Monday, February 1, 2016

Winston Plywood Weekly Update- Jan 29

Foundations:

· No work this week

Site Utilities:

· Adjusted valve box elevations for roadway paving on south end of plant

Buildings:

· Continued hanging doors and installing door hardware

· Installed glass in doors and continued installing door hardware

· Building inspection was performed by structural engineer, building manufacturer, building installation contractor, and construction management – five questions were asked during the inspection and all were answered to the satisfaction of inspection team during inspection

Racetrack Piping:

· No work this week

High Voltage Electrical:

· Energized incoming power to plant site from substation to power pole at southwest corner of plant (where electrical feeder goes underground)

· Inspections were performed on gear by electrical engineer and Louisville Electrical Service prior to “Phase I Power-On” to be conducted on Monday


Low Voltage Electrical:

· Continued installing lighting in Building 10

· Continued pulling tray cable throughout buildings

· Completed installing exterior building lighting

· Continued terminations in Electrical Rooms

· Began work on cleaning electrical rooms

· Locks and lockouts were installed on Vista Gear for underground switchgear


Hog Room, Glue Room, Chipper Deck:

· Continued installing stairs at glue room (over first floor wall), to elevated tank floor, and to roof level over glue tanks

· Continued laying blocks on glue room first floor walls


Plant Build-Out:

· Continued laying block wall on Column Line “F” (East side of Building 3)

· Continued laying block wall beneath mezzanine at breakroom and restrooms

· Continued installing HVAC branch lines on ductwork below mezzanine floor at east breakroom

· Received door frames for internal buildings

· Continued performing pressure tests on water piping for restrooms and breakrooms


Plant Piping:

· Continued installing steam piping to Dryers No. 1, 2, and 3

· Began layout on header in boiler room and steam/condensate piping to green-end and vaults

Site Paving:

· Correction from 01-24-2015 progress report

- Received concrete reinforcing for continuation of paving

· Performed fine grading to continue site paving east of building

· Installed rebar and placed concrete in approximately 19,000 SF of site paving on east side of plant

· Installed rebar in approximately 8,000 additional square feet of site paving at southeast corner of plant


Fire Protection System:

· Continued work on installing valve boxes in roadway on east side and south sides of plywood building

· Continued installing piping from main fire line into fill pump for fire tank

· Continued installing underground piping around fire tank to main fire pump

· Completed underground supply line from main fire pump to supply line to plant


Log Conditioning Vaults:

· Completed wet curing concrete slab for vaults 11, 12, 13, & 14 and removed burlap

· Continued placing backfill sand and select fill material around water storage tank walls

· Completed assembling forms and placed reinforcing / form system on west wall of Vault No. 7

· Continued pre-tying rebar mats for vault concrete walls


Log Pro Equipment Foundations:

· Completed placing fabric and stone for Log Pro foundation section No. 3

· Completed installing rebar mats and embedded steel plates in foundation section No. 3

· Placed, finished, and sawcut section No. 3 concrete slab

· Installed vertical rebar and began installing forms for debarker vertical foundations

· Set forms and began placing stone for foundations in section No. 3-A (At log infeed deck to mercher)


Equipment Foundations (East and West Residuals:

· Performed layout for west-side residual handling equipment

· Twelve west-side residual equipment foundations were placed this week


Winston Plywood & Veneer

· Continued work on refurbishing and installing Lathes No. 1 & 2

· Worked on assembly of Lathe Charger No. 1

· Installed Lathe Charger No. 2

· Continued work on refurbishing Dryers No. 1 & 2

· Continued installation of cable tray for green-end power wiring

· Continued work on electrical installation at Green-End equipment conduit and power

· Continued assembly and installation of Dryer No. 3

· Continued fabricating structural support steel for step-feeders and lathe infeed equipment

· Continued installing electrical conduit from electrical room to Log Pro equipment (unistrut and support brackets)

· Continued installing electrical conduit from electrical room to Green-End equipment