Monday, September 7, 2015

Winston Plywood Update-9-4-15



Foundations:
·         Placed and finished Building 4 slab
·         Continued forming foundations for green chipper in Building 10
·         Formed and placed rebar for final section of slab for Building 2
·         Began block work on Hog Room
·         Finished forming for placement of Boiler Room slab.  Slab is to be placed tonight.
·         Placed concrete around dryer wash water drain piping

Building:
·         Continued installing standing-seam roof on Buildings 3 and 8
·         Continued installing beams and joists on Building 2 (West side of overall building)
·         Continued erecting structural steel framing for Lathe & Chipper Deck
·         Continued trim-out and detailing on Building 2 & 3 structural steel

Fire Protection:
·         Continued installing sprinkler system in Building 3
·         Completed tie-in on systems in Buildings 5, 9, & 10

Electrical:
·         Completed concrete foundations for transformers No. 1-4
·         Continued installing primary power and grounding at transformers 1-4  (at south end of Building No. 3)
·         Continued finish grading and placement of stone around transformers 5-13
·         Continued block work on electrical room (southeast corner of Building 3)

Winston Plywood:
·         Continued refurbishing existing veneer dryers
·         Continued refurbishing and installing green-end equipment for west lathe line
·         Received and off-loaded additional loads of green-end equipment
·         Received and off-loaded additional Log-Pro equipment for log processing

Miscellaneous:
·         Held pre-con meetings for Plant Electrical, Plant Piping (Racetrack), and Site Paving Packages

Progress photo’s attached:
·         6258       Building 4 ready for concrete placement
·         6331       Building 4 slab in place and finished
·         6343       Electrical room block work and transformer pads in place
·         6355       Forms and rebar in place for Boiler Room slab
·         6363       West lathe line equipment being installed (1)
·         6364       West lathe line equipment being installed (2)
·         6369       Building as of 09-04-2015