Winston Plywood Weekly Update-9-11-2015
Foundations:
· Formed, placed, and finished final section of slab for Building 2
· Continued block work on Hog Room
· Placed and finished Boiler Room and Air Compressor Room slab
· Began work on Green-end Electrical Room
· Began formwork on Sander Foundation in finishing area
· Placed and finished foundation walls for Green Chipper
Building:
· Continued installing standing-seam roof on Buildings 3 and 8
· Continued installing insulation and water seal on Buildings 3 & 7
· Continued installing beams and joists on Building 2 (West side of overall building)
· Continued erecting structural steel framing for Lathe & Chipper Deck
· Continued trim-out and detailing on Building 2 & 3 structural steel
· Seamed roofing sheets on Buildings 1, 9, and 10
· Continued installing wall girts on Building 3
Fire Protection:
· Continued installing sprinkler system in Building 3
· Completed tie-in on systems in Buildings 5, 9, & 10
· Began installing risers and system control valves
Electrical:
· Continued installing primary power at transformers 1-4 (at south end of Building No. 3)
· Continued finish grading and placement of stone around transformers 5-13
· Completed block work on electrical room (southeast corner of Building 3)
· Began block work on green-end electrical room
· Continued underground primary power supply (moving west through previous RTO site)
Winston Plywood:
· Continued refurbishing existing veneer dryers
· Continued refurbishing and installing green-end equipment for west lathe line
· Received and off-loaded additional loads of green-end equipment
· Received and off-loaded additional Log-Pro equipment for log processing
· Began installation of base plates for boiler installation