· Set forms and placed rebar for new charger foundation at Lathe No. 2
Site Utilities:
· Continued installing fire suppression valve boxes on underground piping in area to allow additional paving on east and south sides of plywood building
Buildings:
· Completed gutters on Building 2
· Continued downspouts on Buildings 2, 3, 5, & 9
· Installed roof curbs for boiler stacks in Building 7
· Continued installing Personnel Doors and Rollup Doors on exterior of building
· Continued installing finish trim on buildings 5 and 10
Racetrack Piping:
· Began work on raising piping over circulating fan motors on Dryers No. 1 & 2
High Voltage Electrical:
· Began work on punch list items
Low Voltage Electrical:
· Continued installing lighting in Buildings 3, 8, & 11
· Continued pulling tray cable throughout buildings
· Continued conduit rough-in for block walls in breakrooms, restrooms, and maintenance shop areas
· Continued installing exterior building lighting
Hog Room, Glue Room, Chipper Deck:
· Placed block walls on chipper deck electrical room
Plant Build-Out:
· Filled block at office, restrooms, and breakroom areas with grout
· Began laying block on Column Line F between Buildings 3 and 6, 6A & 7
· Continued installing plumbing rough-in for breakroom and restroom areas; performed pressure test on copper lines on west break room area
Plant Piping:
· No work this week
Site Paving:
· No work this week
Fire Protection System:
· Installed valve boxes in roadway on east side of plywood building
· Installed piping from fire tank fill pump to fire water holding tank
Log Conditioning Vaults:
· Correction for last week’s report:
1. Placed concrete slab for vaults 8, 9, & 10
2. Continued placing rebar for slabs in vaults 11, 12, 13, & 14
· Placed concrete slab for vaults 11, 12, 13, & 14
· Placed balance of concrete walls in water recovery tank and began removing forms from walls following placement
· Began placing backfill sand around water recover tank walls
Log Pro Equipment Foundations:
· Placed fabric and began placing stone for Log Pro foundation section No. 3
Winston Plywood and Utility:
· Continued work on refurbishing and installing lathes No. 1 & 2
· Continued work on refurbishing dryers No. 1 & 2
· Continued work on electrical installation at green-end equipment
· Continued work on installing Dryer No. 3
· Continued fabricating and installing structural steel and setting Log Pro Equipment
· Continued setting MCC units for finishing equipment (Sander and Trim Saws)
· Finished and painted sheetrock on interior of conex control rooms at green-end, and began installing electrical equipment
· Installed valve boxes in roadway on east side of plywood building
· Installed piping from fire tank fill pump to fire water holding tank
Log Conditioning Vaults:
· Correction for last week’s report:
1. Placed concrete slab for vaults 8, 9, & 10
2. Continued placing rebar for slabs in vaults 11, 12, 13, & 14
· Placed concrete slab for vaults 11, 12, 13, & 14
· Placed balance of concrete walls in water recovery tank and began removing forms from walls following placement
· Began placing backfill sand around water recover tank walls
Log Pro Equipment Foundations:
· Placed fabric and began placing stone for Log Pro foundation section No. 3
Winston Plywood and Utility:
· Continued work on refurbishing and installing lathes No. 1 & 2
· Continued work on refurbishing dryers No. 1 & 2
· Continued work on electrical installation at green-end equipment
· Continued work on installing Dryer No. 3
· Continued fabricating and installing structural steel and setting Log Pro Equipment
· Continued setting MCC units for finishing equipment (Sander and Trim Saws)
· Finished and painted sheetrock on interior of conex control rooms at green-end, and began installing electrical equipment