Monday, February 29, 2016
Winston Plywood Update- Feb 26
Foundations:
· No work this week
Site Utilities:
· No work this week
Buildings:
· Building contractor onsite to address warranty issues with building leaks
· Continued installing door trim (Front main pedestrian entrance and exterior doors on east side of building)
Racetrack Piping:
· No work this week
High Voltage Electrical:
· No work this week
Low Voltage Electrical:
· Continued installing lighting fixtures in Buildings 6, 6A, & 7
· Continued pulling tray cable throughout buildings (Mainly in green-end area near lathes)
· Continued terminations in Electrical Rooms
· Continued installing electrical conduits to Chipper Deck Electrical Room
· Continued installing lights in glue room and hog room
· Continued installing fire alarm piping, boxes, and wiring
Hog Room, Glue Room, Chipper Deck:
· Continued work on HVAC ductwork in glue room
· Set MCC on second level of Glue Room, installed conduit to MCC, and began pulling power cables to MCC
· Installed support framing for Chipper Deck Electrical Room roofing system, installed insulation, and placed wood perimeter framing
Plant Build-Out:
· Installed HVAC units on all three electrical rooms and installed frames for return air in walls
· Began installing HVAC units in both lathe control rooms (Conex boxes)
· Continued laying block walls in east mezzanine area (Restrooms, breakroom, office area, and maintenance shop)
· Took final measurements on both over head cranes at lathes and maintenance shop for crane & rail fabrication and installation
Plant Piping:
· Continued installing steam piping to Dryers No. 1, 2, and 3
· Continued installing steam piping along east building wall to green-end and vaults
· Continued installing insulation on steam and condensate piping
· Continued running steam and condensate piping along west side of presses
Site Paving:
· Worked on finish grading at south end of plant building
Fire Protection System:
· No work this week
Log Conditioning Vaults:
· Jumped forming system and placed west wall of Vault No. 11
· Installed tee-section on west wall of Vault No. 8
· Completed form work, installed rebar, and set embed plates for Vaults No. 17, 18, 19, & 20
· Jumped forms and began installing rebar for Vault No. 12
· Began forming and placing rebar for tee-section at Vaults 8 & 9
Log Pro Equipment Foundations:
· No work this week
Equipment Foundations (East and West Residuals):
· No work this week
Winston Plywood & Veneer
· Continued work on refurbishing and installing Lathes No. 1 & 2
· Installed chain conveyor through both Lathes and out to chipper
· Continued work on refurbishing Dryers No. 1 & 2
· Continued work on electrical installation at Green-End equipment (conduit and power wiring)
· Continued assembly and installation of Dryer No. 3 (I/F and O/F Sections)
· Continued installing electrical conduit from electrical room to Log Pro equipment (uni-strut, cable tray, and conduit)
· Continued installing electrical conduit from electrical room to Green-End equipment
· Continued installing green-end equipment downstream from lathes
· Set three chippers on Chipper Deck
· Continued installing electrical power to Dryers No. 2 & 3
· Continued making modifications to Stacker for Dryer No. 2 (reverse hand)
· Continued installing pre-presses
Meeting Agenda- March 1
CITY OF LOUISVILLE
TUESDAY, MARCH 1, 2016
REGULAR MEETING AGENDA 5:30 P.M.
- CALL TO ORDER
- INVOCATION
- PLEDGE OF ALLEGIANCE TO FLAG
- APPROVAL OF MINUTES
- NEW BUSINESS
- Docket of Claims #17108-17299 for $130,814.52 -enclosed
- Winston Plywood invoices
- Winston Plywood recommendations
- Airport: Pay Clearwater Consultants $22,500.00 for 2015 AIP Grant for Airport Layout Plan Update
- Saferoom: Pay JBHM $30,000
- Request for Kayla Rogers to attend the Summer Court Clerk Conference, June 27-28, at IP Biloxi
- Request for Babs Fulton to attend an Elections training in Hattiesburg on March 23
- Request for Babs Fulton to attend a Tax training on April 13-14 in Raymond
- E911- Vera McCarty request for training, the APCO MS Chapter Annual Conference, April 17-20, in Tupelo, cost reimbursable
- Request for Todd McCullough to attend MS Recreation & Park Association Field Maintenance Workshop, in Oxford on Wednesday, March 2, registration $30.00
- Discussion of zoning appeal – See enclosed
- Authorize execution of quitclaim deed to Annette Orouke for property erroneously deeded to the City of Louisville
- Unclean Properties:
- Set hearing for dilapidated structure located at 221 South Johnson, owned by Thomas Annie Estes Estate, parcel # 1512-83401-0600800 for April 5, 2016
- Set hearing for unclean property located at 607 West College, owned by James Curtis Triplett, parcel # 151282804-0700400 for April 5, 2016
- Request by Jody Fulton for Cemetery equipment purchase, state contract pricing, $9,649.32, see enclosed
- LPD, request for training for ICS 300, Winston County Courthouse, March 14, 15, & 16, 6:30-9:00 pm. Capt Ronnie Graham, Capt Vernon Eichelberger, Capt Ed Hunt, Capt Donnie Graham, Lt Greg Clark, Lt Barry McWhirter, Sgt Karl Black, & Sgt Tonya McWhirter
- LPD, request for training for Preventing the Escape: The Tactical Transporting of the Prisoner, March 17, 2016, Holmes Community College in Ridgeland, MS for Lawrence Estes, no registration fee
- Louisville Police Department, personnel matter
- OTHER BUSINESS
- ADJOURN
Friday, February 19, 2016
Winston Plywood Update Feb 19
Foundations:
· No work this week
Site Utilities:
· Continued installing protective pipe bollards around fire hydrants
· Continued flushing and testing fire protection loop and sprinkler systems
Buildings:
· Building contractor onsite to address warranty issues with building leaks
Racetrack Piping:
· Continued installing insulation on branch lines from racetrack
· Final inspection was conducted on racetrack trusses and piping. No issues were noted. Hydro test are to be performed on piping.
High Voltage Electrical:
· No work this week
Low Voltage Electrical:
· Continued installing lighting fixtures in Buildings 6, 6A, & 7
· Continued install cable tray and pulling tray cable throughout buildings
· Continued terminations in Electrical Rooms
· Continued installing electrical conduits to Chipper Deck Electrical Room
· Began installing lights in glue room and hog room
Hog Room, Glue Room, Chipper Deck:
· Installed roll-up doors to hog room (2 ea)
· Placed concrete fill in stair treads that access second floor and roof of glue room
· Continued work on HVAC ductwork in glue room
Plant Build-Out:
· Continued installing HVAC branch lines on ductwork at west-side breakrooms and restrooms
· Continued laying block on walls at east-side restrooms, breakroom, boiler room, and air compressor room
Plant Piping:
· Continued installing steam piping to Dryers No. 1, 2, and 3
· Continued installing steam piping along east building wall to green-end and vaults
Site Paving:
· No work this week
Fire Protection System:
· Began filling fire water storage tank with water
· Continued flushing underground fire look and sprinkler systems
Log Conditioning Vaults:
· Continued pre-tying rebar mats for vault concrete walls
· Formed and placed west wall for Vault No. 10
· Completed forming and placed concrete for corner and north wall on Vault No. 7
· Completed form work, installed rebar, and placed floor slabs for Vaults No. 14, 15, and 16
· Began installing rebar mats for floor slab on Vaults 17, 18, 19, and 20
· Began moving forms forward for next vault wall
Log Pro Equipment Foundations:
· Received final design on log deck vertical wall
Equipment Foundations (East and West Residuals):
· Formed, placed, and finished truck bin foundation slab
Winston Plywood & Veneer
· Continued work on refurbishing and installing Lathes No. 1 & 2
· Completed assembly and installed Lathe Charger No. 1
· Continued work on refurbishing Dryers No. 1 & 2
· Continued installation of cable tray for green-end power wiring
· Continued work on electrical installation at Green-End equipment conduit and power
· Continued assembly and installation of Dryer No. 3 (I/F and O/F Sections)
· Continued fabricating structural support steel for step-feeders and lathe infeed equipment
· Continued installing electrical conduit from electrical room to Log Pro equipment (unistrut, cable tray, and conduit)
· Continued installing electrical conduit from electrical room to Green-End equipment
· Continued setting support steel for Log Pro Equipment
· Set debarker frame on support steel
· Installed singulator, infeed conveyor, and tunnel conveyor to debarker
· Continued installing by products drag chains on Log Pro Equipment
· Received both dry veneer stackers and set Dryer No. 3 stacker in place.
· Moved Dryer No. 2 stacker into place and began reversing making modifications to stacker
· Continued installing green-end equipment downstream from lathes
· Continued pre-tying rebar mats for vault concrete walls
· Formed and placed west wall for Vault No. 10
· Completed forming and placed concrete for corner and north wall on Vault No. 7
· Completed form work, installed rebar, and placed floor slabs for Vaults No. 14, 15, and 16
· Began installing rebar mats for floor slab on Vaults 17, 18, 19, and 20
· Began moving forms forward for next vault wall
Log Pro Equipment Foundations:
· Received final design on log deck vertical wall
Equipment Foundations (East and West Residuals):
· Formed, placed, and finished truck bin foundation slab
Winston Plywood & Veneer
· Continued work on refurbishing and installing Lathes No. 1 & 2
· Completed assembly and installed Lathe Charger No. 1
· Continued work on refurbishing Dryers No. 1 & 2
· Continued installation of cable tray for green-end power wiring
· Continued work on electrical installation at Green-End equipment conduit and power
· Continued assembly and installation of Dryer No. 3 (I/F and O/F Sections)
· Continued fabricating structural support steel for step-feeders and lathe infeed equipment
· Continued installing electrical conduit from electrical room to Log Pro equipment (unistrut, cable tray, and conduit)
· Continued installing electrical conduit from electrical room to Green-End equipment
· Continued setting support steel for Log Pro Equipment
· Set debarker frame on support steel
· Installed singulator, infeed conveyor, and tunnel conveyor to debarker
· Continued installing by products drag chains on Log Pro Equipment
· Received both dry veneer stackers and set Dryer No. 3 stacker in place.
· Moved Dryer No. 2 stacker into place and began reversing making modifications to stacker
· Continued installing green-end equipment downstream from lathes
Monday, February 15, 2016
Winston Plywood Weekly Update Feb 12
Foundations:
· Placed base foundation for Lathe No. 1 Charger
Site Utilities:
· Began installing protective pipe bollards around fire hydrants
Buildings:
· No work this week
Racetrack Piping:
· Continued installing insulation on branch lines
High Voltage Electrical:
· No work this week
Low Voltage Electrical:
· Continued installing lighting fixtures in Buildings 6, 6A, and 8
· Turned on building lighting in Building 11
· Turned on exterior lighting on east wall of plant
· Turned power on to convenience outlets in Buildings 1 and 3
· Continued pulling tray cable throughout buildings
· Continued terminations in Electrical Rooms
· Completed installing duct bank for electrical service from primary power to fire system transformer
· Continued installing electrical conduits to Chipper Deck Electrical Room
Hog Room, Glue Room, Chipper Deck:
· Completed installing stairs and handrails at glue room to elevated tank floor, and to roof level over glue tanks
Plant Build-Out:
· Continued installing HVAC branch lines on ductwork at west-side breakrooms and restrooms
Plant Piping:
· Continued installing steam piping to Dryers No. 1, 2, and 3
· Began installing steam piping along east building wall to green-end
Site Paving:
· No work this week
Fire Protection System:
· Placed concrete floors in both buildings at fire pumps
· Installed piping for fire department connections along exterior of east building wall
Log Conditioning Vaults:
· Completed installing sand backfill at holding tank and placed stone base for slab around tank
· Set forms, installed reinforcing, and placed & finished concrete for trench along north end of vaults 15 to 21
· Continued pre-tying rebar mats for vault concrete walls
· Formed and placed west wall for Vault No. 9 (progress impacted by winds on Monday and Tuesday)
· Began forming corner and north wall on Vault No. 7
· Began form work and placed rebar for floor slabs on Vaults No. 15 through 21
Log Pro Equipment Foundations:
· Removed forms from control cab foundation and Section 3A slab
Equipment Foundations (East and West Residuals:
· Placed additional six equipment foundations on west-side equipment
· Formed and placed foundation footings for west-side truck bins
Winston Plywood & Veneer
· Continued work on refurbishing and installing Lathes No. 1 & 2
· Completed assembly of Lathe Charger No. 1
· Continued work on refurbishing Dryers No. 1 & 2
· Set step feeder at Lathe No. 1 Infeed
· Continued installation of cable tray for green-end power wiring
· Continued work on electrical installation at Green-End equipment conduit and power
· Continued assembly and installation of Dryer No. 3 (I/F and O/F Sections)
· Continued fabricating structural support steel for step-feeders and lathe infeed equipment
· Continued installing electrical conduit from electrical room to Log Pro equipment (unistrut, cable tray, and conduit)
· Continued installing electrical conduit from electrical room to Green-End equipment
· Continued setting support steel for Log Pro Equipment
· Began installing by products drag chains on Log Pro Equipment
· Continued installing panel trim-saw equipment
· Received both dry veneer stackers and set Dryer No. 3 stacker in place.
· Pressure washed dry veneer stacker for Dryer No. 2
· Set Debarker Outfeed Tunnel Conveyor and infeed conveyor to
Log Pro Cut-Up system
· Installed structural support steel and Log Pro operator cab
· Installed structural support steel for Debarker Infeed Conveyor
· Began painting structural support steel at Log Pro Equipment
· Installed structural support steel and Log Pro operator cab
· Installed structural support steel for Debarker Infeed Conveyor
· Began painting structural support steel at Log Pro Equipment
Tuesday, February 9, 2016
Tree Giveaway to be Held in Louisville on February 26th
The City of Louisville has partnered with the Mississippi Forestry Commission and the National Arbor Day Foundation to offer the Mississippi Tree Recovery Campaign, in response to the tornado that hit the city on April 28, 2014. The tree giveaway is scheduled to take place on Friday, February 26, 2016, from 1:00 pm – 5:00 pm at the Louisville Coliseum. The event will be hosted by the City of Louisville Parks and Recreation Department and the Winston County Master Gardeners. This (2016) will mark the second year that these organizations worked together to provide a diverse mix of native tree species to homeowners in Tupelo and Louisville.
Monday, February 8, 2016
Winston Plywood Weekly Update 1-24-16
Foundations:
· Formed and installed rebar/embedded steel plates for base foundation at No. 1 Lathe Charger
Site Utilities:
· Flushed underground fire loop around the plant site
Buildings:
· No work this week
Racetrack Piping:
· Continued installing insulation on branch lines from racetrack
High Voltage Electrical:
· Energized power from incoming high voltage to Vista Gear and from Vista gear to Transformers 3 and 5 for building lighting
Low Voltage Electrical:
· Turned on building lighting in Buildings 1, 2, 3, 4, 5, and 10
· Completed installing lighting fixtures in Building 10
· Continued pulling tray cable throughout buildings
· Continued terminations in Electrical Rooms
· Completed cleaning electrical room
· Installed duct bank for electrical service from primary power to fire system transformer
Hog Room, Glue Room, Chipper Deck:
· Continued installing stairs and handrails at glue room (over first floor wall), to elevated tank floor, and to roof level over glue tanks
· Completed laying blocks on glue room first floor walls
Plant Build-Out:
· Continued laying block wall on Column Line “F” (East side of Building 3)
· Completed block wall between boiler room and maintenance shop
· Completed installing HVAC branch lines on ductwork below mezzanine floor at east breakroom
· Continued performing pressure tests on water piping for restrooms and breakrooms
Plant Piping:
· Continued installing steam piping to Dryers No. 1, 2, and 3
Site Paving:
· No work this week
Fire Protection System:
· Finished installing nozzles in fire water storage tank and installed piping to nozzles
· Installed piping from fill pump to water storage tank
· Installed piping from storage tank to fire water pump
· Completed installing water storage tank
Log Conditioning Vaults:
· Continued placing backfill sand and select fill material around water storage tank walls
· Completed assembling forms and placed reinforcing / form system on west wall of Vault No. 7
· Placed west wall on Vault No. 7
· Continued pre-tying rebar mats for vault concrete walls
· Formed, installed reinforcing, and placed west wall for Vault No. 8
· Began forming west wall for Vault No. 9
Log Pro Equipment Foundations:
· Completed placing fabric and stone for Log Pro foundation section No. 3A and placed concrete in 3A
· Completed vertical rebar forms for debarker vertical foundations, and placed debarker foundation
· Formed, installed reinforcing, and placed concrete foundation for Log Pro operator cab
Equipment Foundations (East and West Residuals:
· Placed five equipment foundations
· Placed bag house foundation
Winston Plywood & Veneer
· Continued work on refurbishing and installing Lathes No. 1 & 2
· Continued assembly of Lathe Charger No. 1
· Continued work on refurbishing Dryers No. 1 & 2
· Continued installation of cable tray for green-end power wiring
· Continued work on electrical installation at Green-End equipment conduit and power
· Continued assembly and installation of Dryer No. 3 (I/F, O/F, access steps, door latch hardware, etc)
· Continued fabricating structural support steel for step-feeders and lathe infeed equipment
· Continued installing electrical conduit from electrical room to Log Pro equipment (unistrut, cable tray, and conduit)
· Continued installing electrical conduit from electrical room to Green-End equipment
· Continued setting support steel for Log Pro Equipment
· Installed core conveyor
· Continued installing panel trim-saw equipment
Monday, February 1, 2016
New Police Officers Swearing In
Friends and family gathered at the Louisville City Hall on Tuesday evening as the Louisville Police Department welcome two new officers. Joining the force at LPD are Justin Marshall and Dalton Womble.
The officers were sworn in by Louisville Mayor Will Hill with family members and police chief L. M. Claiborne on hand. The two new officers were later introduced to the Board of Aldermen at the regularly scheduled meeting later that evening.
Justin Marshall |
Dalton Womble |
LtoR: Mayor Will Hill, Justin Marshal, Dalton Womble and L.M. Claiborne |
Winston Plywood Weekly Update- Jan 29
Foundations:
· No work this week
Site Utilities:
· Adjusted valve box elevations for roadway paving on south end of plant
Buildings:
· Continued hanging doors and installing door hardware
· Installed glass in doors and continued installing door hardware
· Building inspection was performed by structural engineer, building manufacturer, building installation contractor, and construction management – five questions were asked during the inspection and all were answered to the satisfaction of inspection team during inspection
Racetrack Piping:
· No work this week
High Voltage Electrical:
· Energized incoming power to plant site from substation to power pole at southwest corner of plant (where electrical feeder goes underground)
· Inspections were performed on gear by electrical engineer and Louisville Electrical Service prior to “Phase I Power-On” to be conducted on Monday
Low Voltage Electrical:
· Continued installing lighting in Building 10
· Continued pulling tray cable throughout buildings
· Completed installing exterior building lighting
· Continued terminations in Electrical Rooms
· Began work on cleaning electrical rooms
· Locks and lockouts were installed on Vista Gear for underground switchgear
Hog Room, Glue Room, Chipper Deck:
· Continued installing stairs at glue room (over first floor wall), to elevated tank floor, and to roof level over glue tanks
· Continued laying blocks on glue room first floor walls
Plant Build-Out:
· Continued laying block wall on Column Line “F” (East side of Building 3)
· Continued laying block wall beneath mezzanine at breakroom and restrooms
· Continued installing HVAC branch lines on ductwork below mezzanine floor at east breakroom
· Received door frames for internal buildings
· Continued performing pressure tests on water piping for restrooms and breakrooms
Plant Piping:
· Continued installing steam piping to Dryers No. 1, 2, and 3
· Began layout on header in boiler room and steam/condensate piping to green-end and vaults
Site Paving:
· Correction from 01-24-2015 progress report
- Received concrete reinforcing for continuation of paving
· Performed fine grading to continue site paving east of building
· Installed rebar and placed concrete in approximately 19,000 SF of site paving on east side of plant
· Installed rebar in approximately 8,000 additional square feet of site paving at southeast corner of plant
Fire Protection System:
· Continued work on installing valve boxes in roadway on east side and south sides of plywood building
· Continued installing piping from main fire line into fill pump for fire tank
· Continued installing underground piping around fire tank to main fire pump
· Completed underground supply line from main fire pump to supply line to plant
Log Conditioning Vaults:
· Completed wet curing concrete slab for vaults 11, 12, 13, & 14 and removed burlap
· Continued placing backfill sand and select fill material around water storage tank walls
· Completed assembling forms and placed reinforcing / form system on west wall of Vault No. 7
· Continued pre-tying rebar mats for vault concrete walls
Log Pro Equipment Foundations:
· Completed placing fabric and stone for Log Pro foundation section No. 3
· Completed installing rebar mats and embedded steel plates in foundation section No. 3
· Placed, finished, and sawcut section No. 3 concrete slab
· Installed vertical rebar and began installing forms for debarker vertical foundations
· Set forms and began placing stone for foundations in section No. 3-A (At log infeed deck to mercher)
Equipment Foundations (East and West Residuals:
· Performed layout for west-side residual handling equipment
· Twelve west-side residual equipment foundations were placed this week
Winston Plywood & Veneer
· Continued work on refurbishing and installing Lathes No. 1 & 2
· Worked on assembly of Lathe Charger No. 1
· Installed Lathe Charger No. 2
· Continued work on refurbishing Dryers No. 1 & 2
· Continued installation of cable tray for green-end power wiring
· Continued work on electrical installation at Green-End equipment conduit and power
· Continued assembly and installation of Dryer No. 3
· Continued fabricating structural support steel for step-feeders and lathe infeed equipment
· Continued installing electrical conduit from electrical room to Log Pro equipment (unistrut and support brackets)
· Continued installing electrical conduit from electrical room to Green-End equipment
· No work this week
Site Utilities:
· Adjusted valve box elevations for roadway paving on south end of plant
Buildings:
· Continued hanging doors and installing door hardware
· Installed glass in doors and continued installing door hardware
· Building inspection was performed by structural engineer, building manufacturer, building installation contractor, and construction management – five questions were asked during the inspection and all were answered to the satisfaction of inspection team during inspection
Racetrack Piping:
· No work this week
High Voltage Electrical:
· Energized incoming power to plant site from substation to power pole at southwest corner of plant (where electrical feeder goes underground)
· Inspections were performed on gear by electrical engineer and Louisville Electrical Service prior to “Phase I Power-On” to be conducted on Monday
Low Voltage Electrical:
· Continued installing lighting in Building 10
· Continued pulling tray cable throughout buildings
· Completed installing exterior building lighting
· Continued terminations in Electrical Rooms
· Began work on cleaning electrical rooms
· Locks and lockouts were installed on Vista Gear for underground switchgear
Hog Room, Glue Room, Chipper Deck:
· Continued installing stairs at glue room (over first floor wall), to elevated tank floor, and to roof level over glue tanks
· Continued laying blocks on glue room first floor walls
Plant Build-Out:
· Continued laying block wall on Column Line “F” (East side of Building 3)
· Continued laying block wall beneath mezzanine at breakroom and restrooms
· Continued installing HVAC branch lines on ductwork below mezzanine floor at east breakroom
· Received door frames for internal buildings
· Continued performing pressure tests on water piping for restrooms and breakrooms
Plant Piping:
· Continued installing steam piping to Dryers No. 1, 2, and 3
· Began layout on header in boiler room and steam/condensate piping to green-end and vaults
Site Paving:
· Correction from 01-24-2015 progress report
- Received concrete reinforcing for continuation of paving
· Performed fine grading to continue site paving east of building
· Installed rebar and placed concrete in approximately 19,000 SF of site paving on east side of plant
· Installed rebar in approximately 8,000 additional square feet of site paving at southeast corner of plant
Fire Protection System:
· Continued work on installing valve boxes in roadway on east side and south sides of plywood building
· Continued installing piping from main fire line into fill pump for fire tank
· Continued installing underground piping around fire tank to main fire pump
· Completed underground supply line from main fire pump to supply line to plant
Log Conditioning Vaults:
· Completed wet curing concrete slab for vaults 11, 12, 13, & 14 and removed burlap
· Continued placing backfill sand and select fill material around water storage tank walls
· Completed assembling forms and placed reinforcing / form system on west wall of Vault No. 7
· Continued pre-tying rebar mats for vault concrete walls
Log Pro Equipment Foundations:
· Completed placing fabric and stone for Log Pro foundation section No. 3
· Completed installing rebar mats and embedded steel plates in foundation section No. 3
· Placed, finished, and sawcut section No. 3 concrete slab
· Installed vertical rebar and began installing forms for debarker vertical foundations
· Set forms and began placing stone for foundations in section No. 3-A (At log infeed deck to mercher)
Equipment Foundations (East and West Residuals:
· Performed layout for west-side residual handling equipment
· Twelve west-side residual equipment foundations were placed this week
Winston Plywood & Veneer
· Continued work on refurbishing and installing Lathes No. 1 & 2
· Worked on assembly of Lathe Charger No. 1
· Installed Lathe Charger No. 2
· Continued work on refurbishing Dryers No. 1 & 2
· Continued installation of cable tray for green-end power wiring
· Continued work on electrical installation at Green-End equipment conduit and power
· Continued assembly and installation of Dryer No. 3
· Continued fabricating structural support steel for step-feeders and lathe infeed equipment
· Continued installing electrical conduit from electrical room to Log Pro equipment (unistrut and support brackets)
· Continued installing electrical conduit from electrical room to Green-End equipment
Subscribe to:
Posts (Atom)