· Removed forms for sander foundation
· Connected sanitary sewer to west restrooms
· Installed grating in boiler room drains trenches
Building:
· Installed decking on Building 8
· Started installing decking on Building
· Continued installing standing seam roofing on Building 2 & 3, and started installing on Building 4
· Continued installing louvers on west wall of Building 2 and started installing on Building 4
· Started installing louvers on east wall of Building 3
· Installed framed opening for 16’ door on Building 8
· Continued installing personnel doors on Buildings 8 and 11
· Completed installing edge angles for decking on Building 8
· Continued installing wall sheets on west side of Building 1 (upper wall section)
· Continued installing wall sheets on west side of Building 2
· Started pressure washing structural steel framing
· Began installing decking on Building 6A
Fire Protection:
· Continued installing pipe bracings and supports throughout buildings
· Received partial shipment of piping for Buildings 8 & 11
Hog Room, Glue Room, and Lathe & Chipper Deck:
· Began erecting structural steel on Glue Room
· Began installing glue tanks in glue room
Electrical:
· Continued electrical rough-in for lighting and miscellaneous electrical in Buildings 1, 2, 3, 5 and 9, and continued rough-in for lighting in building 4 (Conduit and junction boxes)
· Received shipment of cable tray for electrical installations
· Started installing cable tray throughout the plant
· Completed coring for electrical in both north electrical rooms and began coring on south electrical room
· Began moving switchgear to the north electrical rooms to begin installation
· Continued running conduit for process equipment at Dryers 1 & 2
· Continued installing primary underground service to transformers (grounding only) on transformers 5-13 and started installation on transformers 1-4
Site Utilities:
· Continued installing water line from connection at City of Louisville main water line
· Continued saw-cutting paving in parking lot and installed city water approximately 95% of way across lot
Racetrack Piping:
· Received and installed four additional sections of racetrack trusses and piping
· Began installing flexible connections between sections of racetrack piping
· Started installing support hangers for branch lines from the racetrack piping
Log Conditioning Vaults
· Continued excavation for 16’ deep concrete holding tank for vault water and pumped rainwater that accumulated in excavation
Winston Plywood:
· Continued refurbishing and installing green-end equipment for both east and west lathe lines· Continued to receive used process equipment
· Continued construction of No. 3 Veneer Dryer (Dryer main framework)
· Completed press pit foundation modifications on Presses No. 1 and 3
· Continued press pit foundation modifications on Press No. 2
· Installed press columns, base, frame and platens on Press No. 1; Installed press columns, base, and top frame on Press No. 4
· Continued modifications to veneer lathes
Miscellaneous:
· Continued construction for primary power line to WP&V site