Monday, February 29, 2016

Winston Plywood Update- Feb 26


Foundations:

· No work this week

Site Utilities:

· No work this week

Buildings:

· Building contractor onsite to address warranty issues with building leaks

· Continued installing door trim (Front main pedestrian entrance and exterior doors on east side of building)

Racetrack Piping:

· No work this week


High Voltage Electrical:

· No work this week

Low Voltage Electrical:

· Continued installing lighting fixtures in Buildings 6, 6A, & 7

· Continued pulling tray cable throughout buildings (Mainly in green-end area near lathes)

· Continued terminations in Electrical Rooms

· Continued installing electrical conduits to Chipper Deck Electrical Room

· Continued installing lights in glue room and hog room

· Continued installing fire alarm piping, boxes, and wiring

Hog Room, Glue Room, Chipper Deck:

· Continued work on HVAC ductwork in glue room

· Set MCC on second level of Glue Room, installed conduit to MCC, and began pulling power cables to MCC

· Installed support framing for Chipper Deck Electrical Room roofing system, installed insulation, and placed wood perimeter framing


Plant Build-Out:

· Installed HVAC units on all three electrical rooms and installed frames for return air in walls

· Began installing HVAC units in both lathe control rooms (Conex boxes)

· Continued laying block walls in east mezzanine area (Restrooms, breakroom, office area, and maintenance shop)

· Took final measurements on both over head cranes at lathes and maintenance shop for crane & rail fabrication and installation



Plant Piping:

· Continued installing steam piping to Dryers No. 1, 2, and 3

· Continued installing steam piping along east building wall to green-end and vaults

· Continued installing insulation on steam and condensate piping

· Continued running steam and condensate piping along west side of presses


Site Paving:

· Worked on finish grading at south end of plant building


Fire Protection System:

· No work this week


Log Conditioning Vaults:

· Jumped forming system and placed west wall of Vault No. 11

· Installed tee-section on west wall of Vault No. 8

· Completed form work, installed rebar, and set embed plates for Vaults No. 17, 18, 19, & 20

· Jumped forms and began installing rebar for Vault No. 12

· Began forming and placing rebar for tee-section at Vaults 8 & 9


Log Pro Equipment Foundations:

· No work this week



Equipment Foundations (East and West Residuals):

· No work this week

Winston Plywood & Veneer

· Continued work on refurbishing and installing Lathes No. 1 & 2

· Installed chain conveyor through both Lathes and out to chipper

· Continued work on refurbishing Dryers No. 1 & 2

· Continued work on electrical installation at Green-End equipment (conduit and power wiring)

· Continued assembly and installation of Dryer No. 3 (I/F and O/F Sections)

· Continued installing electrical conduit from electrical room to Log Pro equipment (uni-strut, cable tray, and conduit)

· Continued installing electrical conduit from electrical room to Green-End equipment

· Continued installing green-end equipment downstream from lathes

· Set three chippers on Chipper Deck

· Continued installing electrical power to Dryers No. 2 & 3

· Continued making modifications to Stacker for Dryer No. 2 (reverse hand)

· Continued installing pre-presses