Foundations:
· Placed and finished Building 4 slab
· Continued forming foundations for green chipper in Building 10
· Formed and placed rebar for final section of slab for Building 2
· Began block work on Hog Room
· Finished forming for placement of Boiler Room slab. Slab is to be placed tonight.
· Placed concrete around dryer wash water drain piping
Building:
· Continued installing standing-seam roof on Buildings 3 and 8
· Continued installing beams and joists on Building 2 (West side of overall building)
· Continued erecting structural steel framing for Lathe & Chipper Deck
· Continued trim-out and detailing on Building 2 & 3 structural steel
Fire Protection:
· Continued installing sprinkler system in Building 3
· Completed tie-in on systems in Buildings 5, 9, & 10
Electrical:
· Completed concrete foundations for transformers No. 1-4
· Continued installing primary power and grounding at transformers 1-4 (at south end of Building No. 3)
· Continued finish grading and placement of stone around transformers 5-13
· Continued block work on electrical room (southeast corner of Building 3)
Winston Plywood:
· Continued refurbishing existing veneer dryers
· Continued refurbishing and installing green-end equipment for west lathe line
· Received and off-loaded additional loads of green-end equipment
· Received and off-loaded additional Log-Pro equipment for log processing
Miscellaneous:
· Held pre-con meetings for Plant Electrical, Plant Piping (Racetrack), and Site Paving Packages
Progress photo’s attached:
· 6258 Building 4 ready for concrete placement
· 6331 Building 4 slab in place and finished
· 6343 Electrical room block work and transformer pads in place
· 6355 Forms and rebar in place for Boiler Room slab
· 6363 West lathe line equipment being installed (1)
· 6364 West lathe line equipment being installed (2)
· 6369 Building as of 09-04-2015