Foundations:
· No work this week
Site Utilities:
· Continued installing protective pipe bollards around fire hydrants
· Continued flushing and testing fire protection loop and sprinkler systems
Buildings:
· Building contractor onsite to address warranty issues with building leaks
Racetrack Piping:
· Continued installing insulation on branch lines from racetrack
· Final inspection was conducted on racetrack trusses and piping. No issues were noted. Hydro test are to be performed on piping.
High Voltage Electrical:
· No work this week
Low Voltage Electrical:
· Continued installing lighting fixtures in Buildings 6, 6A, & 7
· Continued install cable tray and pulling tray cable throughout buildings
· Continued terminations in Electrical Rooms
· Continued installing electrical conduits to Chipper Deck Electrical Room
· Began installing lights in glue room and hog room
Hog Room, Glue Room, Chipper Deck:
· Installed roll-up doors to hog room (2 ea)
· Placed concrete fill in stair treads that access second floor and roof of glue room
· Continued work on HVAC ductwork in glue room
Plant Build-Out:
· Continued installing HVAC branch lines on ductwork at west-side breakrooms and restrooms
· Continued laying block on walls at east-side restrooms, breakroom, boiler room, and air compressor room
Plant Piping:
· Continued installing steam piping to Dryers No. 1, 2, and 3
· Continued installing steam piping along east building wall to green-end and vaults
Site Paving:
· No work this week
Fire Protection System:
· Began filling fire water storage tank with water
· Continued flushing underground fire look and sprinkler systems
Log Conditioning Vaults:
· Continued pre-tying rebar mats for vault concrete walls
· Formed and placed west wall for Vault No. 10
· Completed forming and placed concrete for corner and north wall on Vault No. 7
· Completed form work, installed rebar, and placed floor slabs for Vaults No. 14, 15, and 16
· Began installing rebar mats for floor slab on Vaults 17, 18, 19, and 20
· Began moving forms forward for next vault wall
Log Pro Equipment Foundations:
· Received final design on log deck vertical wall
Equipment Foundations (East and West Residuals):
· Formed, placed, and finished truck bin foundation slab
Winston Plywood & Veneer
· Continued work on refurbishing and installing Lathes No. 1 & 2
· Completed assembly and installed Lathe Charger No. 1
· Continued work on refurbishing Dryers No. 1 & 2
· Continued installation of cable tray for green-end power wiring
· Continued work on electrical installation at Green-End equipment conduit and power
· Continued assembly and installation of Dryer No. 3 (I/F and O/F Sections)
· Continued fabricating structural support steel for step-feeders and lathe infeed equipment
· Continued installing electrical conduit from electrical room to Log Pro equipment (unistrut, cable tray, and conduit)
· Continued installing electrical conduit from electrical room to Green-End equipment
· Continued setting support steel for Log Pro Equipment
· Set debarker frame on support steel
· Installed singulator, infeed conveyor, and tunnel conveyor to debarker
· Continued installing by products drag chains on Log Pro Equipment
· Received both dry veneer stackers and set Dryer No. 3 stacker in place.
· Moved Dryer No. 2 stacker into place and began reversing making modifications to stacker
· Continued installing green-end equipment downstream from lathes
· Continued pre-tying rebar mats for vault concrete walls
· Formed and placed west wall for Vault No. 10
· Completed forming and placed concrete for corner and north wall on Vault No. 7
· Completed form work, installed rebar, and placed floor slabs for Vaults No. 14, 15, and 16
· Began installing rebar mats for floor slab on Vaults 17, 18, 19, and 20
· Began moving forms forward for next vault wall
Log Pro Equipment Foundations:
· Received final design on log deck vertical wall
Equipment Foundations (East and West Residuals):
· Formed, placed, and finished truck bin foundation slab
Winston Plywood & Veneer
· Continued work on refurbishing and installing Lathes No. 1 & 2
· Completed assembly and installed Lathe Charger No. 1
· Continued work on refurbishing Dryers No. 1 & 2
· Continued installation of cable tray for green-end power wiring
· Continued work on electrical installation at Green-End equipment conduit and power
· Continued assembly and installation of Dryer No. 3 (I/F and O/F Sections)
· Continued fabricating structural support steel for step-feeders and lathe infeed equipment
· Continued installing electrical conduit from electrical room to Log Pro equipment (unistrut, cable tray, and conduit)
· Continued installing electrical conduit from electrical room to Green-End equipment
· Continued setting support steel for Log Pro Equipment
· Set debarker frame on support steel
· Installed singulator, infeed conveyor, and tunnel conveyor to debarker
· Continued installing by products drag chains on Log Pro Equipment
· Received both dry veneer stackers and set Dryer No. 3 stacker in place.
· Moved Dryer No. 2 stacker into place and began reversing making modifications to stacker
· Continued installing green-end equipment downstream from lathes