Setting forms, embeds, and rebar for Log Pro equipment foundations |
Buildings:
- Installed south wall sheets on Building 3
- Installed east wall sheets on south end section of Building 3 (adjacent to Building 6)
- Installed east side wall sheets on Building 4
- Installed south end wall sheets on Building 6
- Continued punchlists on Building 1, 2, & 3
- Completed trim-out and louver installation on Buildings 3 (North End), 6, 6A, 7, 8, and 11
Fire Protection:
- Continued installing hose station piping
- Continued installing drum-drips and drains for sprinkler systems
- Continued installing sprinkler systems in Buildings 6, 6A, 7, 8, and 11
- Placed charger pedestal concrete foundations at Lathes 1 & 2
- Continued electrical rough-in for lighting and miscellaneous electrical services
- Continued installing cable tray throughout the plant
- Continued hanging lighting fixtures in Building 2
- Continued setting electrical switchgear in north electrical room
- Continued pulling primary electrical feeders to north and south electrical rooms
- Continued running conduit for process equipment at green- end, dryers, presses, and dry-end
- Continued installing primary underground service to transformers 9-13 on north end and 1-4 on south end of plant
- Continued installing flexible connections between sections of racetrack piping
- Continued installing support hangers for branch lines from racetrack piping
- Continued installation and insulation of branch lines for water and air piping from racetrack
- Continued installing valving and instrumentation on boilers and water softener units
- Continued curing bottom slab in vault water holding tank
- Began excavation and placing No. 57 stone for vault foundations
- Began demo of forms and installed drainage piping around base of vault water holding tank
Log Pro Merchandiser:
- Began setting forms and embedded steel for foundations (adjacent to and east of Building 10)
- Continued refurbishing and installing green-end equipment for both east and west lathe lines
- Continued painting green-end equipment at lathes
- Continued to receive both new and used process equipment
- Continued construction of No. 3 Veneer Dryer
- Began setting electrical gear in south electrical room
- City of Louisville (MDR) installed power from corner of parking lot to final pole at southwest corner of site
- No rain recorded at the site this week
Excavation and placement of #57 stone for vault foundations |
Exterior wall on Buildings 1, 6, and 6A |
Power supply from Louisville Utilities to feeder poles at southwest corner of plywood plant |