·Excavated, placed reinforcing, and placed concrete for boiler room drain trenches ·Excavated, placed reinforcing, and placed concrete bottoms for Building 4 and for dryer drains ·Set edge forms for Building 4 ·Set edge forms for Slab-on-grade for Buildings 6, 6A and 7. ·Placed forms and rebar for chipper foundation in Building 10
Building:
·Continued placing insulation and standing-seam roof on Building 5 ·Installed roof insulation and vapor barrier on south end of Building 1 (hip-roof section) ·Began installing standing-seam roof on south end of Building 1 ·Completed installation of B-Decking on Building 3 (East side of building) ·Stood all perimeter wall columns on Building 2 at Column Line A (West wall of building) ·Received structural steel and B-decking for Building 4
Fire Protection:
·Completed installing sprinkler system in Building 1 ·Completed installing sprinkler system in Buildings 9 & 10 ·Performed layout for sprinklers in south end of Building 3 ·Received and staged materials for sprinkler system in Building 3 ·Began assembly of risers for currently installed systems
Electrical:
·Continued installing primary-power duct banks at transformers 1-4 ·Placed additional foundations for transformers and switches at transformers 1-9 ·Began grounding installing grounding for transformers and switches 1-9
Site & Utilities:
·Continued excavation, undercut, and backfill at site of new parking lot extension (south of existing main parking lot
RTO Relocation:
·Formed, placed, and finished RTO foundation slab ·Placed RTO support columns (12) ·Prepared area around the existing and new RTO foundations to allow for transport and setting of the existing RTO on new foundations ·Cut loose supports from RTO in existing location in preparation for moving to new foundations
Winston Plywood
·Continued refurbishing existing veneer dryers ·Received veneer stacker ·Established layout and control lines for installation of equipment at west lathe line