vaults:

· Correction for last week’s report:

1. Placed concrete slab for vaults 8, 9, & 10

2. Continued placing rebar for slabs in vaults 11, 12, 13, & 14

· Placed concrete slab for vaults 11, 12, 13, & 14

· Placed balance of concrete walls in water recovery tank and began removing forms from walls following placement

· Began placing backfill sand around water recover tank walls


Log Pro Equipment Foundations:

· Placed fabric and began placing stone for Log Pro foundation section No. 3


Winston Plywood and Utility:

· Continued work on refurbishing and installing lathes No. 1 & 2

· Continued work on refurbishing dryers No. 1 & 2

· Continued work on electrical installation at green-end equipment

· Continued work on installing Dryer No. 3

· Continued fabricating and installing structural steel and setting Log Pro Equipment

· Continued setting MCC units for finishing equipment (Sander and Trim Saws)

· Finished and painted sheetrock on interior of conex control rooms at green-end, and began installing electrical equipment