Foundations:
· Formed, placed, and finished concrete pit and walls for dry-hog foundations
· Continued erecting forms and rebar for green chipper foundation
· Continued forms and grading for new dryer foundations
· Excavated, placed rebar, and placed trench bottoms for drainage in boiler room area
· Placed additional grade beams in boiler room area
Building:
· Completed installing standing-seam roof on south end of Building 1
· Began installing standing-seam roofing on Building 3
· Staged structural steel and joists for erecting on Building 2
· Began installing beams and joists on Building 2 (West side of overall building)
· Began installing structural framing for wall louvers on north end of Building 5
· Installed interior framing between Buildings 9 & 10
· Began erecting structural steel framing for Lathe & Chipper Deck
Fire Protection:
· Completed installing sprinkler system in Building 5
· Began installing sprinkler system in south end of Building 3
Electrical:
· Continued installing grounding grid at transformers 5-13 (north end of building)
· Placed additional foundations for transformers 1-4 and switches at transformers at south end of building
· Continued installing primary power to transformers and switches at south end of building
· Began finish grading around transformers 5-13
· Continued block work on electrical rooms (southeast corner of Building 3)
RTO Relocation:
· Equipment mobilized to the site to begin relocation of the RTO to new foundation (start on August 24th)
Winston Plywood
· Continued refurbishing existing veneer dryers
· Received six loads of new Log Pro merchandising equipment and used process equipment