Monday, November 2, 2015

Winston Plywood Weekly Update 10-30-15



Foundations:
·         Removed forms for sander foundation
·         Connected sanitary sewer to west restrooms
·         Installed grating in boiler room drains trenches

Building:
·         Installed decking on Building 8
·         Started installing decking on Building
·         Continued installing standing seam roofing on Building 2 & 3, and started installing on Building 4
·         Continued installing louvers on west wall of Building 2 and started installing on Building 4
·         Started installing louvers on east wall of Building 3
·         Installed framed opening for 16’ door on Building 8
·         Continued installing personnel doors on Buildings 8 and 11
·         Completed installing edge angles for decking on Building 8
·         Continued installing wall sheets on west side of Building 1 (upper wall section)
·         Continued installing wall sheets on west side of Building 2
·         Started pressure washing structural steel framing
·         Began installing decking on Building 6A

Fire Protection:
·         Continued installing pipe bracings and supports throughout buildings
·         Received partial shipment of piping for Buildings 8 & 11

Hog Room, Glue Room, and Lathe & Chipper Deck:
·         Began erecting structural steel on Glue Room
·         Began installing glue tanks in glue room

Electrical:
·         Continued electrical rough-in for lighting and miscellaneous electrical in Buildings 1, 2, 3, 5 and 9, and continued rough-in for lighting in building 4 (Conduit and junction boxes)
·         Received shipment of cable tray for electrical installations
·         Started installing cable tray throughout the plant
·         Completed coring for electrical in both north electrical rooms and began coring on south electrical room
·         Began  moving switchgear to the north electrical rooms to begin installation
·         Continued running conduit for process equipment at Dryers 1 & 2
·         Continued installing primary underground service to transformers (grounding only) on transformers 5-13 and started installation on transformers 1-4

Site Utilities:
·         Continued installing water line from connection at City of Louisville main water line
·         Continued saw-cutting paving in parking lot and installed city water approximately 95% of way across lot

Racetrack Piping:
·         Received and installed four additional sections of racetrack trusses and piping
·         Began installing flexible connections between sections of racetrack piping
·         Started installing support hangers for branch lines from the racetrack piping

Log Conditioning Vaults
·         Continued excavation for 16’ deep concrete holding tank for vault water and pumped rainwater that accumulated in excavation

Winston Plywood:
·         Continued refurbishing and installing green-end equipment for both east and west lathe lines
·         Continued to receive used process equipment
·         Continued construction of No. 3 Veneer Dryer (Dryer main framework)
·         Completed press pit foundation modifications on Presses No. 1 and 3
·         Continued press pit foundation modifications on Press No. 2
·         Installed press columns, base, frame and platens on Press No. 1;  Installed press columns, base, and top frame on Press No. 4
·         Continued modifications to veneer lathes

Miscellaneous:
·         Continued construction for primary power line to WP&V site
·         Received a total of 3.6” of rain during the week