·Formed, placed, and finished final section of slab for Building 2 ·Continued block work on Hog Room ·Placed and finished Boiler Room and Air Compressor Room slab ·Began work on Green-end Electrical Room ·Began formwork on Sander Foundation in finishing area ·Placed and finished foundation walls for Green Chipper
Building:
·Continued installing standing-seam roof on Buildings 3 and 8 ·Continued installing insulation and water seal on Buildings 3 & 7 ·Continued installing beams and joists on Building 2 (West side of overall building) ·Continued erecting structural steel framing for Lathe & Chipper Deck ·Continued trim-out and detailing on Building 2 & 3 structural steel ·Seamed roofing sheets on Buildings 1, 9, and 10 ·Continued installing wall girts on Building 3
Fire Protection:
·Continued installing sprinkler system in Building 3 ·Completed tie-in on systems in Buildings 5, 9, & 10 ·Began installing risers and system control valves
Electrical:
·Continued installing primary power at transformers 1-4 (at south end of Building No. 3) ·Continued finish grading and placement of stone around transformers 5-13 ·Completed block work on electrical room (southeast corner of Building 3) ·Began block work on green-end electrical room ·Continued underground primary power supply (moving west through previous RTO site)
Winston Plywood:
·Continued refurbishing existing veneer dryers ·Continued refurbishing and installing green-end equipment for west lathe line ·Received and off-loaded additional loads of green-end equipment ·Received and off-loaded additional Log-Pro equipment for log processing ·Began installation of base plates for boiler installation