Foundations:
· No work this week
Site Utilities:
· No work this week
Buildings:
· Continued hanging doors and installing door hardware
Racetrack Piping:
· Connected potable and non-potable water to racetrack piping
High Voltage Electrical:
· Continued work on punch list items
Low Voltage Electrical:
· Continued installing lighting in Buildings 8 & 11
· Continued pulling tray cable throughout buildings
· Continued installing exterior building lighting
· Continued setting MCC’s and installing power cables
· Continued terminations in Electrical Rooms
Hog Room, Glue Room, Chipper Deck:
· Removed shoring supports for chipper deck concrete floor
· Began installing stairs at glue room (over first floor wall) and to elevated tank floor
· Continued laying blocks on glue room first floor walls
· Placed grout in block walls on Chipper Deck Electrical Room
Plant Build-Out:
· Continued laying block wall on Column Line “F” (East side of Building 3)
· Continued laying block wall beneath mezzanine at breakroom and restrooms
· Installed HVAC ductwork below mezzanine floor at breakroom and restrooms
Plant Piping:
· Began installing steam piping to Dryers No. 1 and 2
Site Paving:
· Received concrete for continuation of paving
· Performed fine grading to continue site paving east of building
Fire Protection System:
· Continued work on installing valve boxes in roadway on east side and south sides of plywood building
· Continued installing piping from main fire line into fill pump for fire tank
· Continued installing underground piping around fire tank to main fire pump
Log Conditioning Vaults:
· Continued wet curing concrete slab for vaults 11, 12, 13, & 14
· Continued placing backfill sand and select fill material around water storage tank walls
· Assembled and placed form system for first vault wall, and began installing wall embedded steel
· Continued pre-tying rebar mats for vault concrete walls
Log Pro Equipment Foundations:
· Continued placing fabric and stone for Log Pro foundation section No. 3
· Began installing rebar mats and embedded steel plates in foundation section No. 3
Winston Plywood and Utility:
· Continued work on refurbishing and installing Lathes No. 1 & 2
· Worked on assembly of Lathe Charger No. 1
· Continued work on refurbishing Dryers No. 1 & 2
· Continued work on electrical installation at Green-End equipment
· Continued work on installing Dryer No. 3
· Continued fabricating structural support steel for Log Pro equipment
· Began installing MCC units in Chipper Deck Electrical Room
· Continued installing electrical conduit from electrical room to
Log Pro equipment
· Continued installing electrical conduit from electrical room to Green-End equipment
· Continued installing electrical conduit from electrical room to Green-End equipment