· No work this week
Site Utilities:
· Adjusted valve box elevations for roadway paving on south end of plant
Buildings:
· Continued hanging doors and installing door hardware
· Installed glass in doors and continued installing door hardware
· Building inspection was performed by structural engineer, building manufacturer, building installation contractor, and construction management – five questions were asked during the inspection and all were answered to the satisfaction of inspection team during inspection
Racetrack Piping:
· No work this week
High Voltage Electrical:
· Energized incoming power to plant site from substation to power pole at southwest corner of plant (where electrical feeder goes underground)
· Inspections were performed on gear by electrical engineer and Louisville Electrical Service prior to “Phase I Power-On” to be conducted on Monday
Low Voltage Electrical:
· Continued installing lighting in Building 10
· Continued pulling tray cable throughout buildings
· Completed installing exterior building lighting
· Continued terminations in Electrical Rooms
· Began work on cleaning electrical rooms
· Locks and lockouts were installed on Vista Gear for underground switchgear
Hog Room, Glue Room, Chipper Deck:
· Continued installing stairs at glue room (over first floor wall), to elevated tank floor, and to roof level over glue tanks
· Continued laying blocks on glue room first floor walls
Plant Build-Out:
· Continued laying block wall on Column Line “F” (East side of Building 3)
· Continued laying block wall beneath mezzanine at breakroom and restrooms
· Continued installing HVAC branch lines on ductwork below mezzanine floor at east breakroom
· Received door frames for internal buildings
· Continued performing pressure tests on water piping for restrooms and breakrooms
Plant Piping:
· Continued installing steam piping to Dryers No. 1, 2, and 3
· Began layout on header in boiler room and steam/condensate piping to green-end and vaults
Site Paving:
· Correction from 01-24-2015 progress report
- Received concrete reinforcing for continuation of paving
· Performed fine grading to continue site paving east of building
· Installed rebar and placed concrete in approximately 19,000 SF of site paving on east side of plant
· Installed rebar in approximately 8,000 additional square feet of site paving at southeast corner of plant
Fire Protection System:
· Continued work on installing valve boxes in roadway on east side and south sides of plywood building
· Continued installing piping from main fire line into fill pump for fire tank
· Continued installing underground piping around fire tank to main fire pump
· Completed underground supply line from main fire pump to supply line to plant
Log Conditioning Vaults:
· Completed wet curing concrete slab for vaults 11, 12, 13, & 14 and removed burlap
· Continued placing backfill sand and select fill material around water storage tank walls
· Completed assembling forms and placed reinforcing / form system on west wall of Vault No. 7
· Continued pre-tying rebar mats for vault concrete walls
Log Pro Equipment Foundations:
· Completed placing fabric and stone for Log Pro foundation section No. 3
· Completed installing rebar mats and embedded steel plates in foundation section No. 3
· Placed, finished, and sawcut section No. 3 concrete slab
· Installed vertical rebar and began installing forms for debarker vertical foundations
· Set forms and began placing stone for foundations in section No. 3-A (At log infeed deck to mercher)
Equipment Foundations (East and West Residuals:
· Performed layout for west-side residual handling equipment
· Twelve west-side residual equipment foundations were placed this week
Winston Plywood & Veneer
· Continued work on refurbishing and installing Lathes No. 1 & 2
· Worked on assembly of Lathe Charger No. 1
· Installed Lathe Charger No. 2
· Continued work on refurbishing Dryers No. 1 & 2
· Continued installation of cable tray for green-end power wiring
· Continued work on electrical installation at Green-End equipment conduit and power
· Continued assembly and installation of Dryer No. 3
· Continued fabricating structural support steel for step-feeders and lathe infeed equipment
· Continued installing electrical conduit from electrical room to Log Pro equipment (unistrut and support brackets)
· Continued installing electrical conduit from electrical room to Green-End equipment