Setting forms, embeds, and rebar for Log Pro equipment foundations

Buildings:
  • Installed south wall sheets on Building 3
  •  Installed east wall sheets on south end section of Building 3 (adjacent to Building 6)
  •  Installed east side wall sheets on Building 4
  •  Installed south end wall sheets on Building 6
  • Continued punchlists on Building 1, 2, & 3
  •  Completed trim-out and louver installation on Buildings 3 (North End), 6, 6A, 7, 8, and 11

Fire Protection:
  • Continued installing hose station piping
  •  Continued installing drum-drips and drains for sprinkler    systems
  •  Continued installing sprinkler systems in Buildings 6, 6A, 7, 8, and 11
Hog Room, Glue Room, and Lathe & Chipper Deck:
  •  Placed charger pedestal concrete foundations at Lathes 1 & 2
Electrical:
  • Continued electrical rough-in for lighting and miscellaneous  electrical services
  •  Continued installing cable tray throughout the plant
  •  Continued hanging lighting fixtures in Building 2
  •  Continued setting electrical switchgear in north electrical room
  •  Continued pulling primary electrical feeders to north and south  electrical rooms
  •  Continued running conduit for process equipment at green-  end, dryers, presses, and dry-end
  •  Continued installing primary underground service to  transformers 9-13 on north end and 1-4 on south end of plant
Racetrack Piping:
  •  Continued installing flexible connections between sections of  racetrack piping
  • Continued installing support hangers for branch lines from  racetrack piping
  •  Continued installation and insulation of branch lines for water  and air piping from racetrack
Boiler and Steam:
  • Continued installing valving and instrumentation on boilers and water softener units
Log Conditioning Vaults
  • Continued curing bottom slab in vault water holding tank
  •  Began excavation and placing No. 57 stone for vault foundations
  •  Began demo of forms and installed drainage piping around base of vault water holding tank
Log Pro Merchandiser:
  • Began setting forms and embedded steel for foundations (adjacent to and east of Building 10)
Winston Plywood:
  • Continued refurbishing and installing green-end equipment for  both east and west lathe lines
  •  Continued painting green-end equipment at lathes
  •  Continued to receive both new and used process equipment
  •  Continued construction of No. 3 Veneer Dryer
  •  Began setting electrical gear in south electrical room
Miscellaneous:
  • City of Louisville (MDR) installed power from corner of parking lot to final pole at southwest corner of site
  •  No rain recorded at the site this week
Excavation and placement of #57 stone for vault foundations


Exterior wall on Buildings 1, 6, and 6A

Power supply from Louisville Utilities to feeder poles at southwest corner of plywood plant