Saturday, July 18, 2015

Winston Plywood Progress - July 17, 2015

Foundations:
·         Placed balance of footing wall foundations on Column Row A (For
Building 2)
·         Placed forms for concrete wall on south end of Column Row A (For Building 2)
·         Began placing stone base for concrete slab in Building 2 (North End)
·         Removed unsuitable materials and installed crushed concrete base for slab in buildings 9 & 10
·         Removed unsuitable materials to install stone base for slab at glue room
·         Began undercut and backfill in Area 1 east of plant for concrete paving

Building:
·         Continued installing insulation and roofing on west side of Building 1, completing from column rows 1- 21.
·         Continued setting columns, rafters, and bar joists on Building 3 (from column rows 5-11)
·         Continued framing trim-out and detailing on Buildings 1, 5, and 9
·         Continued framing on building 2
·         Received structural framing materials for Buildings 6, 6A, 7, 8, and 11.
·         Began erecting structural steel on Building 7 & 8

Fire Protection:
·         Contractor continued installing sprinklers in roof of Building 1

Electrical:
·         Continued layout and construction of primary underground piping to transformers 5-13 (north east corner of building 2), and transformers 1-4 (southeast corner of building 2)

Winston Plywood
·         Began removing old presses and related equipment
·         Continued refurbishing existing veneer dryers