Foundations:
· Placed 100’ of footing wall foundations on Column Row A (West side of plant building)
· Prepared foundations for part of Building 9 and for slab replacement at demo site of old No. 1 Dryer
Building:
· Completed roofing on Building 1 on east side from column rows 3-23
· Continued installing insulation and began installing roofing on west side of Building 1, completing from column rows 1- 7. Continued setting columns, rafters, and bar joists on Building 3 (from column rows 5-11)
· Continued framing trim-out and detailing on Buildings 1, 5, and 9
Fire Protection:
· Sprinkler contractor mobilized to the site, received materials, and began installation of ceiling sprinkler system in Building No. 1. Sprinkler piping is in place from column rows 19-23
Electrical:
· Contractor for 13 KV primary power supply completed underground duct banks to transformers 5-13 (northeast corner of plant), and began layout and construction of underground to transformers 1-4 (southeast corner of plant)
Miscellaneous
· Received Nicholson A-8 Debarker frame and Log-Pro merchandising equipment