Buildings:
· Continued installing wall sheets and translucent wall panels on Building 2
· Began installing wall sheets on Building 4
· Installed roof decking on Buildings 6, 6A, and 11
· Began installing standing-seam roofing on Building 8
· Completed installing wall purling on Buildings 6, 6A, 7, 8, and 11
· Continued seaming roof panels on Buildings 3 and 4
Fire Protection:
· Continued installing pipe bracings and supports throughout buildings in preparation for system testing
· Continued installing hose station piping
· Continued installing underground fire loop, specifically along the north side of the existing main parking lot
· Tied in main loop to previously installed section of piping at northwest corner of plywood plant building
· Began erecting fire water storage tank
Hog Room, Glue Room, and Lathe & Chipper Deck:
· Continued erecting structural steel on Glue Room
· Finished installing glue tanks in glue room
· Placed concrete containment wall at west section of glue room
Electrical:
· Continued electrical rough-in for lighting and miscellaneous electrical
· Began lighting mock-up installation for review and acceptance for building lighting system
· Continued installing cable tray throughout the plant
· Installed electrical switchgear in center electrical room and began pulling primary feeders
· Continued running conduit for process equipment at green-end, dryers, presses, and dry-end
· Continued installing primary underground service to transformers 9-13
Site Utilities:
· Continued installing water line from connection at City of Louisville main water line; Made hot-tap connection onto existing city water line to connect plywood plant water systems
· Installed precast meter vault, meter base, and back-flow prevention system just west of fire water storage tank
· Installed final section of storm drain piping and tied into trench drain
Racetrack Piping:
· Received and installed six additional sections of racetrack trusses and piping
· Continued installing flexible connections between sections of racetrack piping
· Continued installing support hangers for branch lines from the racetrack piping
· Began installation of branch lines for process water and air piping from racetrack
Boiler and Steam:
· Installed exhaust stacks on three boilers
· Received and staged boiler DA tank
Log Conditioning Vaults
· Continued excavation for 16’ deep concrete holding tank and reached final grade
· Continued to pump accumulated water from rains throughout the week
Log Pro Merchandiser:
· Laid out boundaries of Log Pro equipment foundations
Winston Plywood:
· Continued refurbishing and installing green-end equipment for both east and west lathe lines
· Disassembled east lathe and painted main frames
· Continued to receive both new and used process equipment
· Continued construction of No. 3 Veneer Dryer (Dryer main framework and heating system)
· Continued concrete base and wall modifications in Press Pit No. 3
· Installed press platens in Press No. 4
· Continued to set layup line and finishing line equipment in place
Miscellaneous:
· Continued construction for primary power line to WP&V site – pulled overhead transmission wiring into place along power line
· Received 2.5” of rain through noon Friday of this week