Foundations:
· Continued to set forms and install rebar on pedestals for lathe chargers
Buildings:
· Completed seaming roof panels on Buildings 3 and 4
· Continued installing wall sheets and translucent panels on Building 4
· Continued installing wall sheets on north end of Building 5
· Completed framing and began installing decking on mezzanine in Building 7
· Completed installing standing-seam roofing on Building 8
· Began installing standing-seam roof on Building 11
Fire Protection:
· Continued installing hose station piping
· Continued installing drum-drips and drains for sprinkler systems
· Continued installing underground fire loop, specifically along the north side of the existing main parking lot
· Installed two hydrants in parking lot area
· Continued installing underground sectional valve boxes
· Continued erecting fire water storage tank
Hog Room, Glue Room, and Lathe & Chipper Deck:
· Continued erecting structural steel on Glue Room
· Installed roof decking on glue rooms and hog room
· Demo’d forms on glue room containment wall and finished walls
Electrical:
· Continued electrical rough-in for lighting and miscellaneous electrical
· Completed lighting mock-up installation on building lighting; Mock-up was approved
· Continued installing cable tray throughout the plant
· Completed installing electrical switchgear in center electrical room and continued pulling primary feeders
· Began installing electrical switchgear in north electrical room
· Continued running conduit for process equipment at green-end, dryers, presses, and dry-end
· Continued installing primary underground service to transformers 9-13
Site Utilities:
· Completed installing water line from connection at City of Louisville main water line
Racetrack Piping:
· Received and installed additional sections of racetrack trusses and piping; two sections remain to be installed on east side of racetrack, as well as north and south sections of track
· Continued installing flexible connections between sections of racetrack piping
· Continued installing support hangers for branch lines from the racetrack piping
· Continued installation of branch lines for process water and air piping from racetrack
Boiler and Steam:
· Installed support structure and DA tank for boilers
Log Conditioning Vaults
· Placed stone, set forms, and began installing rebar for floor slab in holding tank for vaults
Log Pro Merchandiser:
· Received remaining embed plates and rebar for foundations
· Began grading foundation site to finish grade
Winston Plywood:
· Continued refurbishing and installing green-end equipment for both east and west lathe lines
· Continued to receive both new and used process equipment
· Continued construction of No. 3 Veneer Dryer (Dryer main framework and heating coils)
· Continued concrete base and wall modifications in Press Pit No. 3
· Continued to set layup line and finishing line equipment
Miscellaneous:
· Made tie-in at main substation for new primary electrical line to plywood plant
· Received 2.6” of rain through noon Friday of this week