FOUNDATIONS:

No work


BUILDINGS:

Wall sheets building 10

Complete wall sheets on building 8

Installing gutters on building 4,6,6a, East side.

Detailing fascia trim on 3,4,6,6a,9,10


ELECTRICAL:

Transformer set for RTO.

Pipe Bollards painted at all transformers Continued installing lighting throughout plant Completed large conduit from Electrical rooms Placed remaining housekeeping pads in Electrical rooms


HOG ROOM,GLUE ROOM, CHIPPER DECK

Completed structural steel at glue room

Placed decking for level 2 glue room.


PLANT BUILDOUT

Continued block at office area

Continued placing block at Mezzanine area


SITE PAVING

Placed paving East side approx. 12,000 SF


LOG CONDITIONING VAULTS

Continued backfill at water recovery tank 1st lift Continued forming wall at water recovery tank 2nd lift Placed portion of trench bottom to conditioning vaults.

Continued placing rebar for log conditioning vaults


LOG PRO EQUIPMENT FOUNDATIONS

Tilled area up to attempt to dry. ( per Geotech. Recommendations)

This was a short week due to New Years, work outside of the plant was impacted by rain early in the week.