Monday, February 29, 2016
Winston Plywood Update- Feb 26
Foundations:
· No work this week
Site Utilities:
· No work this week
Buildings:
· Building contractor onsite to address warranty issues with building leaks
· Continued installing door trim (Front main pedestrian entrance and exterior doors on east side of building)
Racetrack Piping:
· No work this week
High Voltage Electrical:
· No work this week
Low Voltage Electrical:
· Continued installing lighting fixtures in Buildings 6, 6A, & 7
· Continued pulling tray cable throughout buildings (Mainly in green-end area near lathes)
· Continued terminations in Electrical Rooms
· Continued installing electrical conduits to Chipper Deck Electrical Room
· Continued installing lights in glue room and hog room
· Continued installing fire alarm piping, boxes, and wiring
Hog Room, Glue Room, Chipper Deck:
· Continued work on HVAC ductwork in glue room
· Set MCC on second level of Glue Room, installed conduit to MCC, and began pulling power cables to MCC
· Installed support framing for Chipper Deck Electrical Room roofing system, installed insulation, and placed wood perimeter framing
Plant Build-Out:
· Installed HVAC units on all three electrical rooms and installed frames for return air in walls
· Began installing HVAC units in both lathe control rooms (Conex boxes)
· Continued laying block walls in east mezzanine area (Restrooms, breakroom, office area, and maintenance shop)
· Took final measurements on both over head cranes at lathes and maintenance shop for crane & rail fabrication and installation
Plant Piping:
· Continued installing steam piping to Dryers No. 1, 2, and 3
· Continued installing steam piping along east building wall to green-end and vaults
· Continued installing insulation on steam and condensate piping
· Continued running steam and condensate piping along west side of presses
Site Paving:
· Worked on finish grading at south end of plant building
Fire Protection System:
· No work this week
Log Conditioning Vaults:
· Jumped forming system and placed west wall of Vault No. 11
· Installed tee-section on west wall of Vault No. 8
· Completed form work, installed rebar, and set embed plates for Vaults No. 17, 18, 19, & 20
· Jumped forms and began installing rebar for Vault No. 12
· Began forming and placing rebar for tee-section at Vaults 8 & 9
Log Pro Equipment Foundations:
· No work this week
Equipment Foundations (East and West Residuals):
· No work this week
Winston Plywood & Veneer
· Continued work on refurbishing and installing Lathes No. 1 & 2
· Installed chain conveyor through both Lathes and out to chipper
· Continued work on refurbishing Dryers No. 1 & 2
· Continued work on electrical installation at Green-End equipment (conduit and power wiring)
· Continued assembly and installation of Dryer No. 3 (I/F and O/F Sections)
· Continued installing electrical conduit from electrical room to Log Pro equipment (uni-strut, cable tray, and conduit)
· Continued installing electrical conduit from electrical room to Green-End equipment
· Continued installing green-end equipment downstream from lathes
· Set three chippers on Chipper Deck
· Continued installing electrical power to Dryers No. 2 & 3
· Continued making modifications to Stacker for Dryer No. 2 (reverse hand)
· Continued installing pre-presses