Setting final section of Racetrack truss and piping
Foundations:
- Placed Lathe Charger pedestals at Lathes 1 and 2
Buildings:
- Completed installing upper wall sheets on west side of Building 1 and installed ground-level wall sheets on east side of Building 1
- Started punchlists on Building 1
- Completed valley metals on Building 3 (North and south sides at Buildings 7 & 8)
- Completed installing wall sheets and translucent panels on Building 4 (south end of plant)
- Completed installing wall sheets on north end of Building 5 and began installing louver trim-out (north end of plant)
- Completed installing insulation and roof sheets on Building 7
- Continued installing mezzanine decking for elevated slab in Building 8
- Completed installing standing-seam roof on Building 11
Fire Protection:
- Continued installing hose station piping
- Continued installing drum-drips and drains for sprinkler systems
- Completed installing underground fire loop, specifically along the north side of the existing main parking lot
- Continued erecting fire water storage tank (two remaining nozzles to install)
- Received two prefabricated fire system houses
- Pneumatically tested building sprinkler systems and repaired leaks
- Began installing sprinkler systems in Buildings 6, 6A, 7, 8, and 11
Hog Room, Glue Room, and Lathe & Chipper Deck:
- Continued erecting structural steel on Glue Room
- Continued finishing concrete walls around Glue Room
Electrical:
- Continued electrical rough-in for lighting and miscellaneous electrical services
- Continued installing cable tray throughout the plant
- Continued setting electrical switchgear in north electrical room
- Continued pulling primary electrical feeders to north and center electrical rooms
- Continued running conduit for process equipment at green-end, dryers, presses, and dry-end
- Continued installing primary underground service to transformers 9-13
Racetrack Piping:
- Completed installation of Racetrack trusses and piping
- Continued installing flexible connections between sections of racetrack piping
- Continued installing support hangers for branch lines from racetrack piping
- Continued installation and insulation of branch lines for water and air piping from racetrack
Boiler and Steam:
- Began installing valving and instrumentation on boilers
Log Conditioning Vaults
- Completed forms and rebar, and placed bottom slab in vault water holding tank
Log Pro Merchandiser:
- Drained and removed rain water from foundation area
Winston Plywood:
- Continued refurbishing and installing green-end equipment for both east and west lathe lines
- Began painting green-end equipment downstream from lathes
- Continued to receive both new and used process equipment
- Continued construction of No. 3 Veneer Dryer (Dryer main framework, heating coils, side plating, and fan drive motors)
- Continued concrete base and wall modifications in Press Pit No. 3
Miscellaneous:
- City of Louisville (MDR) installed power line across rail track to corner of WPV parking lot
- Received 4.8” of rain on Tuesday night and Wednesday of this week
|