Winston Plywood Progress - July 24, 2015
· Placed balance of concrete wall and piers on Column Row A (For Building 2)
· Continued placing stone base for concrete slab in Building 2 (North End – between new concrete wall and existing building slab)
· Installed crushed concrete base for slab in buildings 9 & 10; Installed vapor barrier and reinforcing for these buildings as well
· Continued undercut and backfill in Area 1 east of plant in preparation for concrete paving
Building:
· Continued installing insulation and roofing on west side of Building 1, completing from column rows 3-22.
· Completed decking on Building 1 west side from column rows 3-28; insulation placed to column row 24
· Completed setting rafters on building 3; set bar joists to column row 21 and half of bay from columns 21-23
· Continued framing trim-out and detailing on Buildings 1, 3, 5, 9, and 10
· Began decking on building 5 (clear-span loading area)
· Began insulation and roofing on buildings 9-10
Fire Protection:
· Contractor continued installing sprinklers in roof of Building 1; Contractor is hanging sprinkler piping in north to south direction; piping is in place from columns 23-13
Electrical:
· Continued layout and construction of primary underground piping to transformers 5-13 (north east corner of building 2), and transformers 1-4 (southeast corner of building 2)
Site & Utilities:
· Cleared rubbish and prepared drainage ditch west of parking lot and placed rip-rap material
Winston Plywood
· Continued removing old presses and related equipment
· Continued refurbishing existing veneer dryers