No work
BUILDINGS:
Wall sheets building 10
Complete wall sheets on building 8
Installing gutters on building 4,6,6a, East side.
Detailing fascia trim on 3,4,6,6a,9,10
ELECTRICAL:
Transformer set for RTO.
Pipe Bollards painted at all transformers Continued installing lighting throughout plant Completed large conduit from Electrical rooms Placed remaining housekeeping pads in Electrical rooms
HOG ROOM,GLUE ROOM, CHIPPER DECK
Completed structural steel at glue room
Placed decking for level 2 glue room.
PLANT BUILDOUT
Continued block at office area
Continued placing block at Mezzanine area
SITE PAVING
Placed paving East side approx. 12,000 SF
LOG CONDITIONING VAULTS
Continued backfill at water recovery tank 1st lift Continued forming wall at water recovery tank 2nd lift Placed portion of trench bottom to conditioning vaults.
Continued placing rebar for log conditioning vaults
LOG PRO EQUIPMENT FOUNDATIONS
Tilled area up to attempt to dry. ( per Geotech. Recommendations)
Tilled area up to attempt to dry. ( per Geotech. Recommendations)
This was a short week due to New Years, work outside of the plant was impacted by rain early in the week.