Winston Plywood Weekly Update Feb 12


Foundations:
· Placed base foundation for Lathe No. 1 Charger

Site Utilities:
· Began installing protective pipe bollards around fire hydrants

Buildings:
· No work this week

Racetrack Piping:

· Continued installing insulation on branch lines

High Voltage Electrical:
· No work this week

Low Voltage Electrical:
· Continued installing lighting fixtures in Buildings 6, 6A, and 8
· Turned on building lighting in Building 11
· Turned on exterior lighting on east wall of plant
· Turned power on to convenience outlets in Buildings 1 and 3
· Continued pulling tray cable throughout buildings
· Continued terminations in Electrical Rooms
· Completed installing duct bank for electrical service from primary power to fire system transformer
· Continued installing electrical conduits to Chipper Deck Electrical Room

Hog Room, Glue Room, Chipper Deck:
· Completed installing stairs and handrails at glue room to elevated tank floor, and to roof level over glue tanks

Plant Build-Out:
· Continued installing HVAC branch lines on ductwork at west-side breakrooms and restrooms

Plant Piping:

· Continued installing steam piping to Dryers No. 1, 2, and 3
· Began installing steam piping along east building wall to green-end

Site Paving:

· No work this week

Fire Protection System:

· Placed concrete floors in both buildings at fire pumps
· Installed piping for fire department connections along exterior of east building wall

Log Conditioning Vaults:

· Completed installing sand backfill at holding tank and placed stone base for slab around tank
· Set forms, installed reinforcing, and placed & finished concrete for trench along north end of vaults 15 to 21
· Continued pre-tying rebar mats for vault concrete walls
· Formed and placed west wall for Vault No. 9 (progress impacted by winds on Monday and Tuesday)
· Began forming corner and north wall on Vault No. 7
· Began form work and placed rebar for floor slabs on Vaults No. 15 through 21

Log Pro Equipment Foundations:
· Removed forms from control cab foundation and Section 3A slab

Equipment Foundations (East and West Residuals:
· Placed additional six equipment foundations on west-side equipment
· Formed and placed foundation footings for west-side truck bins

Winston Plywood & Veneer

· Continued work on refurbishing and installing Lathes No. 1 & 2
· Completed assembly of Lathe Charger No. 1
· Continued work on refurbishing Dryers No. 1 & 2
· Set step feeder at Lathe No. 1 Infeed
· Continued installation of cable tray for green-end power wiring
· Continued work on electrical installation at Green-End equipment conduit and power
· Continued assembly and installation of Dryer No. 3 (I/F and O/F Sections)
· Continued fabricating structural support steel for step-feeders and lathe infeed equipment
· Continued installing electrical conduit from electrical room to Log Pro equipment (unistrut, cable tray, and conduit)
· Continued installing electrical conduit from electrical room to Green-End equipment
· Continued setting support steel for Log Pro Equipment
· Began installing by products drag chains on Log Pro Equipment
· Continued installing panel trim-saw equipment
· Received both dry veneer stackers and set Dryer No. 3 stacker in place.
· Pressure washed dry veneer stacker for Dryer No. 2
· Set Debarker Outfeed Tunnel Conveyor and infeed conveyor to

Log Pro Cut-Up system
· Installed structural support steel and Log Pro operator cab
· Installed structural support steel for Debarker Infeed Conveyor
· Began painting structural support steel at Log Pro Equipment