Winston Plywood Weekly Update 1-24-16


Foundations:

· Formed and installed rebar/embedded steel plates for base foundation at No. 1 Lathe Charger

Site Utilities:

· Flushed underground fire loop around the plant site

Buildings:

· No work this week

Racetrack Piping:

· Continued installing insulation on branch lines from racetrack

High Voltage Electrical:
· Energized power from incoming high voltage to Vista Gear and from Vista gear to Transformers 3 and 5 for building lighting

Low Voltage Electrical:

· Turned on building lighting in Buildings 1, 2, 3, 4, 5, and 10

· Completed installing lighting fixtures in Building 10

· Continued pulling tray cable throughout buildings

· Continued terminations in Electrical Rooms

· Completed cleaning electrical room

· Installed duct bank for electrical service from primary power to fire system transformer

Hog Room, Glue Room, Chipper Deck:

· Continued installing stairs and handrails at glue room (over first floor wall), to elevated tank floor, and to roof level over glue tanks

· Completed laying blocks on glue room first floor walls

Plant Build-Out:

· Continued laying block wall on Column Line “F” (East side of Building 3)

· Completed block wall between boiler room and maintenance shop

· Completed installing HVAC branch lines on ductwork below mezzanine floor at east breakroom

· Continued performing pressure tests on water piping for restrooms and breakrooms

Plant Piping:


· Continued installing steam piping to Dryers No. 1, 2, and 3

Site Paving:

· No work this week

Fire Protection System:

· Finished installing nozzles in fire water storage tank and installed piping to nozzles

· Installed piping from fill pump to water storage tank

· Installed piping from storage tank to fire water pump

· Completed installing water storage tank

Log Conditioning Vaults:

· Continued placing backfill sand and select fill material around water storage tank walls

· Completed assembling forms and placed reinforcing / form system on west wall of Vault No. 7

· Placed west wall on Vault No. 7

· Continued pre-tying rebar mats for vault concrete walls

· Formed, installed reinforcing, and placed west wall for Vault No. 8

· Began forming west wall for Vault No. 9

Log Pro Equipment Foundations:

· Completed placing fabric and stone for Log Pro foundation section No. 3A and placed concrete in 3A

· Completed vertical rebar forms for debarker vertical foundations, and placed debarker foundation

· Formed, installed reinforcing, and placed concrete foundation for Log Pro operator cab

Equipment Foundations (East and West Residuals:

· Placed five equipment foundations

· Placed bag house foundation

Winston Plywood & Veneer

· Continued work on refurbishing and installing Lathes No. 1 & 2

· Continued assembly of Lathe Charger No. 1

· Continued work on refurbishing Dryers No. 1 & 2

· Continued installation of cable tray for green-end power wiring

· Continued work on electrical installation at Green-End equipment conduit and power

· Continued assembly and installation of Dryer No. 3 (I/F, O/F, access steps, door latch hardware, etc)

· Continued fabricating structural support steel for step-feeders and lathe infeed equipment

· Continued installing electrical conduit from electrical room to Log Pro equipment (unistrut, cable tray, and conduit)

· Continued installing electrical conduit from electrical room to Green-End equipment

· Continued setting support steel for Log Pro Equipment

· Installed core conveyor

· Continued installing panel trim-saw equipment