Foundations:
· Formed and installed rebar/embedded steel plates for base foundation at No. 1 Lathe Charger
Site Utilities:
· Flushed underground fire loop around the plant site
Buildings:
· No work this week
Racetrack Piping:
· Continued installing insulation on branch lines from racetrack
High Voltage Electrical:
· Energized power from incoming high voltage to Vista Gear and from Vista gear to Transformers 3 and 5 for building lighting
Low Voltage Electrical:
· Turned on building lighting in Buildings 1, 2, 3, 4, 5, and 10
· Completed installing lighting fixtures in Building 10
· Continued pulling tray cable throughout buildings
· Continued terminations in Electrical Rooms
· Completed cleaning electrical room
· Installed duct bank for electrical service from primary power to fire system transformer
Hog Room, Glue Room, Chipper Deck:
· Continued installing stairs and handrails at glue room (over first floor wall), to elevated tank floor, and to roof level over glue tanks
· Completed laying blocks on glue room first floor walls
Plant Build-Out:
· Continued laying block wall on Column Line “F” (East side of Building 3)
· Completed block wall between boiler room and maintenance shop
· Completed installing HVAC branch lines on ductwork below mezzanine floor at east breakroom
· Continued performing pressure tests on water piping for restrooms and breakrooms
Plant Piping:
· Continued installing steam piping to Dryers No. 1, 2, and 3
Site Paving:
· No work this week
Fire Protection System:
· Finished installing nozzles in fire water storage tank and installed piping to nozzles
· Installed piping from fill pump to water storage tank
· Installed piping from storage tank to fire water pump
· Completed installing water storage tank
Log Conditioning Vaults:
· Continued placing backfill sand and select fill material around water storage tank walls
· Completed assembling forms and placed reinforcing / form system on west wall of Vault No. 7
· Placed west wall on Vault No. 7
· Continued pre-tying rebar mats for vault concrete walls
· Formed, installed reinforcing, and placed west wall for Vault No. 8
· Began forming west wall for Vault No. 9
Log Pro Equipment Foundations:
· Completed placing fabric and stone for Log Pro foundation section No. 3A and placed concrete in 3A
· Completed vertical rebar forms for debarker vertical foundations, and placed debarker foundation
· Formed, installed reinforcing, and placed concrete foundation for Log Pro operator cab
Equipment Foundations (East and West Residuals:
· Placed five equipment foundations
· Placed bag house foundation
Winston Plywood & Veneer
· Continued work on refurbishing and installing Lathes No. 1 & 2
· Continued assembly of Lathe Charger No. 1
· Continued work on refurbishing Dryers No. 1 & 2
· Continued installation of cable tray for green-end power wiring
· Continued work on electrical installation at Green-End equipment conduit and power
· Continued assembly and installation of Dryer No. 3 (I/F, O/F, access steps, door latch hardware, etc)
· Continued fabricating structural support steel for step-feeders and lathe infeed equipment
· Continued installing electrical conduit from electrical room to Log Pro equipment (unistrut, cable tray, and conduit)
· Continued installing electrical conduit from electrical room to Green-End equipment
· Continued setting support steel for Log Pro Equipment
· Installed core conveyor
· Continued installing panel trim-saw equipment